Select Committee on Environment, Food and Rural Affairs Written Evidence


Memorandum submitted by the Coleford Area Market and Coastal Towns Initiative Partnership (FL 105)

  This submission is on behalf of the above named organisation which is involved in development of a community led regeneration strategy for the Parish of Coleford, West Gloucestershire and its surrounding area.

FLOODING ISSUES DURING JUNE AND JULY 2007 AND THEIR EFFECT ON THE COLEFORD AREA

Executive Summary

  The flooding that happened during June and July 2007 is not without precedent in the Coleford area, but the speed and ferocity was not experienced to such a degree in such a short period of time.

  The problems faced in Coleford area are not unusual, being:

    (a)  Failure of government to accede to the needs for finance local authorities to enable local authorities to maintain and improve surface water drainage systems to cope with additional development within the area.

    (b)  Failure to identify responsibility for existing drainage ditches and culverts constructed in the Victorian era, leaving this liability to an unsuspecting public as being riparian owners. (Land Drainage Act 1991)

    (c)  Failure to allow sewage authorities to raise additional funding to deal with known problems of ingress of surface water into the foul drainage system and to plan for the future to ensure this does not continue in the future.

  All of these problems have resulted in an infrastructure that, at best, did not satisfy the needs of the community before extensive development that has taken place over the past 50 years.

  Local authorities have worked together well in providing emergency care but previous attention to the above issues would have meant that the emergencies could have been averted.

Coleford, West Gloucestershire: Flooding Problems 2007

  1.  Topography: The area of land covered by this report is a large basin with shallow top-soil on a clay bed leading to a narrow winding valley. Previous heavy rain led to the upper soil levels being saturated and the lack of ability for further penetration to lower levels. Levels from the rim of the basin begin at over 700 feet above sea level to a level at the point of entry into the River Wye of more than 200 feet above sea level. None of the area can therefore be classed as a flood plain in the normally accepted sense.

Approximately 1 inch of rain falling in the area produces in the region of 45 million gallons of water draining through a narrow valley, the head of which is near the town itself. On 25th June alone 59 properties in the small town were reported as being affected, that quantity having fallen in a few hours.

  2.  Existing land drainage: The drainage system comprises Victorian culverts running for a distance over more that 1.5 miles. They are fed by the confluence of small streams each entering higher in the valley. The culverts join together in the town centre and the main run varies in size as it passes through the area, due to the many repairs carried out over a long period of time by various land owners, often without consideration of the effects on other properties. Surface water run-off from most properties and developments finds its way into this system resulting in a huge build-up of hydraulic pressure and collapse of parts of the culverted system. In addition springs are evident as the land slopes downwards running through farmland and small hamlets adding to the flow where the culvert becomes a torrent in open stream sections. The least of the worries are that bating could assist in some areas whilst wholesale repairs and renewal may have to be the ultimate solution in others.

  3.  Sewer systems: Some properties discharge surface water into the sewers resulting in surcharge of that system and consequent spillage onto the streets of the town and some local farmland. Urgent inspection of which properties affect the situation is needed but property owners are reticent to allow dye testing and this will be a lengthy process.

  4.  Road drainage: The majority of existing road drains are of the "chute" variety that allow all debris to enter the system resulting in the blockage of drains. Where "sump" type gullies have been installed there is a large build up of debris and silt that is normally only cleaned out once a year except when emergencies arise. This is due to the lack of revenue available for such work.

  5.  Action taken: A Public Meeting was held on Saturday 21 July, following which a Forum has been set up through the Partnership and comprises representatives of the Statutory Authorities, Parish, Town and District Councillors and Partnership volunteers. The Forum has discussed the existing problems and all bodies are of the opinion that a large sum of money is required to enable proper surveys to be undertaken resulting in a well formed plan for provision of proper drainage that will cope with existing problems and prepare for the future threats of further climate change. Financial help is therefore urgently needed to avoid any further repetition of the problems so frequently experienced in this rural area.

Coleford Area Market and Coastal Towns Initiative Partnership

September 2007





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 7 May 2008