Memorandum submitted by Gloucestershire
Constabulary (FL 110)
GLOUCESTERSHIRE WATER EMERGENCY 2007
CHIEF CONSTABLE'S
MEMORANDUM
We have aimed to make the document as accurate
as possible, however, due to a number of independent reviews and
de-briefs being conducted by other agencies, information contained
within the document may need further clarification as detailed
reports become available.
1. EXECUTIVE
SUMMARY
1.1 Operation Outlook was the multi-agency
response to the emergency resulting from the unprecedented flooding
in Gloucestershire in July 2007 which was the largest peacetime
event this Country has seen in terms of complexity, duration and
those affected. Gloucestershire Constabulary led the Strategic
Co-ordinating Group and the Gold, Silver and Bronze Command structure,
co-ordinating the response to the emergency. Much of the success
of the operation can be attributed to the investment made by Gloucestershire
Constabulary and the Gloucestershire Police Authority in the Gloucestershire
Tri-Service Emergency Centre (GTEC), and Police Headquarters.
These facilities ensured seamless communication between the emergency
services as the events of 20th July 2007 unfolded, by providing
the platform for the Gold and Silver Command arrangements and
accommodating representatives from each of the agencies concerned.
The design of the HQ, opened in December 2005, to accommodate
a Strategic Co-ordination Centre (SCC) ensured effective lines
of communication and rapid decision making to meet the challenges
of the emergency situation.
1.2 Also key to the success of the operation
was the work that had previously been undertaken by the Local
Resilience Forum (LRF) and its constituent members. The extensive
planning, training and exercise regimes delivered by the LRF ensured
that senior representatives and their staff were familiar with
the concept of emergency planning and in particular the SCC and
associated arrangements. These measures together allowed the response
to the emergency to be rapidly established and successfully managed.
The plan to regionalise the fire control centre at Taunton, should
be revised to allow for continuation of the Tri-Service facility
at Gloucester. This background of partnership and investment has
also been demonstrated by the County gaining "Beacon Status"
for emergency planning.
1.3 The Gloucestershire Strategic Recovery
Co-ordination Group is a multi-agency group comprises representatives
from all the key agencies concerned in the post-emergency recovery
work. The Chair of the LRF, a Constabulary Chief Officer, is a
member of this Group to ensure that the distinction between recovery
and resilience issues is clear and the work co-ordinated.
1.4 A number of issues arising from the
flooding clearly need addressing and are brought to the attention
of the Committee:
All agencies need to re-visit their
contingency plans and re-evaluate worst case scenarios and plan
accordingly.
The resilience of utilities across
the Country needs to be reviewed and addressed as a matter of
urgency.
National and regional Utility companies
need to engage at a local level with Local Resilience Forums so
as to identify key local risks and confirm contingency arrangements.
There must be an increased capacity
to supply basic needs to communities in the event of an emergency.
There needs to be a strategic reserve
of light, heat and sanitation Countrywide.
The Tri-Service Emergency Centre
should be maintained and strengthened through continual commitment
and investment.
The County and Government need to
consider fully the impact of continuing to build new homes on
flood plains.
There should be a specific requirement
for national agencies to attend Strategic Co-ordinating meetings
when so requested and to ensure consistency of representation.
The importance of maintaining county-based
structures needs to be recognised as these represent a suitably
strategic organisation, but one, which has local roots and knowledge.
There should be a review of national
reserve emergency supplies of food, water, feeding and cooking
amenities.
Gloucestershire Constabulary is a
strategic Force.
1.5 Most of these considerations are relevant
at a national level, and therefore there should be a national
review of contingency planning in terms of contingency reserves
of basic utilities including food, water, shelter and sanitation.
These reserve provisions would be available in the event of threat
of disruption to basic living requirements from terrorism or environmental
threat, as well as from conventional or CBRN attack in the event
of war.
1.6 There were three fatalities that are
all subject to a Coroner's inquest. The Chief Constable would
like to reaffirm his sincere condolences to family and friends
of those who lost their lives.
2. INTRODUCTION
2.1 Prolonged heavy rainfall resulted in
widespread flash flooding across Gloucestershire which began on
Friday 20th July with what the Met Office had warned would be
"a major rainfall event".
2.2 Early forecasts released by the Met
Office at 0554 hrs on Friday 20th July indicated that "rain
will be persistent and locally very heavy at times throughout
the day, with "fresh north east winds". A precipitation
forecast issued at the same time stated that "current indications
from models imply that the highest rainfall totals will probably
be over the Welsh mountains and more south eastern areas of the
region. The rain should weaken and become more showery in nature
overnight and through Saturday".
2.3 On the basis of the Met Office forecast,
the Constabulary had not issued any additional information regarding
the weather conditions expected for Friday 20th July. The earliest
indications of the evolving emergency came from Ambulance, who
were beginning to have difficulty in responding to their 999 calls.
Silver control was established at 1529 hrs on Friday 20th July
as a consequence of the changing events.
2.4 The report also indicated that a heavy
rainfall warning was in force at the time of issue. It would appear
that there was no indication of the unprecedented amount or duration
of rainfall that eventually fell on the County. It is interesting
to note that whilst the best intentions of the forecast indicated
the anticipated precipitation levels, there was no indication
of the effects this rainfall would have on already fully-saturated
ground.
2.5 Approximately 1,600 calls were made
to the Constabulary in the first eight hours of the crisis, and
it soon became apparent that this was not just a major rainfall
event but also a flooding crisis. Many homes across the County
were directly affected by flooding, and around 350,000 households
were without drinking water for 17 days after the Mythe water
treatment plant at Tewkesbury was inundated by the floods.
2.6 Gold Command was initiated on the evening
of Friday 20th July at County Police Headquarters and Operation
Outlook was the name given to the multi-agency response to the
flooding and associated issues in Gloucestershire. The emergency
phase finally ended with the return of drinking water supplies
on 7th August.
2.7 Preliminary assessment by the Centre
for Ecology and Hydrology (CEH)[37]
indicates a combination of factors contributed to the flooding.
Exceptionally high rainfall levels had resulted from the jet stream
following a route further south than usual, and the high pressure
cell from the Azores that would usually influence our weather
bypassing Britain. These phenomena, combined with a sustained
series of low-pressure systems over the preceding 12 weeks, had
added to the unprecedented rainfall levels, indeed the May and
June rainfall total was the highest on record for Britain by a
substantial margin.
2.8 In a "normal" summer flood
risk is low due to dry ground through which water can drain away.
However, this year due to the record levels of rainfall and flooding
in June, the soil was so saturated it could not cope with the
rainfall of July. In addition urban drainage systems were overwhelmed
by the intense rainfall resulting in localised "flash floods".
2.9 The role of anthropogenic carbon as
the root cause of climate change has been cited as an explanation
for these "freak" weather patterns. Other theories would
contest climate change is simply part of a natural global cycle
on which human activities have little impact. Such debates are
beyond the scope of this report, however what is clear is that
the weather leading to the July flooding could become more frequent
no matter what the reason behind climate change.
2.10 The events of the two week water emergency
were unprecedented and Gloucestershire emergency services, County
and District Council as well as other agencies, responded with
flexibility and energy to ensure emergency supplies and the restoration
of water.
2.11 These were unprecedented events however
they are no longer, and all agencies therefore need to use the
benefits of experience to protect the County.
3. FLOODING IN
GLOUCESTERSHIRE
3.1 Historically Gloucestershire is no stranger
to flooding. Flooding is a regular part of life in many parts
of Gloucestershire, but 1947 is the benchmark year in living memory
for every subsequent flood. Comparisons with 1947 are difficult
but it seems likely that the overall effects of the 2007 floods
were substantially greater. Changes in landscape cannot be ruled
out as contributory factors at this stage. This would be for other
enquiries such as the Pitt Review to determine.
3.2 The Gloucestershire emergency differed
from Humberside and Worcestershire, as there was no loss of water
supply or power outage in these areas. The water supply for the
majority of the County was lost for 9 days and drinking water
for even longer. Electricity was lost in parts of the County and
there was the threat of loss to the Whole County, parts of Bristol
and Worcestershire. This was the largest peacetime emergency to
have affected this Country, in terms of complexity, duration and
affects.
3.1. The Severn Corridor[38]
3.1.1 The Severn, after rising in the Welsh
Hills, flows generally north-eastwards into England before turning
southwards to reach the sea through the Bristol Channel. The basin
is generally sparsely populated (approximately 1.5 million): the
majority of the population lives in the larger towns. Riverside
towns on the Severn include Llanidloes, Newtown, Welshpool, Shrewsbury,
Ironbridge, Bridgnorth, Bewdley, Worcester, Upton-upon-Severn,
Tewkesbury and Gloucester.
3.2. The Upper Severn
3.2.1 This area covers the upper reaches
of the River Severn from its source on Plynlimon in Powys to its
confluence with the River Perry upstream of Shrewsbury in Shropshire.
3.2.2 There has been flood prevention work
on the upper and middle reaches of the basin but this has not
been extended to the lower sections.
3.2.3 There was extensive flooding in the
Severn Uplands area in 1998, 1999 and Autumn 2000.
3.3. The Middle Severn
3.3.1 The Middle Severn, covers the length
between the Perry and Teme confluences, a distance of 119 km.
Here the river drains a catchment that lies mainly within the
counties of Shropshire and Worcestershire and covers an area of
2,634 km2.
3.3.2 The River Severn runs broad and deep
between fairly high banks over a clay bed. In the upper catchment
there are two large impounding reservoirs, Llyn Clywedog and Llyn
Vyrnwy. The river regularly floods in winter, in some reaches,
up to 6-8 times a year.
3.4. Severn and Avon Vales
3.4.1 The area of Severn and Avon Vales
is centred on the broad flood plain around the confluence of the
Rivers Severn and the Warwickshire Avon.
3.5. River Severn
3.5.1 From the Teme mouth, just below Worcester,
to the Gloucester Weirs, the 46 km length of the Severn drains
an area of about 1000 km2. The only other large town is Tewkesbury
although there are numerous smaller riverside towns and villages
such as Kempsey, Severn Stoke and Upton-upon-Severn.
3.6. River Avon
3.6.1 The River Avon catchment covers much
of the County of Warwickshire and parts of Leicestershire, Northamptonshire,
Gloucestershire, Worcestershire and the City of Coventry. The
head of the river is near Naseby in Northamptonshire and it meets
the Severn at Tewkesbury. The Avon is the longest tributary of
the River Severn (179 km).
3.7. Areas at Risk from Flooding
3.7.1 The River Severn has been subject
to several high profile floods during 1998 and 2000. The main
urban areas affected by flooding on the Severn are Shrewsbury,
Ironbridge, Bewdley, Worcester, Upton-upon-Severn, Gloucester
and Tewkesbury. However, in the Worcester to Gloucester area there
are more properties at risk of flooding outside the towns than
found within the main urban areas.
3.7.2 There are indications to suggest that
in recent years flooding has occurred in areas not previously
at risk, particularly on tributaries. Flooding may be getting
worse, or the catchment may be experiencing an abnormally wet
period, or it may be returning to normal after an abnormally dry
period.
3.8. The Tidal Effects of the Severn[39]
3.8.1 Surges of water in areas covered by
flood water are often unpredictable due to, amongst other factors,
the undulation of the ground over which the water flows. There
is also the issue of flooding in the water table caused by the
saturation of the ground that may equally be prone to flooding
despite being some distance away from rivers or water courses.
Comment to this effect was made by a representative from the Environment
Agency at a GOLD Command meeting reinforcing the unpredictable
nature and circumstances in which various types of flooding can
occur.
3.8.2 The Severn estuary is subject to the
second highest tidal rise in the world. The basic geology and
geomorphology of the Severn estuary is complicated but the combination
of the underlying geology and geomorphology and the exceptional
tides and estuary river flows regularly produces the effect known
as the Severn Bore. At a time of inland flooding, the substantial
effect of flood water, with the incoming water of the tide, aggravates
the effect of flooding in the Gloucester flood plain area (Alney
Island, Castlemeads and Gloucester Quay) reducing the outward
rate of flow from the inland flooded area. The Walham electricity
sub-station is situated near Alney Island and the Castlemeads
electricity sub-station is located on Alney Island.
3.8.3 Recent effects of planning and building
are not within the scope of this report, nor is it within the
competency of the police to comment upon relatively recent planning
decisions and building operations. However, it must be said that
since the benchmark flooding of 1947, there has been the completion
of the Gloucester northern bypass, built on a causeway, as well
as substantial residential and business development in the flood
plain areas. Many households, together with the utility sites
at Castlemeads, Walham and other premises were affected by water
rising from the saturated ground in the flood plain.
3.9. Overview of Flooding in Severn and Avon
Basin
3.9.1 The low-lying areas near the rivers
Severn and Avon suffered from excessive flooding in light of the
events of 20 - 21st July and this led to the search and rescue
phase of Operation Outlook.
3.9.2 During this phase, a fatality occurred
which is subject to a Coroner's inquest. Two other fatalities
occurred on the night of Wednesday/Thursday 25-26th July at Tewkesbury
rugby ground when two individuals were attempting to pump out
the clubhouse. These fatalities are also subject to a Coroner's
inquest.
3.9.3 The situation then stabilised for
several hours before flood water moving in volume from the upper
and lower Severn met water seeking to flow from the Avon, at the
confluence of the two rivers at Mythe Bridge.
3.9.4 The water appears to have backed up
and overflowed at Mythe Bridge, flooding the nearby treatment
works, the intakes of which were also subject to excessive pressure
from an exceptional flow of water from the Severn.
3.9.5 This water then moved in volume to
affect the Alney Island, Castlemeads and Gloucester Quays areas,
peaking at approximately 2200 hrs Monday 23 July.
3.9.6 The recess of this water was delayed
by the twice-daily effect of the incoming tide.
3.9.7 In addition, low-lying areas near
the river were subject to rising water from the saturated ground.
3.9.8 It must be noted, however, that the
Environment Agency, briefed Gold Command to the effect that the
detailed consequences of the general movement water across the
flood plains is extremely difficult to predict because of the
effect of surges across undulating ground.
3.9.9 At no point until 22 July was Gold
Command alerted to the excessive potential of flooding at Mythe
or Walham.
4. MILITARY AID
TO CIVIL
POWERS (MACP) AND
FORMAL REQUEST
FOR MILITARY
AID FOR
THE CIVIL
AUTHORITIES (MACA)
4.1 Prior to a formal request for MACA,
Royal Air Force (RAF) search and rescue helicopters were deployed
during the initial response to the emerging emergency on Friday
20th July. There was therefore a military presence in Gloucestershire
from Friday evening. The request for MACP came from the Silver
Co-ordinating Group as a result of the escalating nature of the
situation. Also as part of the initial response, military liaison
officers were an integral part of the Group. Lead elements from
HM Coastguard and Severn Area Rescue Association (SARA) were also
available for deployment from an early stage.
4.2 As an inland County the emergency services
had not anticipated nor foreseen the use of search and rescue
aircraft as part of incident response. Therefore ground to air
communications, with military aircraft, was not an established
facet of the Silver or Gold Command arrangements. A means to communicate
with the RAF helicopters had to be set up as a separate system
by the military and this was enhanced by the early contributions
of the military liaison officers. This has been noted as a future
modification to our own systems of communication. The rescue phase
of Operation Outlook constituted the largest search and rescue
operation mounted in peacetime by the RAF.
4.3 Following the formal request from the
Chief Constable for MACA, on Sunday 22nd July, the contribution
and role of the military in this emergency cannot be under- estimated.
A critical function performed by the military aid throughout the
emergency was the co-ordination and development of a logistical
plan for distribution of water, as well as assisting in the delivery
of bulk water, which included bowsers and bottled water to distribution
points across the County. For the duration of the emergency, all
military aid remained under the direct command and control of
Gold Command.
4.4 Military aid was also vital in providing
engineering expertise together with lift and shift capacity to
build temporary defences at Mythe and Walham.
4.5 Military aid was released as soon as
the situation had stabilised and there were suitable resources
in place to maintain the basic provisions for the people of Gloucestershire.
4.6 Military aid formally ceased on 31 July,
when full responsibility for the distribution of emergency water
supply was formally handed over to the County Council and STW.
5. THE LOSS
OF WATER
AND THREATENED
LOSS OF
ELECTRICITY
5.1. Mythe Water Treatment Works
5.1.1 Mythe is fundamentally the single
source of water supply for Cheltenham, Gloucester and Tewkesbury.
The water treatment works was established 100 years ago and currently
produces 120 mega litres of water for Gloucestershire every day.
Gold Command was informed at 0900 hrs on Sunday 22nd July that
at 0200 hrs the same day, the Mythe had been breached and the
site evacuated. There appears to have been no early warning or
indication other than a request made at 0002 hrs on Sunday 22
by Fire to arrange for the urgent attendance of an engineer at
the treatment plant.
5.1.2 This was approximately seven hours
after flood water had entered the treatment works. Gold Command
had no prior warning of the likelihood of this being a risk of
happening, from any of the respective agencies. STW estimated
that it would take between 7 and 14 days to restore supply, an
estimate that proved to be accurate.
5.1.3 Gold Command encouraged a more prompt
restoration of water supply, but, due to major engineering works,
this period could not be foreshortened, this was not possible.
The engineering challenge was considerable and STW should be complimented
on completing the restoration of the equipment in 8 days from
disruption of supply. The disruption to the supply of water, however,
left Gold Command in the unprecedented situation of having to
supply 350,000 people with water for drinking, cooking and basic
sanitation purposes.
5.1.4 The challenge was unprecedented in
modern times, but relatively quickly Gold Command was able to
ensure approximately 6 million litres of drinking water was distributed
every day, 3 mega litres from bottled water and 3 million from
bowser supplies. The initial bowser distribution process developed
by STW proved ineffective because of there being initially too
few bowsers to cover the area affected and inadequate numbers
of small, rigid tankers to transfer water from bulk tankers to
locally distributed bowsers. With the assistance from Gold Command
and the Military the distribution problem was effectively resolved
by Thursday 25 July and bowsers were then replenished three times
daily.
5.1.5 It is important to note that there
were no adverse effects reported in relation to people going thirsty
or dehydration, inability to cook and boil water, or basic sanitation
problems. Essential users, including hospitals, were identified
early on and supplies maintained throughout. The County and District
Councils and their network of volunteers ensured that supplies
of water were provided to vulnerable individuals and households.
5.1.6 However, it is important to note that
supplies to 350,000 people in Gloucestershire were only available
for the duration of disconnection through bottled water and bowsers.
This was despite attempts to provide alternative mains water solutions
throughout the emergency. There was some initial panic buying
of bottled water on Sunday 22 July, although residual mains water
continued to flow to some parts of the County until Monday. Panic
buying ceased by Monday 23 July as a result of commercial supplies
running out but being replenished by the first emergency supplies
of bottled water. Emergency supply centres were set up across
the County manned by various combinations of STW officials, various
District and County Council officials and volunteers overseen
by police personnel. There were few incidents of anti-social behaviour
and damage to bowsers.
5.2. Walham Electricity Sub-station
5.2.1 The threat to Walham sub-station,
operated by National Grid, was of a critical and extreme nature.
The sub-station supplies electricity from the National Grid to
600,000 people in Gloucestershire, effectively the whole of the
County, as well as to areas in the South Midlands and South Wales.
Alternative supplies could have been found for South Wales but
not for Gloucestershire.
5.2.2 The potential threat to Walham was
identified and driven by Gold Command. At 1007 hrs on Sunday 22
July at the Gold meeting, the Gold Commander tasked the Environment
Agency to contact Central Networks to determine any future problems
with supply of electricity from the Walham sub-station. At the
same meeting, the Environment Agency was also tasked to provide
maps of the likely flooding in and around the Quay, Hempsted,
Alney Island, Castlemeads and Walham.
5.2.3 There was no early warning or indication
from the National Grid or the Environment Agency as to the potential
risks to Walham of flooding and the subsequent loss of electricity
to the County and surrounding areas.
5.2.4 As previously noted, the sub-station
is situated on a flood plain near to the River Severn and has
been there for many years. The surrounding area is routinely flooded
but not to the extent as to place the sub-station under threat.
Therefore the threat that was reported to Gold Command on Sunday
22 July was not only unexpected but also unprecedented. A representative
from the National Grid was subsequently present in Gold Command
for the duration of the emergency.
5.2.5 The risks were immediately apparent
to Gold, as loss of electricity would have meant that households
could not have boiled water, cooked food, including baby food,
and provide basic heating. Furthermore, essential services within
the County would have been reliant on generators and sewage would
not have been pumped. Street and domestic lighting would have
been lost for the duration of the emergency.
5.2.6 It was anticipated that the loss of
electricity could be for up to 3 weeks. Gold Command therefore
made an immediate decision to ensure that barriers and pumps were
in place to protect the sub-station and contingency arrangements
made to ensure emergency supplies were provided. However, the
primary intent was protecting the integrity of the sub-station.
At no time were plans developed for the evacuation of the County.
This would have been an inappropriate reaction.
5.2.7 Emergency barriers were provided from
the Bristol/Bath area by the Environment Agency (EA) and these,
reinforced by sandbags, were constructed throughout the remainder
of Sunday 22 and Monday 23 July using civil and military personnel.
Throughout, a major pumping operation continued using nationally
supplied equipment under the direction of Gloucestershire Fire
and Rescue Service. The critical point was high water on the evening
of Monday 23 July for which the prediction from the EA indicated
that the measures already in place would be sufficient to save
the plant, and this proved to be the case. High water passed at
2200 hours without the plant being compromised. Estimates vary
as to the precise margin of safety but at no point was it two
inches from the top of the external emergency barriers. There
is no doubt that the major pumping operation and the huge effort
of building the Hesco barriers saved the Walham electricity sub-station
from being lost, however, it must be noted that the critical risk
to the sub-station came from an internal threat from rising flood
water which came through the ground as a result of saturation
and the rising water table, and not as a result of the external
Hesco barriers being overwhelmed by flood water. It is a fact
that internal rising flood water came within 2 inches of the base
of the switching gear. This factor must be a vital consideration
in future contingency planning to protect the utility sites from
flooding.
5.3. Castlemeads Electricity Sub-station
5.3.1 The Castlemeads sub-station, operated
by Central Networks, transfers electricity to the south Gloucester
City area. Therefore, resources and effort were primarily focussed
at Walham. Gold Command made the decision to switch off the sub-station
to prevent substantial damage to the switching gear when it became
threatened by the flood water. Power was subsequently lost to
a small percentage of the population of Gloucester for a few hours
on Monday 23 July, but this prompt action allowed power to be
resumed the following day re-supplying the majority of homes and
businesses affected, once the flood water had receded.
5.4. Cooperation with Utility Companies
5.4.1 Severn Trent Water, National Grid
and Central Networks all provided staff to Gold Command throughout
the emergency. It was, however, evident that the situation exceeded
previous experience and contingency planning, and solutions had
therefore to be dynamically developed in cooperation with the
Police, Fire, Military, Health and other participating agencies.
This included the provision of Hesco Bastion defences at the Mythe
and Walham to limit the effects of future flooding. It should
be noted that STW and electricity company representatives worked
hard to provide solutions to the problems with which they were
confronted. It should also be noted that the re-commissioning
of the Mythe Treatment Works and the re-supply of the Gloucestershire
mains networks were significant feats of engineering.
5.4.2 The Hesco Bastion barriers at Mythe
and Walham are of a temporary nature, and are intended to inhibit
the lateral flow of water across the sites. These will not inhibit
rising water from saturated ground, or water pressure on the waterworks'
intakes. It is for the Utilities themselves to address these issues.
Central Networks has already provided enhanced external barriers
for protection at Castlemeads.
6. CONTROL AND
CO-ORDINATION
6.1. Local Resilience and Planning
6.1.1 Gloucestershire has invested heavily
to ensure the infrastructure is in place for emergency management.
This has undoubtedly secured the successful response to the flooding
emergency. However this same level of investment is not replicated
across the Country, and it is not clear that other parts of the
Country could have managed a similar emergency as efficiently
and effectively.
6.1.2 The Beacon Scheme recognises excellence
and innovation in local government. The Gloucestershire local
authorities successfully bid for and were awarded Beacon Status
in March 2007 in recognition of the way they plan for and respond
to major emergencies. Gloucestershire was one of only 7 authorities
to achieve the award out of 29 applications.
6.1.3 Factors in the successful bid were
partnership working and community involvement. County and District
Officers regularly plan, train and exercise together and the judges
were particularly impressed with the way they worked with partner
agencies in the LRF to ensure that they can respond effectively
to any emergency. The Gloucestershire local authorities also have
a well established but unique volunteers accreditation scheme,
which ensures that suitably trained volunteers are available to
assist in caring for those affected by an emergency and they are
also recognised as a centre of excellence for Business Continuity.
6.1.4 The Gloucestershire LRF was created
in 2005 as a replacement for the County Major Incident Co-ordinating
Group that had been working together since its' formation in 1989.
This was as a direct result of the Civil Contingencies Act 2004,
which laid statutory duties on certain agencies to plan, train,
exercise and respond to Major Incidents in a co-ordinated fashion.
The agencies, referred to as category 1 responders, include the
Police, Fire Service, Ambulance Service, Health Services, Local
Authorities, Maritime and Coastguard Agency and Environment Agency.
6.1.5 Further agencies make up what is known
as category 2 responders and include the utilities and other companies
concerned with the national infrastructure, such as the Highways
Agency. It was evident as a consequence of the events created
by the emergency that the utility companies were unfamiliar with
the Gold, Silver and Bronze structure of incident management and
response.
6.1.6 A Constabulary chief officer is currently
the Chair of the LRF. The LRF has a long history of engagement
and commitment to ensuring emergency preparedness within the County.
Joint planning, training and exercising has enabled successful
response to the recent flooding events and previous chemical incidents
such as the fire at Andoversford. LRF Gold awareness training,
which has been delivered over a number of years, enabled executives
and support staff from Category 1 responders and the military
to be familiar with the Strategic Co-ordinating Centre accommodation
and processes.
6.1.7 It became clear as the emergency progressed
that Severn Trent Water (STW) needed help. STW had intended to
use the bowsers as the sole solution for water distribution. Their
experience to date had been limited to short-term disconnections
and localised distribution for short periods of time. The STW
plan soon collapsed and it became clear they had neither the infrastructure
nor resources to maintain sufficient supplies of drinking water
to those affected by the emergency. On the Chief Constable's instigation,
two senior officers from West Midlands Police were deployed to
STW's headquarters, in Coventry, in support of the operation,
and the emergency response from STW began to greatly improve.
Although not a statutory responsibility, the police alongside
the military assisted in the distribution of bottled water, and
the staffing of a centralised water distribution point at Cheltenham
Racecourse. This facility delivered approximately 3 million litres
of bottled water to the County daily.
6.1.8 Engagement of and communication with
communities was recognised as being an essential pre-requisite
to a successful operation. This was achieved through the tasking
of Police Safer Community Teams that remained in place throughout
the emergency and through the use of Independent Advisors. These
measures ensured the feelings and difficulties within communities
were understood and addressed and enabled the monitoring of any
community tensions and an appropriate strategic response from
Gold.
6.2. Gloucestershire Constabulary County Headquarters
6.2.1 The Constabulary was successful in
securing £17 million PFI funding for a purpose built headquarters
that was able to transform in part into a Strategic Command Centre
(Gold). The building was completed in December 2005. The events
of July/August 2007 have highlighted the return on investment
identified within Vision5 and continuing into Vision2010, the
Constabulary's over-arching strategic plans.
6.3. Gold Command Suite and Local Emergency
Centre
6.3.1 The Gold Command Suite is a permanently
established space that provides the nucleus for the Strategic
Co-ordination Centre (SCC) to immediately establish a control
centre in the event of a major incident or event.
6.3.2 The Gold Command Suite has excellent
and immediate communications systems, including IT, telephony,
terrestrial and non-terrestrial television and radio facilities
which are core to Gold Command.
6.4. Strategic Co-ordination Centre Overlay
6.4.1. Outside of the Gold Command Suite
itself, the SCC facility is activated when there is a major incident,
utilising accommodation that is used on a daily basis for a lower
priority need. The size and nature of the overlay is dependent
on the particular incident, but in all cases it is able to rely
upon excellent and immediate communications.
6.4.2. The command structure adopted in
responding to the emergency situation is the well-recognised and
established Gold, Silver and Bronze system. These are respectively
the Strategic, Tactical and Operational levels at which a situation
is dealt with. This structure was adopted for the emergency.
6.4.3. In an emergency situation requiring
a multi-agency response it is well established, and laid out in
the Association of Chief Police Officers (ACPO) Emergency Procedures
Manual, that it is the responsibility of the Police to establish
and chair the Strategic Co-ordinating Group. This occurred.
6.4.4. One of the key factors in the successful
response to the emergency is the investment that Gloucestershire
has made in the Gloucestershire Tri-Service Emergency Centre (GTEC).
This accommodates all the emergency services in the same building
and allows for excellent communication and effective co-ordination
of resources in response to the emergency. Without doubt the absence
of GTEC would have led to a delayed and potentially chaotic initial
response to the emergency. As it was, GTEC ensured that co-ordination
between the three front line emergency services was on the "front
foot" early in the emergency.
6.4.5. Gold was initiated at 18:00 hours
on Friday 20 July. The formation of the Strategic Co-ordinating
Group brought together key agencies who could draw on their combined
resources to address the dynamically developing situation, and
quickly make strategic decisions that were pragmatic and co-ordinated
the actions of all agencies. In the absence of this set up cooperative
working is hindered, communication is strained and duplication
of efforts inevitable.
6.4.6. The SCC worked extremely effectively
in response to the emergency and this can be attributed in the
main to a number of factors.
6.4.7. Firstly the police officers and police
staff of Gloucestershire Constabulary showed professionalism,
willingness, enthusiasm, dedication and flexibility in support
of the operation. Many of whom worked far beyond expectations,
and these outstanding efforts should be recognised.
6.4.8. Secondly, Gloucestershire has a strong
history of partnership working that extends long before the introduction
of the LRF. Training, planning and exercising with our partners
has developed strong relationships, and provided a familiarity
with the concepts of emergency management and the facilities available.
This ensured the establishment of the Strategic Co-ordinating
Group was rapid and with roles and responsibilities clearly understood,
enhancing the effectiveness of the response.
6.4.9. Thirdly, the Police Head Quarters
(HQ) provides a purposely-designed Strategic Co-ordination Centre
(SCC) to accommodate agencies. This set-up places all the agencies
on an open plan floor adjacent to the Gold Command Room. This
is flexible and can easily be expanded to accommodate other additions
to Gold. Each person is provided with access to a telephone, computer,
Gold e-mail addresses and the Gold Messaging Application (GMA)
(software that records actions and policy decisions by the Strategic
Co-ordinating Group). Without this purpose-designed accommodation
the response to the emergency would be fragmented and lack the
same high level of co-ordination, leading to a hindered emergency
response.
6.4.10. Fourthly, the County has one of
only three Tri-Service (Police, Fire and Ambulance) emergency
control centres in the Country (GTEC). This was opened in 2002.
This routinely ensures co-ordinated management of incidents involving
the three services, and enhanced Silver Command facilities which
enables early instigation of joint command management. This was
evident in the early hours of the emergency on 20 July, and enabled
the three County emergency services to get on the "front
foot" and stay there.
6.5. Silver Command
6.5.1 On Friday 20 July at 15:29 hours a
Silver Command was set up at the GTEC, again in accommodation
designed for this purpose, as the impact of the torrential rain
brought Gloucestershire's transport infrastructure to a standstill.
Informal dialogue and co-ordination had taken place as the emergency
evolved due to the close proximity of on duty staff from police,
fire and ambulance.
6.5.2 The management of the emergency demonstrated
that Gloucestershire Constabulary is a strategic force, having
both the capacity and capability to deal with what has been described
as the "largest peace time operation this Country has seen".
The Constabulary also continued with daily business, for example
in dealing with a murder that occurred on day four of the operation.
6.5.3 Non-essential staff were sent home
to preserve utilities at HQ. By the end of the first week police
staff who do not normally face the public were being used in a
completely different role in water distribution. Officers and
other essential staff were placed on 12-hour shifts for the duration
of the emergency. The dynamic use of resources gave Gloucestershire
Constabulary the flexibility that was required to deal with the
emergency without calling for mutual aid.
6.5.4 The de-brief process and review of
the Operation Outlook is still at this stage work in progress,
however early indications are extremely positive. Whilst there
are some minor issues that will be addressed, these should not
detract from the overall huge success of the operation.
6.6. Dissemination of Information
6.5.1 A Gold Media Cell was established
with a clear strategy in relation to the dissemination of information
to the public, both via the media and through postal delivery
of health information. From the start it was determined that Gold
Command should be as frank with the media and public as possible,
and to see the media as an ally, not an inconvenience.
6.5.2 A daily press conference was held
at County Police Headquarters, attended by local and national
media, led by the Chief Constable. The live news bulletins communicated
relevant and timely information and also delivered the Chief Constable's
key messages which were "patience and forbearance, use of
common sense, listening to key messages and be a good neighbour".
24 hour media broadcasting was used to optimum effect and feedback
indicated that people felt reassured and that the flow of information
was greatly appreciated. Media information was provided to other
interested stakeholders, for example local Members of Parliament
(MPs).
6.5.3 All press releases and attendance
at press conferences was co-ordinated through Gold to ensure consistency
and clarity of messages and so as to avoid any contradiction between
agencies. It was ensured that the expectations of the communities
of Gloucestershire were managed whilst at the same time providing
an honesty and realism about the situation. Public reassurance
and maintenance of confidence were identified as key themes throughout.
6.5.4 Health information and advice in relation
to flooded properties was disseminated on a number of occasions
via the Royal Mail. Their support in this function was greatly
appreciated. The Gold Commander negotiated with Union representatives
from the Royal Mail to postpone strike action to ensure that delivery
of important leaflets. Without the delivery of this important
health information contained in the leaflets, the delay in the
restoration of water supplies to the affected areas would have
been much more protracted. Health information was provided in
a number of formats to seek to ensure the needs of all members
of communities, including those more difficult to reach or whose
first language is not English, were met.
6.5.5 There were a few incidents where media
reporting was inaccurate or unhelpful. This should not detract
though from, on the whole a good relationship with the media who
were a vital part of the emergency response in ensuring a flow
of information. The media nationally and, especially, locally
were notable in providing timely and, within the limits of a dynamic
event, accurate information. There was some sensationalising at
the beginning of the emergency but in the main, a sense of responsibility
characterised media coverage in this emergency.
6.5.6 The emergency officially ended with
mains water being formally declared fit for drinking. Gold Control
stood down on Friday 6 August.
7. BENEFITS OF
EXPERIENCE
At this point a number of issues seem prevalent
to highlight for the committee's consideration.
7.1 All agencies need to re-visit their contingency
plans and re-evaluate worst-case scenarios and plan accordingly.
All agencies need to re-think scenario and contingency
planning and extend these to include previously unthought-of circumstances
and plan accordingly. Whilst it would be impossible to cover every
eventuality, agencies should at the very least ensure contingencies
to deal with the forces of nature are fully considered and robust.
In the light of climate change contingency planning must not be
static but quickly grasp and move with these changes.
7.2 The resilience of Utilities across the
Country needs to be reviewed and addressed as a matter of urgency.
The loss of function at Mythe left the majority
of the County without mains water for an extended period. This
cannot be allowed to happen again, and alternatives should be
easily and quickly available. Although Walham maintained its function,
the consequences to the County and beyond are clear, had this
utility been lost. Alternative electricity sources from the network
need to be available in the event that Walham cannot function.
Exposure to single points of failure is planning to fail.
Medium term flood defences at Mythe, Walham
and Castlemeads provided through Hesco Bastion defences should
not become the long-term solution. Rigorous defences need to be
put in place to prevent the potential loss of function at such
crucial installations in the future event of flooding. Urgent
consideration needs to be given to flooding as a result of the
rise in the water table, in certain areas particularly around
the counties utilities and the affects of ground saturation. The
Hesco Bastion barriers will be no defence to water coming up through
the ground as experienced at Walham, there should be no assumption
that similar defences will stop Mythe from being lost in the future.
The question needs to be asked as to whether
the existing County's flood defences are fit for purpose and what
additional defences are required. The economic, social and emotional
costs on the County as a result of the flooding have been vast.
Any future investment in flood defences should take account of
these costs.
7.3 National and regional utility companies
need to engage at a local level with Local Resilience Forum.
Engagement with the LRF will assist in the identification
of risks at local and strategic levels, with the application of
shared knowledge ensuring the aversion of unnecessary scenarios
being played out. The Gloucestershire LRF has previously made
representations that the engagement of utilities should occur
at this level and not be confined to national and regional forums
as at present.
7.4 There must be an increased capacity to
supply basic needs to communities in the event of an emergency
The County needs to increase its capacity to
supply utilities, feed communities and supply other basic needs
in the event of another sustained emergency situation. Using existing
distribution networks could be one solution that should be explored.
7.5 There needs to be a strategic reserve
of light, heat and sanitation Country-wide
7.6 The Tri-Service Emergency Centre should
be maintained and strengthened through continual commitment and
investment.
Lessons learnt from events of 9/11 and the London
bombings of 7/7 2005 demonstrated the strength of a Tri-Service
co-ordinated approach from the initial response to a significant
event or incident. Events in Gloucestershire in July/August 2007
illustrated that the Tri-Service centre provided an efficient
and effective co-ordinated response, an instant Command and Control
infrastructure and an informal dialogue that promotes decision-making
processes and action. The integration of the three emergency services
at the Tri-Service centre allowed Gold Command to be on the front
foot.
7.7 The Government need to consider fully
the impact of continuing to build new homes on flood plains.
This has the potential to further increase the
number of communities in Gloucestershire who could be adversely
and dramatically affected by flooding to the point of losing their
homes. Also the attraction of buying such housing given recent
events should weigh in considerations.
7.8 There should be a specific requirement
for national agencies to attend GOLD Command meetings when so
requested and to ensure consistency of representation.
7.9 The importance of maintaining County-based
structures needs to be recognised as these represent a suitably
strategic organisation, but one which has local roots and knowledge.
7.10 There should
be a review of national reserve emergency supplies of food, water,
feeding and cooking amenities.
7.11 Gloucestershire Constabulary is a strategic
Force
In dealing with the flooding crisis, the Constabulary
was able to demonstrate its strategic capabilities as a County
Force, without the need for mutual aid when dealing with an event
of this magnitude. A regional response would not have been able
to maximise local knowledge, experiences and co-ordinated such
a dynamic and flexible response. The emergency equally highlighted
the strengths of local entities including fire, ambulance and
regional army brigades.
8. COBR
8.1 Liaison with COBR functioned well throughout
the emergency, and the attention, visits and support from the
Prime Minister, the Secretary of State for the Environment and
the Minister of State for Local Government and Communities was
very well received. It was not entirely clear whether COBR could
always easily access emergency supplies and the build up of contingency
reserves should be considered as a matter of urgency.
8.2 Most of these considerations are relevant
at a national level, and therefore there should be a national
review of contingency planning covering contingency reserves of
basic utilities including food, water, shelter and sanitation.
These reserve provisions would be available in the event of threat
of disruption to basic living requirements from terrorism or environmental
threat, as well as from conventional or CBRN attack in the event
of war.
9. APPRECIATION
9.1 A big part of the success story in handling
the emergency was the spirit and resilience displayed by the people
of Gloucestershire. It was evident by the activities of individuals
and groups of people, that there was a keen sense of ownership
and responsibility both throughout the emergency and when dealing
with the aftermath to resume normality and to help those less
fortunate than themselves.
9.2 From first responders, agencies, voluntary
groups and the wider people of Gloucestershire, there was a sense
and feeling that generally everybody responded positively to the
emergency. Although there were isolated occurrences of damage
and disorder, people queued in an orderly fashion and there were
numerous local support schemes assisting vulnerable locations
and individuals. This was characteristic of the resilience displayed
across Gloucestershire.
9.3 The Chief Constable would like to take
the opportunity in expressing his sincere thanks and appreciation
to everyone who helped, whether directly or indirectly, in the
response and continuing recovery work in relation to the Gloucestershire
water emergency of 2007.
9.4 The Chief Constable would like to extend
particular thanks to those agencies represented in Gold Command,
working alongside Gloucestershire Constabulary.
Gloucestershire Fire and Rescue Service
Great Western Ambulance Service
Gloucestershire County Council
Government Office South West
Health Protection Agency
Gloucestershire Primary Care Trust
ROYAL LOGISTICS CORP (9TH SUPPLY
REGIMENT)
ROYAL ENGINEERS (10th FIELD SQN)
Central Networks (E-On)
Gloucester Animal Health
10. GLOSSARY
ACCAssistant Chief Constable
ACPOAssociation of Chief Police Officers
COBRCabinet Office Briefing RoomMeeting
of the Civil Contingencies Committee.
DCCDeputy Chief Constable
DMADedicated meter areas
DWIDrinking Water Inspectorate
GFRSGloucester Fire and Rescue Service
GMAGold Messaging Application
GTECGloucestershire Tri-Service Emergency
Centre
LRFLocal Resilience Forum
MACPMilitary Aid to the Civil Power
PNCPolice National Computer
SARASevern Area Rescue Association
SCGSilver Co-ordinating Group
SCCStrategic Control Centre
STACScience and Technical Advice Cell
Gloucestershire Constabulary
September 2007
37 Available from www.ceh.ac.uk Back
38
A Severn strategy scoping report. Back
39
http://www.severnbore.ndirect.co.uk/bore2.htm Back
|