1.  INTRODUCTION

  1.1  Many thanks for the opportunity to contribute to your inquiry into the flooding which occurred in our region in June 2007. Before providing a detailed analysis of the flooding, we would like to make the following observations:

    —  We would like to pay tribute to our colleagues whose efforts throughout the flooding event meant that we maintained the clean water supply to the region and that we could respond rapidly and effectively to flooding incidents.

    —  The flooding in Yorkshire was caused by significant and unprecedented rainfall and, as the Secretary of State at DEFRA has stated, no system could have coped.

    —  Our sewerage and pumping infrastructure was filled to capacity in parts of the region and overwhelmed by the severity of the storms and the concentration of the rainfall. We believe our infrastructure performed well in what were exceptional circumstances.

    —  Like others, we are anxious to understand if there could have been better planning and coordination between the relevant agencies and to explore whether we can help to mitigate some of the future risks by improving our infrastructure as part of the multi-agency approaches being undertaken across the region.

    —  In order to facilitate an inter-agency approach, there may have to be statutory changes to the responsibilities of the parties including water companies, the Environment Agency, land drainage boards and local authorities.

  1.2  This memorandum is divided into the following areas:

    —  An overview of Yorkshire Water

    —  Analysis of the rainfall in June

    —  Emergency and contingency planning

    —  Maintaining the clean water supply

    —  Flooding

    —  Recovery

    —  Our statutory responsibilities

  1.3  We would be happy to answer any questions prompted by this document and would be happy to appear before the Committee.

2.  OVERVIEW OF YORKSHIRE WATER

  2.1  Yorkshire Water is a water and sewerage company and serves the area comprising the historic county of Yorkshire.

  2.2  Serving around 5 million people, we supply 1.2 billion litres of clean water daily and we directly employ 2,200 colleagues. We also work in partnership with a number of service partners to invest in and maintain our water and waste water network. Our current investment plan, agreed with our economic regulator in 2004 and known as AMP4, equates to us spending £1 million on the region's water infrastructure daily.

  2.3  We have been named "Utility of the Year" by our peers in the utility sector for the last three years and have been in the top two of Ofwat's league table for operational and customer service for the last two years. Ofwat has also identified Yorkshire Water as the most efficient water company which they regulate.

3.  ANALYSIS OF THE RAINFALL IN JUNE

  3.1  River and surface water flooding during June 2007 was the result of exceptional rainfall events on 15 and 25 June. Data published by the Met Office on 26 July shows that May to July 2007 were the wettest months since records began in 1766. In June, over 103.1 mm of rain fell in Fylingdales, North Yorkshire. Our water gauges show that the storms in Hull were at least a "1 in 151" year rainfall event.

  3.2  The Hull Independent Review Body state in their interim report that the Geography Department at the University of Hull shows that rainfall on 25 June was heavy and sustained with rainfall intensities of over 6mm an hour from 8 am to 5 pm. They concluded that it was highly likely that many areas of Hull were already significantly saturated on 25 June.

4.  EMERGENCY AND CONTINGENCY PLANNING

  4.1  On 12 June, the Met Office warned that unseasonable rainfall may lead to flooding in Yorkshire and the Midlands. On 15 June, exceptionally heavy and prolonged rainfall impacted the region leading to widespread flooding.

  4.2  We established Core Incident Management Teams (CIMT) at our Regional Operational Control Centre (ROCC) in Bradford. We had teams dealing with the clean and waste water sides of our business and our liaison with the Gold and Silver commands at Doncaster, Sheffield, Rotherham and Hull was managed through these teams.

  4.3  Establishing incident management teams early meant that we were well-placed to deal with incidents as they arose. It also gave the emergency command teams a clear single point of contact with the company and with colleagues who were empowered to make decisions.

  4.4  Managing the event from the centre also ensured that we were able to take a region-wide approach and could ensure that company resources were focussed in the right place, at the right time.

  4.5  The incident at Ulley Dam put tremendous pressure on temporary water pumping resources in the region. Whilst we do have reserve pumping capacity available for emergencies, it was difficult to source additional capacity until that situation was resolved.

5.  MAINTAINING THE CLEAN WATER SUPPLY—EMERGENCY RESPONSE

  5.1  Early in the incident, it was clear that supporting the effort to shore-up Ulley Dam was the regional priority. The reservoir, owned by Rotherham Council, was in danger of collapse threatening the major industrial and utility infrastructure further down the valley.

  5.2  We immediately released colleagues with reservoir safety expertise to support and advise the Council on managing this incident and we identified our assets which were within the potential flood inundation area and made arrangements to isolate vulnerable sections of pipework.

  5.3  This prompted us to undertake a proactive programme of visiting our own reservoirs to ensure the integrity of those structures. Whilst we were confident that the risk was low due to our proactive reservoir asset planning approach, we adopted a precautionary approach and colleagues twice daily walked the parameter of those reservoirs we judged to be most at risk to carry out visual inspections.

  5.4  We also managed and monitored the impact of the flood water on our water treatment works. There were two clear priorities; firstly, ensuring that the water treatment works themselves were not inundated with water and secondly, keeping the system under positive pressure as this is essential to the integrity of the system and therefore the quality of the water.

  5.5  Most of our water treatment works are located at areas higher than the areas they supply. This makes economic sense because it minimises the requirement to pump the clean water to customers and it also protects against flooding. This meant that the risk of inundation was low. Our river abstraction works are obviously more vulnerable to flooding and we did experience extremely high river levels at Elvington, Loftsome Bridge and Tophill Low. However these works did not flood internally and continued to operate.

  5.6  A bigger concern was the possible loss of power to the works. Treating and pumping water is an energy intensive activity and any loss of power would have resulted in a loss of pressure, leading to possible inundation and therefore corruption of clean water quality.

  5.7  The immediate issue was the loss of a National Grid supply point which meant there was a drop in capacity in the Sheffield region. Yorkshire Electricity Distribution Limited (YEDL) had to manage a situation where there was not enough power but also where energy usage was very unpredictable. The closure of businesses due to the flooding meant that their requirement predictions, based on existing demand curves, were not reliable.

  5.8  Rather than risk a loss of energy supply to our water treatment works and water pumping stations, we moved to on-site generation. All of our water treatment works have stand-by emergency generation which we supplemented with more generators at key assets, including water pumping stations. We pulled together teams of three people, one from field operations, one for asset management and an electrical and mechanical manager, and they visited each water treatment site and ensured that there was a robust energy supply.

  5.9  We were then able to advise YEDL that we would not be drawing power from the grid which released more capacity for other users in the region. A win-win situation—whilst switching to onsite generation was undertaken primarily to secure our treatment works doing so assisted YEDL in managing their energy demand.

  5.10  We stayed on stand-by generation for about a week after which we were able to reconnect to the grid.

  5.11  The final issue was the management of other physical assets. The Highways Agency advised us, for example, that a trunk main which serves around 150k customer was exposed. Water from the River Don had caused a landslide which exposed the main and made it vulnerable. We developed an engineering solution to shore-up the bank thereby protecting not only the trunk main but also the road and other utility services which ran alongside it and put this is in place within two days.

  5.12  Throughout the flooding event, we did not have any water quality incidents. This is to the credit of our colleagues who literally worked around the clock to ensure that the supply was maintained. Had it been lost, this terrible event would have been a true catastrophe.

  5.13  We lost supply from one water treatment works, Ewden in Sheffield. We were able to maintain supplies by using connections to alternative water treatment works and to our grid.

6.  MAINTAINING THE CLEAN WATER SUPPLY—PLANNING FOR RESILIENCE

  6.1  Our water supply network has high levels of interconnectivity, giving high levels of resilience.

  6.2  Designed to resolve the problems faced by the Company in the drought on 1996, our water grid now means that for around 95% of our customers we can switch to an alternative water supply should their usual supply be lost.

  6.3  Modelling of our system predicts that our systems can maintain supplies for several days even with the loss of more than one low level water treatment works. During this period we would have time to manage down demand and put in place further emergency measures.

  6.4  We believe that our approach to network development and the flexibility this gives us in terms of resilience planning is industry-leading. However we will review the position regarding those limited areas not connected to the grid to assess the costs and benefits of building further resilience into the system.

7.  SEWER FLOODING

  7.1  The unprecedented rainfall led to significant flooding in the region which impacted differently in South Yorkshire, the East Riding of Yorkshire, Selby and Hull.

7.2  South Yorkshire

  7.2.1  In South Yorkshire, the high levels of rainfall led to river flooding. Our waste water treatment works tend to be located close to rivers so, as the Rivers Don, Rother and Dearne and their tributaries overtopped, many of our treatment works were overwhelmed by the flood water. In some cases, colleagues were stranded at the works by flood water. Our waste water treatment works at Blackburn Meadows near Meadowhall, which serves Sheffield, was under 10 feet of water on Monday 25 June.

  7.2.2  During high rainfall, Yorkshire Water pumps screened but untreated flows directly into the river. This is undertaken under a strict consents regime agreed with the Environment Agency. When we cannot pump water into rivers, because the rivers themselves are overflowing, water backs up the system. This is known as fluvial flooding. In these situations, customers may see water coming back from the sewer system into streets.

  7.2.3  Once the water had subsided, we could begin to pump flows into the river again and in South Yorkshire the flood waters quickly subsided.

  7.2.4  The exception was Toll Bar in Doncaster, where due to its low elevation, flood waters remained for a number of days. Our pumping stations at Toll Bar worked throughout this flooding event. We actively monitored the pumping stations and were well placed to respond if they too became overwhelmed.

7.3  Selby and the East Riding of Yorkshire

  7.3.1  In the rural areas of the East Riding of Yorkshire and some parts of Selby, the rainfall did cause our network to become overwhelmed and customers did experience extensive surface water flooding.

  7.3.2  In these cases, the areas affected recovered quickly. Once it stopped raining, the sewers and drains could cope with the flows and the water ran away.

  7.3.3  The East Riding is very flat and low lying therefore excessive rainfall will not drain away quickly. The land drainage facilities, maintained by others, and the water courses maintained by the Environment Agency interlink with the sewerage network maintained by Yorkshire Water.

  7.3.4  The East Riding of Yorkshire is also dependent on drains to discharge flood waters. The high levels of the Burstwick Drain prevented emergency discharge of flood waters from the sewerage system and in the West, the Setting Dyke and the Cottingham Drain overflowed into the sewerage system. These dykes and drains are not owned or maintained by Yorkshire Water.

  7.3.5  The management of flows from the drainage system into the Humber is the responsibility of the Environment Agency. We are dependent on this drainage system as sewers also discharge into it. We would like to work with them to better understand these issues and if possible to develop remedies that allow our networks to discharge effectively rather than backing up, causing our sewers to overflow.

  7.3.6  Some flooding occurred to the west of Hull and affected towns including Hessle and Anlaby in the East Riding. The incidents of flooding in these areas are connected to what happened in the city of Hull and this is covered in the next section.

7.4  Hull

  7.4.1  The City of Hull is below high-tide level and is therefore dependent on an effective sewerage, drainage and water pumping system to remove surface water from the city. As with the East Riding, our sewers interconnect with water courses and land drains operated by others.

  7.4.2  Many of our assets in the city of Hull were overwhelmed by the sheer volume of rain fall on 25 June, including our waste water treatment works at North Ferriby and Saltend. Despite being 2ft under water, our works continued to operate at Saltend. This works serves the ½ million people in the city.

  7.4.3  Our major pumping stations at East and West Hull on the A63 worked to capacity throughout the storm event, pumping over 50,000 litres of water per second into the Humber.

  7.4.4  On Tuesday morning (26 June), we were alerted to a surface water pumping station failure at Bransholme in the north of the city. The foul water pumping station at this site continued to operate throughout the storm event.

  7.4.5  The pumping station, which takes surface water from the Bransholme Estate, was fully operational at the time of the storms but eventually was flooded like the rest of the estate by the exceptional rainfall causing the pumps to fail.

  7.4.6  We responded quickly and some pumping capacity was restored by Tuesday evening and we were able to source additional standby pumps to restore full capacity by Friday. To further assist in the clean-up, we have utilised additional capacity. The pumping station is now being repaired.

  7.4.7  We have contributed to an inquiry commissioned by the Leader of Hull City Council into the flooding. We are currently developing a detailed response to the interim report published by the Inquiry.

  7.4.8  We have also commissioned engineers Arups to carry out a study of the sewerage network in Hull. We want to reassure our customers in that city that we take the concerns they have expressed very seriously.

  7.4.9  We believe that a substantial multi-agency review of drainage arrangements in Hull will be required. The Environment Agency, Hull City Council and Yorkshire Water will all need to contribute to this and will need to be prepared to fund any resulting investment requirements.

8.  RECOVERY

  8.1  The flooding had a massive impact on YW assets and operations with over 30 waste water treatment works, including Blackburn Meadows, and over 100 sewage pumping stations being flooded. The initial emergency response secured a return to normal operational performance albeit with the support of temporary equipment. The next reinstatement phase is now underway which will return the assets to their pre-floods status so that long term operational performance can be sustained. A dedicated Reinstatement Team involving both YW and our Partners is now well established and the programme to reinstate the YW assets in both the South and East of our region is going to plan. The scale of the work is such that it take until December 2008 to complete the programme.

  8.2  Our contractors, Drainsaid worked around the clock to help with the clear-up on those homes directly impacted by flooding from our sewers.

  8.3  We were able to support Severn Trent's water business when their operational area was impacted by high rainfall in July. We contacted them and provided thirty operational colleagues to work under their direction. Our colleagues worked with Severn Trent for twelve days. We also provided tankers, continuous supply trailers, bottled water and bowsers.

9.  STATUTORY RESPONSIBILITIES

  9.1  It is apparent in discussions we have had with our customers and our other stakeholders that there is some confusion over the roles and responsibilities of various agencies with regard to river flooding and the drainage and sewerage networks. There is also confusion about the role of water companies in planning decisions where there is new development.

  9.2  Water companies, local authorities and the Environment Agency all have very clearly areas of responsibilities and these are defined in statute. These provide the framework within which the different agency responses to the flooding event can be understood. Our remit regarding sewerage and drainage is very narrowly defined. Section 94 of the Water Industry Act 1991, states:

    "It shall be the duty of every sewerage undertaker to provide, improve and extend such a system of public sewers (whether inside its area or elsewhere) and so to cleanse and maintain those sewers as to ensure that that area is and continues to be effectually drained".

  Sewers are elsewhere defined as drains serving premises, not open land. Water companies are not therefore liable for surface water and rainfall management.

  9.3  Water companies are subject to strict economic regulation and the Regulator will only allow companies to undertake and therefore charge our customers for activities which are defined in these regulations with regard to the sewerage network.

  9.4  Water companies are not statutory consultees for new planning applications. If we are approached by a developer or the local council, we can request conditions which the approving authority may attach to the permission when granted. We also have no powers to monitor that recommendations we have made are implemented.

  9.5  We are obliged to offer all new developments the right to connect into the public sewerage system under S.104 of the Water Industry Act.

  9.6  Such regulations may have to be reviewed as a result of this summer's flooding event.

Yorkshire Water

September 2007





 