BREAKDOWN OF NATURAL ENGLAND'S £50 MILLION ESTIMATE

  The main elements of Natural England's projected expenditure are:

  1.  Funding for access authority staff. The assumption on which the estimate is based is that funding would be required for one full time project officer to be based in each coastal access authority for three years on average—with variation of the actual term of employment according to the actual size and complexity of each authority's coastline. Provision is also included for administrative costs and necessary expenses, and for the cost of developing IT/GPS equipment and a spatial database to facilitate the work of project officers.

  2.  Funding for establishment works to facilitate new access. This cost estimate is based on work undertaken by independent consultants. Requirements for new infrastructure (such as steps, bridges, drainage, signs and notices) are based on surveys of existing access in four study areas selected to be representative of the English coast. Where appropriate, Natural England's indicative costs for installation of infrastructure are based on Agri-environment scheme payments or on payments under the Access Management Grant Scheme (which funded access authorities in carrying out work to improve access on CROW land). The estimates allow for creation of new access on over 2,000 kms of coast at an estimated cost of £4,945 per km. Natural England does not envisage widespread use of new fencing or artificial surfacing.

  3.  Funding for improvements to existing access. The cost estimates assume that some improvements will be required where existing access on the coast does not meet a satisfactory standard. Costs are included in the estimate for improvements on 780 km of existing access, based on a slightly lower level than the cost of creating new access above (64%) at an estimated cost of £3,185 per km.

  4.  Challenge fund. The proposals for improving access to the coast are for access on foot. However, we are interested in improving access for other users such as horse riders and cyclists where it is appropriate to do so and in agreement with landowners. Natural England's £50 million estimate therefore includes provision for a fund to contribute to locally—based initiatives to deliver wider access improvements.

  5.  Funding for maintenance. Natural England's estimate of costs of maintenance during the 10 year implementation period are based on £580 per km per year. This is based on the average maintenance and management costs for coastal national trails as estimated by independent consultants (RPA Ltd). The estimate takes into account that where the route is an existing right of way the Highway Authority will remain legally responsible for maintenance.

  6.  Other costs. Allowance is made for research and monitoring, including for assessments of any impacts on nature conservation interests; and for a communications programme to inform people of the new right.

  7.  Contingency fund. Natural England recognises that there may be costs which cannot be anticipated at this stage of the project and a 5% contingency fund has been allowed within the estimate.

  Natural England is continuing to refine the cost estimates as implementation plans develop.

Natural England

June 2008





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 July 2008