Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Supplementary memorandum submitted by the Department for Environment, Food and Rural Affairs (DMB 72a)

DEFRA RESPONSE TO COMMITTEE REQUEST FOR FURTHER INFORMATION

Details of the opinion polling undertaken on coastal access [Q 365]

  The Committee asked for information on opinion polling undertaken to support the Government's proposals to improve public access to the English coast. We have provided the Committee with a copy of the research study which was conducted by Ipsos Mori for Natural England. The Ipsos Mori report includes the following findings:

    —    72% of English people have visited the coast in the last 12 months;

    —    over a quarter of English adults (27%) visit the coast frequently and over half (53%) said that they would like to visit more frequently;

    —    9% of respondents said they would visit the coast more often if a clear path existed around the coast; and

    —    6% said they would visit more frequently if more area access were available.

  The report concluded that despite not being visited by everyone, the coast—and access to it—remained important to all and that improving access was seen by most people as something that would attract more visitors to the coast.

  The above information was gathered by Ipsos Mori (2006) using a variety of sampling methods which included group discussions with coastal residents, interviews with potential coastal visitors and with those working in the local tourism trade and a series of accompanied interviews with coast users. The core data came from face to face interviews conducted in the home among a nationally representative sample of 1,741 English residents.

  The following paragraphs are taken from a report by Asken Ltd, the independent consultant undertaking the cost-benefit analysis of the four options and which provided the basis for the figures used in the Impact Assessment:

    "Ipsos Mori (2006) found that 9% of respondents would visit the coast more frequently if a clear path existed around the coast as assumed under Option 1, [improvements using rights of way legislation]. Assuming the objective of an intuitively identifiable coastal access corridor, with in-situ signage where some doubt may arise, then a similar situation could arise for Option 4, [the Government's proposal for new legislation to create a coastal access corridor]. In addition, provision is made in the costs for Option 4 for upgrading infrastructure and improving access along sections of coast where access is already available but not to a good standard. It seems reasonable to make provision for some uplift in this respect too. However, we have no firm evidence for assessing what additional uplift would arise and consequently, we propose a conservative estimate of an extra 1%.

    However, the Ipsos Mori work also found that a significant proportion of people would be less inclined to visit areas where they were unsure of their rights (Option 4 introduces another set of access rights together with the potential for variations and temporary changes to corridor alignment) and which were not clearly and consistently portrayed (such as through on-the-ground measures and/or mapping). As a consequence, the uplift in visitor numbers could be lower, at about 6%, as for Option 2 [making more area access available].

    Given the uncertainty surrounding the change in visitor numbers likely to arise with Option 4 (note that respondents were not asked about this option specifically by Ipsos Mori), it seems appropriate to work with a range of between 6% and 10% increase, with 8% as a mid-point."

  We consider the choice of an 8% midpoint to be a conservative estimate of the likely impact because our proposed approach offers the best of both options considered by the Ipsos Mori survey and we believe it will offer attractions to a wider range of users. At the mid-point we would expect to see an additional 1.2 million visits to the coast per year which would not have been made to the countryside at all without the new access provision. In addition it is estimated that there would be around 3.7 million visits made to the coast which would have been made to another part of the countryside, resulting in a total of around 5 million visits per year attributable to the new access provision.

  The England Leisure Visits Report of the 2005 Survey indicated that in 2005 the value of trips made by residents living in England to the English seaside coast was estimated at £1.4 billion. A further £4.7 billion was spent on trips to seaside towns and cities.

Details of any update carried out on the cost-benefit analysis after the Government decided its preferred policy option (which differed from Option 4 in the Impact Assessment) [Q 377]

  A partial Regulatory Impact Assessment (RIA) was published in June 2007 as part of the public consultation paper Consultation on Proposals to improve access to the English coast. Following the consultation period we considered whether the assessment needed to be revised. We concluded that no change was required to be made to either the scope of the proposal for new legislation or to the estimates of costs and benefits of the proposed option. The proposed option presented in the Impact Assessment, which was published to accompany the draft Marine Bill on 3 April 2008, remained the same as Option 4 in the partial RIA.

  The legislative proposals to improve coastal access set out in Part 9 of the Bill are a means of achieving the Government's objectives, as proposed in Option 4 of the consultation, based on using the existing legislation of the National Parks and Access to the Countryside Act 1949 and the Countryside and Rights of Way Act 2000.

  We have provided the Committee with a copy of the independent research report undertaken by Asken Ltd on the costs and benefits of the 4 options set out in the consultation paper and which provided the basis for the partial RIA and the Impact Assessment. The report is considered to be robust and comprehensive, given the inherent uncertainties involved in putting monetary values on some of the elements.

  The Committee may wish to know that Natural England has undertaken additional work in refining the projected costs (see answer to Q407). In addition, coastal access authorities are to produce local access audits by Spring 2009 that will provide a further basis for checking the robustness of Natural England's cost estimates. Following Royal Assent, Natural England intends to pilot the new procedures and this will also ensure that the resource projections are realistic.

Detailed breakdown of Natural England's £50 million estimate [Q 407]

  The main elements of Natural England's projected expenditure are:

  1.  Funding for access authority and Natural England field staff. The assumption on which the estimate is based is that funding would be required for one full time project officer to be based in each coastal access authority for three years on average—with variation of the actual term of employment according to the actual size and complexity of each authority's coastline. Provision is also included for administrative costs and necessary expenses, and for the cost of developing IT/GPS equipment and a spatial database to facilitate the work of project officers. The estimate also includes provision for costs of Natural England field staff based on 1 officer for each of the 7 coastal regions.

  2.  Funding for establishment works to facilitate new access. This cost estimate is based on work undertaken by independent consultants. Requirements for new infrastructure (such as steps, bridges, drainage, signs and notices) are based on surveys of existing access in four study areas selected to be representative of the English coast. Where appropriate, Natural England's indicative costs for installation of infrastructure are based on Agri-environment scheme payments or on payments under the Access Management Grant Scheme (which funded access authorities in carrying out work to improve access on CROW land). The estimates allow for creation of new access on over 2,000 kms of coast at an estimated cost of £4,945 per km. Natural England does not envisage widespread use of new fencing or artificial surfacing.

  3.  Funding for improvements to existing access. The cost estimates assume that some improvements will be required where existing access on the coast does not meet a satisfactory standard. Costs are included in the estimate for improvements on 780 km of existing access, based on a slightly lower level than the cost of creating new access above (64%) at an estimated cost of £3,185 per km.

  4.  Challenge fund. The proposals for improving access to the coast are for access on foot. However, we are interested in improving access for other users such as horse riders and cyclists where it is appropriate to do so and in agreement with landowners. Natural England's £50m estimate therefore includes provision for a fund to contribute to locally—based initiatives to deliver wider access improvements.

  5.  Funding for maintenance. Natural England's estimate of costs of maintenance during the 10 year implementation period are based on £580 per km per year. This is based on the average maintenance and management costs for coastal national trails as estimated by independent consultants (RPA Ltd.). The estimate takes into account that where the route is an existing right of way the Highway Authority will remain legally responsible for maintenance.

  6.  Other costs. Allowance is made for research and monitoring, including for assessments of any impacts on nature conservation interests; and for a communications programme to inform people of the new right.

  7.  Contingency fund. Natural England recognises that there may be costs which cannot be anticipated at this stage of the project and a 5% contingency fund has been allowed within the estimate.

  A summary table of assumptions used in the calculations and estimated total expenditure on main costs is at Table 1. Natural England's estimates are based on it's, and its predecessors', experience with the development and funding of a number of long distance and National Trails, combined with specific research commissioned in relation to the coastal access project (the RPA report) together with information taken from the Asken report, commissioned by Defra as part of the partial Regulatory Impact Assessment of the proposals.

  Building on the data gathered to date, Natural England are now working with all access authorities around the English coast and undertaking a detailed audit of existing access provision to inform and refine current estimates. They anticipate completing this audit programme by the end of the current financial year at the latest.

Table 1 Key Assumptions and cost estimates summary
Item QuantityCost estimate for 10 years
Length of English coast4,500 kms
Length of new access creation2,090 kms
Length of upgrade to existing access   780 kms
Length of satisfactory access1,630 kms
Number of coastal access authorities     48 kms
Establishment costs—field staff and support £12.9 million
Establishment costs—physical establishment and of new access and upgrades to existing access £14.7 million
Maintenance of new access £6.0 million
Challenge fund and other costs £14.5 million
Contingency£2.5 million


Further information on the outside legal advice taken by Defra that assures the Department its proposals are compatible with human rights legislation [Q 476]

  Before the legislative proposals were drafted, the Department sought advice from Counsel in relation to their compatibility with the European Convention on Human Rights, and on the basis of that advice we were satisfied that the proposals would be compatible with the Convention.

CLARIFICATION

  Finally, I wish to provide some clarification on the legal position with regard to parks and gardens. Parks and gardens are included in schedule 1 to the Countryside and Rights of Way Act 2000 (the CROW Act) which sets out categories of land which are excepted from the right of access. This means that they will continue to be excepted from the new right of access to coastal margin unless any change is made to categories of excepted land. Changes can be made through an order under section 3 of the CROW Act, or under the new section 3A provided for in the draft Marine Bill.

  The draft Marine Bill policy document refers to a paper which is published on the Defra website (and which we have provided to the Committee). This paper sets out the main measures that we intend an order under section 3A to contain, including proposals on any changes to the existing categories of "excepted land" which are contained within Schedule 1 to the Countryside and Rights of Way Act 2000 for the purposes of section 2(1) of the Act. We have set out our intention in the paper to leave the category of "Land used as a park or garden" in Schedule 1 unchanged as it affects land that will become coastal margin.

  Following Royal Assent, the details of the draft order will be subject to a consultation process. The Order will then be subject to Affirmative resolution by both Houses, as required under clause 278(7) of the draft Bill.

Defra

July 2008





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 July 2008