1 Protecting people and properties
from the risk of flooding
1. Some 2.1 million properties in England, affecting
4.3 million people, are at risk of flooding from rivers and the
sea. 48.5% of these properties are at risk of flooding from the
sea, 48% from rivers and 3.5% from both (Figure 1 shows
the Environment Agency's flood zones). England has not experienced
major coastal flooding since 1953, but inland flooding in 2000,
prior to our 2002 report, affected some 9,000 properties.[2]
2. Widespread flooding affected properties in the
Midlands, Yorkshire and Humberside in June 2007 and in the South
and South West of England a month later, and at least four people
tragically lost their lives. There was also significant disruption
to infrastructure. The risk that part of the Ulley reservoir near
Rotherham might collapse due to the increased volume of water
led to 250 people living downstream being evacuated from their
homes and the temporary closure of the M1 motorway. At one stage,
up to 140,000 properties in Tewkesbury, Gloucester and Cheltenham
lost mains water as a result of the flooding of the Mythe water
treatment plant in Tewkesbury and around 48,000 properties in
Gloucestershire were without power at one stage when a number
of sub-stations were inundated.[3]
3. Flood water can cause extensive damage to property,
ruining soft furnishings, carpets and electrical goods and can
also cause structural damage to buildings. The experiences of
those affected by events in June 2007, many of whom have had to
move into temporary accommodation while their homes are cleaned,
allowed to dry out and repaired, show how traumatic and unpleasant
the effects of flooding can be.[4]
4. The Environment Agency (the Agency) is the principal
authority responsible for managing the risk of flooding from main
rivers and the sea in England and Wales.[5]
The Agency planned to undertake a review of the June 2007 floods
to consider the causes and the adequacy of the actions taken.
The Secretary of State for Environment, Food and Rural Affairs
has also commissioned an independent Lessons Learned Review.[6]
Figure 1: The Environment Agency's analysis
of flood zones in England and Wales
Note:
This map does not take account of flood defences.
Source: Environment Agency
5. The level of rainfall in summer 2007 may have
been unprecedented, but there are lessons to learn from the Agency's
immediate response to the situation. The Agency did not deploy
temporary flood defences in Worcester, but the water levels rose
above predicted levels on one river, resulting in the flooding
of some 30 homes. The Agency had a warning system to notify residents
of the imminent risk of flooding and in just one week (25 June-2
July 2007), Floodline Warnings Direct sent out over 90,000 messages.
But sending out warnings by email, fax or telephone at certain
times of the day, for example, late at night or early in the morning
might not be adequate if occupants are not alert to receive
them.[7]
6. The Agency received £483 million from the
Department for flood risk management in 2006-07, including £25
million in local levy from local authorities, compared to a total
of £303 million in 2001-02. Since its inception in 1996,
the Agency has spent £3.4 billion on flood risk management.
Figure 2 shows expenditure each year since 2002-03.[8]
Figure 2: Environment Agency Expenditure
on flood risk management 2002-03 to 2006-07[9]

Source: Environment Agency
7. Commercial and housing developments in the 1960s,
1970s and 1980s resulted in the inappropriate construction of
many properties in the flood plain. Under the Government's latest
agreement with the insurance industry, known as the Statement
of Principles, insurers will offer flood cover to those with a
less than 1 in 75 year risk of flooding and to existing customers
at greater risk where planned work will bring them into the 1
in 75 year category. Where no defences are planned, insurers will
work with existing customers on a case by case basis. The agreement
(renewed in November 2005) depends on the Government reducing
the flood risk to 100,000 homes in the next three years; sustaining
adequate investment in flood defences which take account of climate
change; strengthening land use planning to limit new development
in flood risk areas; providing more detailed information on flood
risk and flood defence schemes; and alleviating the risk of sewer
and flash flooding.[10]
8. The Agency has improved the flood protection for
an additional 100,300 households between 2003-04 and 2005-06 by
investing £900 million on the construction of new defences.
The 169 construction projects completed between 2003-04 and 2005-06
included new sea and river defences and the reconstruction of
existing defences.[11]
The Agency aims to start as many new construction projects as
funding constraints permit. It was not clear, however, that the
Agency was in a position to determine the right balance between
funding new construction projects and ongoing maintenance work.
The Agency had put in place a science programme which included
projects to gather data on the typical lifespan of each asset
type, the influence of maintenance measures on flood risk and
to what extent the visual inspection of a flood defence provides
a suitable assessment of its structural integrity.
9. Existing commitments accounted for nearly £105
million (representing 84%) of the 2007-08 construction budget.
Only £20 million of the 2007-08 budget was therefore available
for new projects. The Agency noted that the amount committed varied
from year to year depending on the portfolio of projects and that
projects often take several years to complete. For example, any
major remedial works resulting from the June 2007 floods, would
have to be funded by deferring or slowing down work on existing
construction schemes.[12]
10. Funding for new construction projects is determined
using a priority score system developed by the Department for
Environment, Food and Rural Affairs. Each potential project was
assessed against three factors: the financial benefits of a proposed
flood defence compared to the estimated cost of construction;
the number of houses protected for each £1,000 spent; and
the impact of a scheme on wildlife habitats and conservation areas.
In 2006-07 any project which scored 25 points or more out of a
possible 44 was likely to receive funding. In 2005-06 the Agency
spent £76 million, representing 29% of its construction budget,
on project development. Funding limitations meant that potential
projects were developed which were unlikely to go ahead. Since
relatively little funding is available in any one year for new
project starts, the development of such schemes, including for
example, the potential flood defence scheme in Ripon, consumed
resources and raised the hopes of communities when there was little
likelihood of construction. The Agency was acting to improve efficiency
and expected to achieve a reduction of 3% a year in expenditure
on study work and other development costs over the next two years.[13]
11. Climate change may lead to changes in typical
weather patterns across the country including the risk of more
intense periods of rainfall in parts of the country. The major
flooding in summer 2007 illustrates the damaging consequences
of such events. Flood defences were typically built to withstand
the risk of a one-in a hundred year flood, but the Agency estimated
that some of the June 2007 floods were in excess of one-in-140
year to one-in-150 year events. Flood water had flowed over barriers
such as those near Doncaster and Sheffield. Drainage systems had
also been overwhelmed.[14]
12. The Agency was researching the extent to which
climate change affected the volume of water flowing in rivers
and existing defences were being rebuilt to withstand projected
flood requirements in 50 years time. Best estimates indicate that
the Agency needs to allow for a 20% increase in flow to take account
of the predicted change in rainfall pattern. Future flood risk
might, however, depend upon the broader management of land in
river catchment areas, for example using water storage areas to
hold excess water upstream temporarily during periods of heavy
rain to protect urban areas.[15]
13. At the time of the Committee's previous report
on inland flood defences in 2002, the Agency had started to develop
catchment flood management plans and later set a target to complete
68 plans by December 2007. These plans are designed to set out
the policy for managing flood risk in a catchment over the next
50 to 100 years, taking into account various factors over the
long term, such as climate change and property development, so
that decisions about construction and maintenance can be made
in the context of the catchment as a whole.[16]
14. The Agency's intention was that proposed construction
projects would be based upon catchment modelling and the policies
set out in the river catchment flood management plans. Only six
of the catchment plans had been completed by June 2007, however,
and the Agency did not expect to complete all plans until the
end of 2008. Budget cuts imposed by the Department in 2006-07
were said to have slowed progress on developing plans. Meanwhile,
the Agency was continuing with its construction programme. £232
million of work was, for example, planned for the Humber Estuary
over the next 25 years. The catchment flood management plans for
the Rivers Don, Rother and Ouse in North East England were, however,
still being developed and would not be completed until July 2008.[17]
15. Existing drainage systems are often put under
strain when new housing developments are built, as usually the
system is extended to include the additional properties with limited
consideration given to the impact on the capacity of the whole
drainage system. The adequacy of urban drainage was becoming an
increasing concern, particularly with more intense rainfall adding
to the risk that drainage systems would be overwhelmed.[18]
16. The Agency was involved in a number of pilot
projects to develop 25 year drainage plans, but their success
would depend upon the collaboration of water companies, local
authorities and developers. The Agency was pressing for greater
use of sustainable urban drainage systems in its discussions with
planners and developers, for example, using permeable concrete
and creating water holding areas so that water could be contained
without entering the drains and causing flash flooding. The difficulty
with these systems was agreeing who would maintain them in the
future. The Agency pointed out that none of the proposals in the
White Paper on Planning for a Sustainable Future, published in
May 2007, specifically addressed flood risk or sustainable drainage
systems. The White paper did, though, propose a more strategic,
clearer and focused national policy framework. Planning Policy
Statement 1Delivering Sustainable Development, was central
to the paper and gave policy support to sustainable urban drainage
systems.[19]
2 C&AG's Report, para 1.1; Ev 7 Back
3
Oral Statement to the House by the Secretary of State on flooding
in England, 26 June 2007; Oral Ministerial Statement by the Secretary
of State on Flooding, 24 July, 2007 Back
4
C&AG's Report para 1.4; Qq 4, 8 Back
5
While we refer to the Agency as responsible for flood risk management
in England, it actually has permissive powers under the Water
Resources Act, 1991, to manage flooding from designated 'main'
rivers and the sea. The legislation confers no right to protection
or to any particular standard of defence. Where the Agency does
not exercise its permissive powers, any flood defence remains
the responsibility of the relevant landowner. Back
6
Ev 29, Ministerial Statement by the Secretary of State on learning
lessons from the recent floods, 12 July 2007; Oral Ministerial
Statement by the Secretary of State on Flooding, 23 July 2007 Back
7
Ev 28; Qq 60, 99-104 Back
8
C&AG's Report, para 1.8; Ev 17 Back
9
Ev 23 Back
10
Q 32; Statement of principles on the provision of flood insurance
updated version, Association of British Insurers, November 2005 Back
11
C&AG's Report, para 3.1 Back
12
Qq 21-25, 52-55; C&AG's Report, paras 2.6, 3.7 Back
13
C&AG's Report paras 3.8-3.10; Qq 24-25, 42-43, 51-53; Ev 25 Back
14
Qq 2-4, 27 Back
15
Qq 2, 4, 27-30, 36-37, 44 Back
16
C&AG's Report, para 2.24 Back
17
C&AG's Report, para 2.24; Appendix 1; Qq 5-8, 29-30, 37, 51-52,
67 Back
18
Qq 32, 36, 38 Back
19
Qq 32-33, 36-38; Ev 22; Planning for a Sustainable Future White
Paper, CM 7120 Back
|