Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 60-79)

HM TREASURY & PARTNERSHIPS UK

6 FEBRUARY 2008

  Q60  Nigel Griffiths: Why do you not make it a requirement is what I am asking and then instead of having two thirds complying with that not unreasonable request, you would have the whole show?

  Mr Kingman: There is a tension between our desire to promote good practice and not actually hamstringing the whole of the public sector by saying the Treasury knows best about everything and there are no circumstances in which you can do something different.

  Q61  Nigel Griffiths: You are making an exaggerated sweeping statement that the Treasury knows best. I am not suggesting the Treasury knows best: I am suggesting that it would be very good if there were a pool of contract managers. Forget "knows best on everything else". I would hope you do know best on this.

  Mr Kingman: If I may, there may be, for example, a small PFI project where actually they do not need a full-time contract manager. I do not know whether that is justified or not. It is a reasonable judgment for someone to make. Our role is to say that it is a very good idea to have a full-time contract manager and you have to have a good reason if you want to do something different.

  Q62  Nigel Griffiths: You have an operational taskforce. Why did it take half a decade of PFI to set that up?

  Mr Stewart: We set it up at what we thought was the most appropriate time when there was some operational experience. That is not to say no support was available before then. We were providing ongoing support: we just formalised that and set up a formal OTF in March 2006.

  Q63  Mr Williams: Only a couple of quick points. We are told that competitive tendering has not always being undertaken where it would have been possible. Why is that? Are they advised they should undertake competitive tendering or not?

  Mr Kingman: They are very strongly advised that they should and we have a very strong presumption in favour of competition. There are three big projects where this did not happen. Two of them were prisons and the procuring authority took a judgment that operationally they could get the existing contractor to manage the risk within the prison context much better than they could getting an outside contractor to do it. Then they benchmarked that price against what they could get and they made a judgment that that was the right thing to do. I certainly would not exclude the possibility that that is a reasonable judgment for a procuring authority to make, but it should absolutely go through very clearly why it is not having competition, whether it has a good value for money reason for not having a competition.

  Q64  Mr Williams: I see new guidance has been issued in 2007. PFI has been around since 1992. Why has it taken so long to produce new guidance?

  Mr Kingman: We continually improve the guidance and there is a sort of archaeology of bits of guidance that we have issued over the years which I hope has continued to improve, learning the lessons as we learned them. PFI has in some form been around since 1992 and the great bulk of PFI projects really started coming on stream at the beginning of this decade.

  Q65  Mr Williams: So what were the principal lessons the new guidance was intended to address?

  Mr McKechnie: The standardisation of PFI contracts has been around for some time. The first one was issued in 1999 and it was version four that was issued in 2007. The two main improvements, with respect to the operational phase, were that it dealt with management fees, which have already come up in discussion, because they were also becoming an increasing problem over the previous years. As James mentioned earlier, it made a distinction between how to handle small changes, medium changes and large changes. The concern had been until then that some of the small changes were being handled in somewhat too bureaucratic a way and it was much more sensible to streamline that.

  Mr Williams: Following on the point Nigel has been dealing with, the fact that a third of the hospitals and one in six schools do not have enough staff to manage their contracts properly, I am as bewildered as Nigel was, as to why you tolerated such a situation. How long have you been aware of the scale of this failure?

  Q66  Chairman: I am amazed Mr Kingman that you do not know the answer. You have had to turn to somebody who has been imported from the private sector. I have to say Mr Kingman I have found your whole attitude during this hearing arrogant and lackadaisical and I hope in the remaining few minutes you will try to do better and try to take this Committee more seriously.

  Mr Kingman: I am sorry Chairman; I certainly do take this Committee seriously.

  Q67  Chairman: You have been asked a direct question and you can perhaps now give us the courtesy of answering it. It says in your biography that you are responsible for £600 billion of public money. Right, well let us now have some answers.

  Mr Kingman: I am afraid I do not know at what time the Treasury has been aware of this.

  Q68  Mr Williams: Do you mean this came as a surprise to you when the National Audit Office mentioned it?

  Mr McKechnie: It did not come as a surprise. We knew that some projects were under-resourced; we have known that for some time.

  Q69  Mr Williams: So what did you do about it?

  Mr McKechnie: We have done things such as set up the operational taskforce and we have encouraged projects to hire more staff. It is not just about numbers, it is also about getting the right skills and that has to do with the training programmes that have been run by the operational taskforce and indeed the NAO itself has run training programmes.

  Q70  Mr Williams: In dealing with setting up a PFI contract, the costs that you incur in relation to the supplier are only part of the costs, are they not? There is the cost that you need to do just what is not being done, to monitor it. Is that cost allowed for anywhere, is financial provision made for adequate supervision?

  Mr Kingman: The Treasury is not resourced to monitor every PFI project and we do not seek to monitor every PFI project.

  Q71  Mr Williams: No, but you tell someone else to.

  Mr Kingman: Departments certainly do and their auditors do and the NAO do and that would be true of a publicly procured project just as much as a PFI one.

  Q72  Mr Williams: But it is therefore part of the cost of the PFI contract is it not to have it properly monitored.

  Mr McKechnie: Yes.

  Mr Kingman: Yes; absolutely.

  Mr Williams: Do we know what that aspect is costing us?

  Q73  Chairman: Well, what is the answer?

  Mr McKechnie: We will need to write you a note on that. [1]

  Q74 Chairman: What is the point of sending us a note? Why are you here?

  Mr Kingman: We do not have that cost at our fingertips.

  Q75  Mr Williams: It is a concealed cost and it looks as though either it is not being met by you or by whomever made the original arrangements or it is not being used properly by those to whom the resource is made available. Which is it?

  Mr Kingman: I would strongly agree that it is part of the cost of the project and when a procuring authority looks at doing a PFI project, it should take that into account and I have every reason to think they do so.

  Q76  Mr Williams: Who ultimately bears the responsibility for ensuring that something as important as this is applied across the 16% of hospitals and 16% of school that are not doing it? Are they being provided with the resources for it?

  Mr Kingman: The responsibility lies with the relevant procuring authorities and ultimately with the relevant accounting officer in the department.

  Mr Williams: We are not getting very far.

  Chairman: No, we are not.

  Q77  Mr Burstow: Just a couple of things I wanted to pick up on. The first thing is something you said earlier on in response to one of the questions that M Bacon was asking in relation to the role Mr McKechnie plays within the Department. You made a comment that we need people from the private sector in the Treasury because they know where the bodies are. Could you perhaps tell us which are the bodies you had in mind and then perhaps Mr McKechnie can tell us where they are?

  Mr Kingman: I will ask him to do that. As the Committee has rightly pointed out on a number of occasions, PFI is complex and risky because there is the risk that the public sector frankly has the wool pulled over its eyes by sophisticated people from whom we are buying services. We think that part of the Treasury's role is to prevent that happening and that is what I mean by saying we need to have people who know how it all really works.

  Q78  Mr Burstow: Is that one of the reasons that all of these extra charges that the Report has uncovered are being lumped on?

  Mr Kingman: On the contrary. I would say that it is a very good example of the kind of thing that we are able to clamp down on because we work out that it is going on and we do something about it.

  Q79  Mr Burstow: If they have been clamped down on, why was it they were revealed through the work the NAO has done?

  Mr Kingman: Our guidance, which said that we thought these fees were unacceptable, was issued in March 2007, well before the NAO began their work.



1   Note by witness: The Committee asked about the financial provision made for monitoring operational PFI projects. The value for money assessment for each PFI project must reflect the cost of ongoing monitoring, as set out in the Treasury's 2006 "Value for Money Assessment Guidance". I am afraid the aggregate cost of monitoring PFI is not recorded by the Treasury nor collected at a departmental level. This is because the ongoing monitoring of PFI projects (or in fact conventionally procured projects) is not recorded separately from the various other ongoing administration costs. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 2 September 2008