Select Committee on Public Accounts Minutes of Evidence


2.  Supplementary memorandum submitted by the Nuclear Decommissioning Authority

  Question 41 (Angela Browning): What the approach has been in terms of longer term recovery of contamination costs compared to the Sellafield site generally.

  In regard to estimates for decommissioning of each of the NDA designated sites, it is the responsibility of the SLC to produce a technically feasible and costed plan for remediation of all the facilities, infrastructure and land on the site to an agreed end state. The end state for each site, which has been consulted on with stakeholders, may differ and as such the extent of the remediation required may well vary. NDA does not proscribe how the end state is achieved but examines as part of the Lifetime Plan assurance activities the approach proposed by the SLCs and the adequacy of provisions made.

  In regard to Sellafield, an exercise is currently underway within the SLC to gain a more refined understanding of the decommissioning costs for the key facilities and potentially contaminated land, with the results of these studies informing future Lifetime plans and thus overall UK civil nuclear liabilities. The majority of the facilities at Sellafield and the other sites are unique and first of a kind with the historic facilities, dating back to the 1940s and 50s, not built with decommissioning in mind. As such whilst opportunities do exist to develop generic decommissioning approaches and tools and techniques on one facility and deploy them elsewhere, translation into a prescriptive national approach is considered over simplistic. The sharing of good practice is achieved by technical baseline sharing and industry wide working groups, sponsored by NDA. Given the diversity of approaches required across the UK sites a simple parametric approach to cost estimating is not possible. As such the decommissioning estimates are subject to significant uncertainties.


  Question 63 (Mr Philip Dunne): What the Comprehensive Spending Review is for your Authority for the next three years?

NDA Summary Income and Expenditure SR04 and CSR07
05/06 06/0707/08 08/0909/10 10/11Total Total% Change
Actual ActualBudget F'castEstimate Estimate
SR04 SR04SR04 CSR07CSR07 CSR07SR04 CSR07
£ million £ million £ million£ million £ million £ million£ million £ million
Berkeley31 3950 6847 47119 16236.2%
Bradwell49 4132 3030 30122 89-26.9%
Dungeness A51 5144 4237 36145 115-21.0%
Hinkley Point A57 5537 4040 40148 120-18.8%
Sizewell A50 5239 4137 37142 115-18.6%
Magnox South Support -- 2829 3029 2887 206.4%
Chapelcross57 6357 5549 48178 152-14.3%
Hunterston A45 3738 5251 54120 15730.5%
Oldbury57 6669 8173 74193 22818.1%
Trawsfynydd50 5351 6257 64155 18318.4%
Wylfa85 90105 9388 92280 274-2.2%
Magnox North Support -- 1818 1819 1855 209.7%
Electricity Trading 9467 7753 5552 238159 -33.1%
Harwell and Winfrith 9699 9560 6060 291180 -38.1%
Dounreay146 147158 152157 160451 4683.8%
Sellafield and Calder Hall 9901,174 1,2081,296 1,2811,301 3,3723,879 15.0%
Capenhurst24 2124 2719 769 54-22.6%
Windscale22 3436 3532 3492 1008.6%
LLWR19 2938 3729 1886 85-2.1%
Springfields262 245267 322328 357773 1,00830.4%
Culham1 10 3 --100.0%
Non site expenditure (includes DRS) 232317 334299 340268 882908 2.9%
Total Expenditure 2,4202,679 2,8062,893 2,8572,827 7,9058,577 8.5%
Commercial Income1,341 1,2501,221 1,1101,247 1,1213,812 3,478-8.8%
Waste Substitution Income -- 160250 -- 160250
Total Income 1,3411,250 1,3811,360 1,2471,121 3,9723,728 -6.1%
Grant in Aid & EYF 1,1681,450 1,3711,535 1,6091,705 3,9894,849 21.6%
End Year Flexibility (EYF) -89 110
(Surplus) / Deficit (89)(110) (56)(2) 11 (56)(0)




 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 10 July 2008