Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 100-119)

MINISTRY OF DEFENCE

17 MARCH 2008

  Q100  Nigel Griffiths: I think it succeeded Clansman.

  Sir Bill Jeffrey: The in-service date was March 2004. It has been gradually rolled out across the Army since then.

  Q101  Nigel Griffiths: But by the time it came in, it was some years late?

  Sir Bill Jeffrey: It was, and indeed this Committee, I think before you joined it, or rejoined it, Mr Griffiths, had a hearing on that procurement, and there was a period during which we had to recontract because the initial contract was not satisfactory.

  Q102  Nigel Griffiths: So figure 23 on page 32, which shows a zero delay, that is a zero delay in what?

  Sir Bill Jeffrey: That is a zero delay, I think, within the year that the MPR 07 study is addressing, and there has been no further delay during that period, but it is a project which was much delayed earlier in its life.

  Q103  Nigel Griffiths: So basically, the clock was reset?

  Sir Bill Jeffrey: It is not so much the clock being reset as the way in which the MPR process works, that each year we look at the change in cost and timeliness within that year.

  Q104  Nigel Griffiths: So on figure 21, where it shows a 6% cost variation since approval, that is not since the original approval in the 1990s, is it?

  Sir Bill Jeffrey: No.[7]


  Q105 Nigel Griffiths: It has doubled and doubled again in cost.

  Lieutenant General Figgures: This particular means of meeting the capability requirement I do not think was approved until September 2001, when, following a competition, GDUK was given the contract. So I think in measuring how much things cost, until we have been to the Investment Approvals Board for the main investment decision, it would be wrong to make a judgment about cost increase. It is only when we have made the main investment decision, and the Approvals Board have given their authority for us to continue, that you can measure the cost. Prior to that, there was an allocation—it was felt it might cost something in the region of, but there was a degree of variation, because of course we did not really understand what the nature of this capability was going to be. We did not really understand in the mid 1990s that you could have a Tactical Internet. We did not understand that you would be able to achieve all the situational awareness that we have been able to achieve from Bowman today.

  Q106  Nigel Griffiths: Absolutely. I mean, if I remember rightly, the price paid for not understanding that was to hamstring our fighting forces with a rather out of date walkie-talkie system.

  Lieutenant General Figgures: Not agreed that it was a rather out of date walkie-talkie system, it was combat net radio which had capacity capable and necessary for the time, but it was not satisfactory for the 21st century, so we had to replace it.

  Q107  Nigel Griffiths: I take it you are telling the Committee the Bowman system is the system we need now?

  Sir Bill Jeffrey: Very much so.

  Q108  Nigel Griffiths: So how do you react to the summary in paragraph 1.18 that it is at risk?

  Sir Bill Jeffrey: One of the key user requirements, if I remember rightly, is described as being at risk, but I do not think it impacts significantly on the roll-out of Bowman.

  General Sir Kevin O'Donoghue: Can I offer a thought there? The latest package, the latest upgrade to Bowman, called number 5, should be being rolled out fairly quickly, and it needs trialling. That trial cannot take place because the brigades that would have been trialling it are deployed, and agreement between HO Land and myself is that we will delay that. That is not an equipment issue, that is a commitment issue.[8]

  Chairman: Thank you, Mr Griffiths. Your last questioner is Mr Keith Hill.

  Q109  Keith Hill: Thank you, Chairman. In contrast to Mr Griffiths, I want to ask several rather broad questions, and the first is: is my impression right that the general history of defence infrastructure development has been characterised by cost and time overruns, and if that is the case, why should that be?

  Sir Bill Jeffrey: I think it is the experience of all defence departments in all advanced countries that acquiring these normally leading-edge, technologically sophisticated pieces of equipment is subject to cost and time overruns. I mean, we are all in the business of trying to minimise these, trying to build the skills of our staff, trying to adapt our procedures; as my colleagues have been saying earlier, more intensively assessing at the early stage in order that we can reduce risk, and in order that we can minimise the likelihood that the thing will in the end slip in time and cost as so many of these projects have in the past. As we were touching on earlier, in one paragraph of the Report, the NAO detects signs that the impact of technical problems is reducing. We would agree, but we need to be cautious about that, because it tends to be some way into the life of the project before they become evident, but we feel we are gradually getting better at controlling those.

  Q110  Keith Hill: You anticipate my second question by your reference to experience in similar countries. It is the case, is it, that these kind of slippages in time and in cost are experienced across the board by our allies and indeed in other countries, as far as we can tell? Perhaps we could have one or two examples of that.

  Sir Bill Jeffrey: Indeed, we can certainly supply the Committee with a note on that.[9] We tend, in international surveys of this kind, to come out rather better than most, in fact, but we know we still have a problem, we know that we still need to work very hard to improve our internal capability, and our ability to ensure that the industry delivers in the way that we want it to. But internationally, I think it is fair to say, Kevin, is it not, that other countries struggle with the same issues?

  General Sir Kevin O'Donoghue: An example might be the C-17, the American aircraft, which had quite a tortuous run early on in its life, very complex aircraft, new aircraft; it is now an absolutely outstanding aircraft, but they took the time and the money to get it right. May I offer just three thoughts on time slippage? I believe there are three basic reasons for slippage in time. One is because the technology is more of a challenge than we thought it was, and what we need to do about that is derisk these programmes before we actually go to main gate on some of them.

  Q111  Keith Hill: What do you mean by derisk them?

  General Sir Kevin O'Donoghue: By sorting out what the technology is, by holding trials, by spending more money upfront before we commit to a production run, taking the risk of technological surprises out of it; so that is one area. The second area, and A400M is a very good example, is international collaboration, where actually, there is not a lot that we can do about slippages when you are collaborating internationally on a project. Still worth collaborating internationally, because the prices are very much less than if we were trying to do it all on our own. The third area for slippage is a deliberate decision; the fifth package for Bowman, that I was talking to Mr Griffiths about, is an example, where because the brigades are committed on operations, we have made a conscious decision that that particular programme would slip. So I think there are a number of different reasons for time slippage. I would accept there are occasions where it slips because we have not gripped the project, and there are always examples of that, which is what I need to do something about.

  Q112  Keith Hill: Thank you actually for that answer, I think there are all sorts of things that if we had time, we would like to follow up in that, but let me just follow up on this point about, as it were, international collaboration. Am I right in thinking that for strategic reasons, and perhaps also from time to time for narrower political considerations, that we tend to place orders with British companies?

  General Sir Kevin O'Donoghue: Yes.

  Q113  Keith Hill: What are the strategic reasons for doing that?

  General Sir Kevin O'Donoghue: I believe we are one of the most open defence procurement organisations around the world. We are happy to buy in most cases where the capability can be got at the best value for money. There are not that many occasions when we say, "No, we will only buy British".

  Sir Bill Jeffrey: If I might just add, Mr Hill, the caricature that one sometimes hears of the defence industrial strategy is that it was principally a means of in some sense protecting British industry. What tends to be forgotten is that the underpinning principle is that we are driven by what will provide the best capability and equipment for the military, and that in the end is what matters. If that means, in a competitive environment, going elsewhere, then subject to the exceptions that are mentioned in the strategy, we are perfectly ready to go elsewhere, and that is not true of every country in the world.

  Q114  Keith Hill: Forgive me, but in glancing through the list of the 20 major projects, what I was not able to pick out was how many of those are actually done by overseas companies rather than British companies.

  Sir Bill Jeffrey: There are some, if you take—I mean, some companies, these days, in the defence sector, of course they are international companies, most of them are, but in terms of companies that did not originate in the UK, Kevin O'Donoghue has just mentioned the A400M project, which is principally being delivered by EADS. We talked about Bowman earlier, which has essentially been delivered by General Dynamics, which is an American company. So it is a mixed picture, although particularly in relation to the big platforms, like destroyers and submarines, for reasons that are explained in the strategy, we tend to go to the indigenous industry.

  Q115  Keith Hill: Are there requirements of our defence forces which are absolutely unique and quite distinctive from those of other countries?

  Lieutenant General Figgures: Should I take that up? Clearly, we would be—yes, if you will indulge me, I am not sure that I wish to get into specifics of requirements that are unique to ourselves, and which are not shared by other countries, and why would I say that? Well, because, of course, we may have identified something that others have not, and therefore, we would not wish to expose an advantage that we have. But for example, the lightweight anti-tank weapon, the Javelin, there we had a military off-the-shelf procurement, but we changed the command launch unit, the means by which—you put the missile on the command launch unit, you peer through the sight, you observe the target and you fire. We felt that in order to make this more effective, and to get the balance right in the battle group, that we needed to improve our ability to see at range. So we improved the capability of the thermal imaging sight, and it is interesting that the work that we did with the contractor has now been picked up by the United States. So that was a very good example of exploiting a military off-the-shelf capability where our requirement actually was accepted as the most cost-effective.

  Q116  Keith Hill: That is very interesting. In terms of learning from other countries, how do you measure and do you attempt to measure the relative merits of defence equipment, for example performance of a British-built tank vis-a-vis a French, US or German tank, for example?

  Lieutenant General Figgures: We did quite a lot of work in preparation for the Defence Industrial Strategy, and I think if you look back there, under the science and technology piece, you see a graph which illustrates the technological lead of the United States, United Kingdom, France, China and so on. What it does illustrate is that investment in research and investment in development gives you a lead; you have to invest about 20 years out in the research side and about five years out in the development side to maintain that lead. Underpinning that was an assessment of individual equipments, so we looked at, say, all the tanks in the world, made judgments of their effectiveness, determined when the research and development had been put in place, and we were able to therefore make judgments about the effectiveness vis-a-vis other nations.

  Q117  Keith Hill: I am hurrying you up because I only have one minute left. But presumably, you systematically do monitor the performance of others and seek to learn from their experiences, and you would purchase if necessary?

  Lieutenant General Figgures: Yes, if there was something that met the capability requirement and all other aspects were equal—

  Q118  Keith Hill: I am sorry to interrupt you, I know you want to come in, Sir Bill, but I just have one final and rather nasty question to lower the tone of our exchanges over the last nine minutes. How do you react to the suggestion that MoD usually underestimates the likely cost and timescale of projects in order to make them more palatable to politicians, the public and perhaps the Treasury?

  Sir Bill Jeffrey: I think there is what some people who are more familiar with this area than I am would describe sometimes as a conspiracy of optimism, in the sense that it suits the supplier, the customer and indeed the eventual user to assume that things will come in at lower prices than would otherwise be the case. I think we have learnt from that. If you take the other example, the LSD(A), which is the subject of a separate Report which is part of these papers, that is a very good example of us ending up spending on the project what a comparative analysis by the NAO suggests is what we ought to have spent on it anyway, but starting off by thinking that it was going to be substantially cheaper than it turned out to be. What we need to do, through the derisking work that the General referred to, is get smarter and smarter at being realistic about costs, and devising deals with our suppliers that tie them in as effectively as we can tie them in, in the knowledge that we cannot in the end completely transfer the risk to them.

  Keith Hill: Thank you for that frank and very fair answer. Chairman?

  Q119  Chairman: Thank you, I just have one question. I think we should ask you about The Landing Ship Dock (Auxiliary) Project, volume III. If we look at page 9, figure 3, this is an absolute catalogue of errors, is it not, General O'Donoghue? Can you give us an assurance that this sort of thing will not happen again, what we saw with Swan Hunter?

  General Sir Kevin O'Donoghue: Yes, and the Permanent Under-Secretary has really just said it, what went wrong there was we did not apply smart procurement. Smart procurement is all about hands-off but eyes-on, and we took our hands off and I think we took our eyes off it as well. In the end, I think we got four ships at about the right price, according to the NAO's analysis, but you are absolutely right, the lessons learned from that were learned hard, but have been taken on board.

  Chairman: They will not happen again, good. I think Mr Bacon has a question on this.


7   Note by witness: The 6% variation shown in Figure 21 of the Report represents the forecast overrun against the "most likely" cost at Main Gate approved for Bowman Back

8   Note by witness: Large-scale trials of the latest capability increment (Bowman CIP5) were affected by the high tempo of operations. Despite this, the trials were successfully conducted in 2007 and the roll-out to the front line has since begun. However, in light of operational pressures, a decision has been taken to extend the roll-out process. This decision was taken with the agreement of the user. Back

9   Ev 15-16 Back


 