Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 20-39)

HIGHWAYS AGENCY

12 MAY 2008

  Q20  Mr Touhig: Did not the costs also increase because you did not foresee the extent to which meeting your very high quality standards meant that the tendering period would double from two to four years to start with? You got off to a pretty ropey start.

  Mr Bradbrook: No. We were of the very firm belief that good preparation work upfront, coming up with a set of clear and unambiguous tender documents and contracts, would reduce the costs later on. We were always looking at the whole life costs. Although the consultancy fee increased three times, if you look at the overall cost of the contract from preferred bidder to award there was not one increase; indeed, it went down by £2 million. Even the NAO's own reports published last year said that typically PFI contracts increased by 17% after preferred bidder stage. That work upfront not only stopped the price increasing after preferred bidder stage.

  Q21  Mr Touhig: Let us explore the work upfront. The tendering process doubled from two to four years?

  Mr Bradbrook: Yes.

  Q22  Mr Touhig: The cost of the tendering increased by 50% from £10 million to £15 million?

  Mr Bradbrook: Yes.

  Q23  Mr Touhig: We see from paragraph 2.4 that the bidders had concern about the validity of the data you gave them. You talk about all the work you did to get it right, but really what you said to the bidders was that they should come and invest in the project and gave them data that was not very reliable.

  Mr Bradbrook: You are talking about one particular type of data which related to the existing assets. It was important for us to get as much of that together as possible because one of the key risks we were transferring was the asset condition.

  Q24  Mr Touhig: But why were you unwilling to warrant the accuracy of the materials you were giving to the bidders?

  Mr Bradbrook: Because it was a risk we were transferring. It would be inappropriate to warrant something for which they were taking the risk.

  Q25  Mr Touhig: Is it any wonder then that you just ended up with two bidders? If I come along to bid for this project and you cannot guarantee the information you give me as the basis for my tender is it any wonder that you really do not have any competition at the end of it?

  Mr Bradbrook: I think that for a contract of this size and complexity with very large bid costs to have two bidders is good. It compares favourably with the Airwave project which had a single bidder at a much earlier stage. We obtained really good competition right up to the point of announcing the preferred bidder.

  Q26  Mr Touhig: So far I think we have established that you did not have a very robust case for going down the PPP line. The costs went out of control and you were giving those who were bidding for the contract information on which you said they could not rely. It sounds a bit absurd, does it not? Here is an agency that knows about road telecommunications; it has a wealth of expertise. It does not want to do the project itself and so it goes off to a PPP; it will not promise the bidders that the information it gives is accurate and so some drop out. Therefore, one does not really have competition at the end of the day for this work?

  Mr Robertson: As Mr Bradbrook said, we definitely did have competition as far as that was concerned. We took two consortia beyond the preferred bidder stage and so we were able to leverage on one side of that contract against that competition and on the other side leverage against the public sector comparator. We knew for how much we could do it ourselves.

  Q27  Mr Touhig: In June 2002 the agency realised that third-party revenues which would make the PPP better value for money would not materialise. Did that not provide any warnings for you? Were you then certain that you should be going along this route?

  Mr Robertson: Absolutely, and that was one of the two principal reasons why the objective of the procurement at that point moved away from what it had been originally, namely something that was to be an infill of the telecommunications network accompanied by the opportunity to realise third-party revenues. In 2001 and 2002 the telecommunications sector went into a collapse for three particular reasons. First, telecommunication entities of government had been sold off and that was accompanied by deregulation. That raised all sorts of expectations about the telecommunications age. Second, the technology itself advanced significantly so that what people previously had thought was a restricted asset suddenly became something akin to a free good.

  Q28  Mr Touhig: I noticed that you go through the KHHD consortium. Are you happy that they are value for money? You pay them £¼ million a month.

  Mr Robertson: Yes.

  Q29  Mr Touhig: I would not be too sure of that. There are only two men overseeing this project. How many people does KHHD have overseeing this project?

  Mr Robertson: There are two, one of whom is here, known to us as the two Davids overseeing this project. One David was apparently enough to slay Goliath, so two might have been considered overkill in this case.

  Q30  Mr Touhig: Paragraph 3.7 of the Report says: "The Agency's ability to manage effectively the cost of KHHD, which earned its fees on an hours worked basis, was limited by the size of the Agency's team..." They are running rings around you, are they not?

  Mr Robertson: There were two people working through this project who I think have done a splendid job. In addition, at a later stage we boosted the size of the team in order to help them work. They always had the support and advice of our PFI advisers and Treasury advisers and have always been working with the accounts and finance team of the Highways Agency, so all of the invoices could be checked.

  Q31  Mr Touhig: How many people from KHHD are working on this project? You have two.

  Mr Bradbrook: Obviously, it depends on the point in the procurement cycle, but at the peak when we had lawyers and accountants involved it was probably of the order of 15.

  Q32  Mr Touhig: They had 15 to your two?

  Mr Bradbrook: As I said before, their cost would be paid for in a stroke by not increasing the price beyond preferred bidder stage and not having any claims whatsoever in the first two years.

  Q33  Mr Touhig: But the point I am trying to establish is: are you satisfied that your two people against their 15 are keeping on top of this work? Paragraph 3.7 of the Report refers to "the considerable volume of material prepared by KHHD and the diverse geographical spread of the team of its advisers". That is clearly having an impact on the ability of your two men to do their job.

  Mr Robertson: I think these people did a good job.

  Q34  Mr Touhig: Not if you look at what is said here.

  Mr Robertson: Looking back at it now, if we were doing it again we would certainly put in more resources up front.

  Q35  Mr Touhig: As an aficionado of Yes, Minister and a former minister myself I know that the best trick in the world is just to sink people under paperwork. Looking at this Report, it seems to me that that is what KHHD is doing to your two people; they are sinking under paperwork and are not really able to manage this project in the way it ought to be.

  Mr Robertson: I think that is an interpretation of the Report. I accept that the vulnerability was there, but in our internal audit checks we have not seen any evidence that this team, albeit with a small core and with the support of the rest of the agency, did other than what I consider to be a very good job.

  Q36  Mr Touhig: It just seems to me that the more we go through the Report the more it highlights the failures of your agency. Were you the agency that also invented the hotline for cones back in the days of John Major?

  Mr Robertson: I believe that was a political inspiration, not an agency one.

  Q37  Chairman: As to KHHD, why was there not some incentive scheme imposed on it to make it manage within budgets?

  Mr Bradbrook: Initially, in the feasibility study we did it for a fixed price. Because we were not committed to follow the recommendations of the feasibility study it was inappropriate to set fixed prices in their tender for the subsequent phases, but once we had started the procurement process to control prices we wrote a project initiation document and various scoping documents for each of the strands of work. From those we produced task allocation forms in which each of the consultant's time was allocated.

  Q38  Chairman: That is all very interesting but you have not answered my question which is dealt with in paragraph 3.8: "In practice, there were no incentives, such as task performance bonuses/deductions, in KHHD's contract..." I want to know why there was not an incentive scheme.

  Mr Robertson: There were not incentive schemes there because we were looking to make the decisions and not have them adjusted by an adviser who was acting up front and would not be there at the end of the day.

  Chairman: That is a fair point.

  Q39  Mr Curry: Mr Robertson, I was thinking of you last Friday evening as I was travelling down the A1. I go up and down that road most weekends and I know it pretty intimately. I was thinking that it made life somewhat easier but you seemed to be removing all the roundabouts from the A1, no doubt at some gigantic cost, even though over 20 years I have never been held up at any of them, but it makes for a smoother ride. I then saw one of your overhead signs which said there were severe delays after—I think it was—the A428. After another mile I saw another sign which said the same thing. Two miles further on there were signs which repeated the message. I did not have the faintest idea where the A428 is, so your information was entirely useless to me. Had it said that there were severe delays after the Peterborough or Welwyn Garden City turnoff, or whatever it happened to be, that would have been helpful. Had it then gone on to say what I should do about it, it would have been seriously useful. The fact of the matter is that I know I use the A14 to access the A1 and I know where I get off the A1, but I do not have the faintest idea of the names, numbers, colours or sex of any of the roads between those two points. Why do you not give me some information that is useful to me as a motorist?

  Mr Robertson: First, thank you for pointing out the developments we are undertaking on the roundabouts on the A1. The roundabouts and the junctions of the A1 with which you will also be familiar have a poor safety record and we are taking them out for safety reasons rather than for reasons of congestion.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 28 October 2008