Select Committee on Public Accounts Fifty-Seventh Report

 
 

 
2  The costs to the taxpayer

7. The Department originally estimated that the total cost of setting up the Programme would be £55 million, with gross savings (before costs) of £112 million up to March 2015, giving a net benefit to the Department of £57 million.[12] The Department now estimates that the Programme will cost £121 million and produce benefits of £40 million, resulting in a net cost to the taxpayer of £81 million (Figure 1).[13]

Figure 1: Summary of costs and benefits of the project
 
ORIGINAL PLAN
 
CURRENT FORECAST
 
 
April 2005
 
March 2008
 
Gross benefits (£m)   
112.4
 
 
40.1
 
Set-up costs (£m) 
34.7
 
 
113.6
 
 
Severance costs (£m)  
20.7
 
 
7.6
 
 
Total Costs (£m)   
(55.4)
 
 
(121.2)
 
Overall Net Present Value (£m)   
57.0
 
 
(81.1)
 

Source: C&AG's Report, Figure 1

8. The Accounting Officer agreed that the projected net cost of £81 million was unacceptable and gave his personal commitment to ensuring that the Programme would not result in a net cost to the taxpayer.[14] The Accounting Officer believed that the current projected net cost was overstated as it was based on the £40 million in benefits that the Department had identified with certainty.[15] The Department expects the Programme to deliver further benefits such as an ultimate saving of 309 full time equivalent staff posts. It also intends to expand shared services to include routine procurement, which it is confident would save significant sums.[16] This is speculative, however, as the Department has not determined the precise scale of the benefits of adding routine procurement, the delivery timeframe nor the costs of achieving them.[17] Given the Department's track record in establishing robust benefits, cost estimates and a realistic timetable, we are concerned that the Department may be being overly optimistic in its assessment of the potential benefits.

9. In January 2006, the Department explored various ways of containing cost increases in its Shared Services programme and decided to use its contractors' offshore staff in India, rather than UK-based personnel. It expected this to cost one-third of the original estimate.[18] In practice, the Department encountered difficulties in obtaining security accreditation for the offshore team and, because of the time pressures involved, some of the work that it had planned to undertake in India was done in the United Kingdom at a higher cost.[19] The Department estimated that the use of offshore staff saved it some £44,000.[20]

10. The Department has, to date, paid Deloitte around £4.6 million for assistance on this project. In April 2004, the Department appointed Deloitte to provide consultancy support to the Department's Support Services Review and subsequently extended this contract to assist it in developing the outline business case and the handover of the shared services design stage to IBM. The value of that contract was some £2 million. Following the appointment of IBM as the Department's main delivery partner, Deloitte has provided quality assurance and other support on the project at a cost to date of around £2.6 million.[21]

11. The Department undertook to subsidise the running costs of the Shared Service Centre in its first years of operation. The subsidy in 2007-08 was around £7 million. The Department expected this figure to reduce to some £3 million in 2008-09. However, due to the delays in the migration to the Shared Service Centre of the Maritime and Coastguard Agency and the Highways Agency, the Department is funding an additional £2 million as there are currently fewer users of the Shared Service Centre than planned and the Centre's running costs are significantly higher than expected.[22] Once the Programme is fully implemented the Department does not expect to subsidise the Centre since it should recover all of its costs from its customers.[23]

12. The Department told us that it had not had to cancel or curtail any of its planned spending on other projects to fund the overspend on this Programme. Through careful management of its annual administration and programme budgets in the years prior to 2007-08 and, in line with HM Treasury's Consolidated Budgeting Guidance, the Department had built up sufficient end-year flexibility within its Departmental Expenditure Limit to fund the majority of cost increases relating to the Shared Services Programme.[24]


12   Q 2; C&AG's Report, Summary para 2 Back

13   Qq 2, 61 Back

14   Qq 83, 111, 127 Back

15   Qq 2, 60, 69 Back

16   Qq 69, 111-112 Back

17   C&AG's Report, para 2.28 Back

18   Q 79 Back

19   Qq 79, 81 Back

20   Q 82; Ev 14 Back

21   Qq 89, 118-119; Ev 14 Back

22   Q 72; C&AG's Report, para 2.14 Back

23   Qq 72-74 Back

24   Qq 76-78; Ev 14 Back


 

 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index  

 
© Parliamentary copyright 2008 
Prepared 16 December 2008