Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 1-19)

14 NOVEMBER 2007

DEPARTMENT FOR CULTURE, MEDIA AND SPORT AND OLYMPIC DELIVERY AUTHORITY

  Q1 Chairman: Good afternoon and welcome to the Committee of Public Accounts. I should like to welcome, first of all, members of the Public Accounts Committees from Guyana and Nigeria; you are very welcome and thank you for attending our hearing today. Our hearing today is on the Comptroller and Auditor General's Report The Budget for the London 2012 Olympic and Paralympic Games, and this is the Committee's second hearing on the preparation for the Games and we welcome back Jonathan Stephens, who is the Permanent Secretary for the Department for Culture, Media and Sport, the lead government department for the Games, and we also welcome David Higgins, who is the Chief Executive of the Olympic Delivery Authority. You are both very welcome and thank you for coming today. Mr Stephens, maybe I could put a couple of general questions to you first, and you might want to look at Figures 6 and 7 on page 17, on the main reasons for the increase in costs from the time of the bid to the budget announced in March 2007. I might say, Mr Stephens, it is a matter of regret to me that the Department announced the revised budget totalling over £9 billion on 15 March, just ten days after our last hearing. I am sure that was not coincidental, was it, Mr Stephens?

  Mr Stephens: Well, I recall that hearing and I remember you asked me when we would have a final budget and I replied it would be soon and you pressed me again, quite rightly, on what I meant by "soon" and I said, "I meant soon and I do not have a date", and I did not at that time, and the final details were not resolved at that time.

  Q2  Chairman: So ten days later you announced that, and this is now our first chance. Anyway, we are here now to ask these questions, so I am looking now at this Figure 7, the main reason for the increase in costs, but what I cannot understand is why you could not budget for such obvious factors, such as tax, contingencies, security and running costs in your initial estimate. Is this bad management?

  Mr Stephens: Well, Figure 6 sets out the increase in gross costs of £5.3 billion. Of that, the tax accounts for £1.2 billion, as the NAO Report makes clear, and that is a cost to the Games, it is not a cost to the Exchequer because it is a receipt to the Exchequer, so, net of tax, the increase in costs is £4.1 billion. Of that, more than half, £2.4 billion, is set aside for contingency in various forms.

  Q3  Chairman: It is £2.7 billion, is it not?

  Mr Stephens: If you net the tax off, it is £2.4 billion in total. Of the remainder, £600 million is set aside for wider policing costs. This was a known uncertainty at the time of the bid, which indeed caused my predecessor to notify the Committee of a contingent liability which could not be estimated at the time.

  Q4  Chairman: But in a sense you have not answered my question. We bid for these Games in an era of heightened security tensions, we all knew about the problem of security and presumably there was uncertainty about tax which you could have offset at the time. Some people might say to you, Mr Stephens, uncharitable people, that you deliberately put in a low bid to get these Games and fool the people, knowing that the bid that you put in at the time to the British taxpayer was totally unrealistic.

  Mr Stephens: Well, the bid was supported, as the NAO Report makes clear, by a succession of expert input and analysis, three separate reports going into the costs in as much detail as was possible, given the state of knowledge and development at the time, remembering of course that this was not an event that was certain, that the land was not in public ownership, that detailed site investigations could not be undertaken, and that the detailed plans of venues and so on could not, in the time available or within reasonable cost constraints, be drawn up.

  Q5  Chairman: I put it to you, Mr Stephens, that all these uncertainties you knew about at the time. You could have offset them and you either acted in bad faith or you were incompetent. Were you incompetent or did you act in bad faith?

  Mr Stephens: Well, you are quite right, there were a number of uncertainties—

  Q6  Chairman: Which were entirely foreseeable.

  Mr Stephens:— and that is why the Department commissioned, on the foot of the first Arup report on the specimen Games, a further PwC report to assess the risks around the Games and that suggested that the costs would lie in the region of £1.1 billion to £2.1 billion. Further, on the basis of the detailed PwC assessment that fed into the final bid, a risk assessment was done around that which suggested that, with an 80% probability, the costs would lie within plus or minus 10% of the sum that they suggested, so attempts were made to assess the risks at the time that the bid was made and also to register that there were some elements that were fundamentally uncertain, including policing where, as I said, my predecessor notified the Committee about contingent liabilities, saying that it could not be estimated at the time, but that the Home Office anticipated that there were wider policing costs. I have to say that, eight years out from an event, I do not know of any other event where you would expect the detailed policing plans—

  Q7  Chairman: No, but we would just expect the taxpayer, who is generally very happy to have these Games, to have an honest estimate at the time that we bid for these Games of what it is going to cost us. Now, we are looking at contingencies now of anything between £2.4 billion and £2.7 billion. The suspicion is that this is a very large contingency because you want to make absolutely certain now that this £9 billion is an upper limit, so really for this purpose you have deliberately made the contingency very large, it is puffed up with loads of uncertainties which we have not got to the bottom of, it is not very transparent, and you are using that as a safety net so that you can come back to us in five years' time and say, "We've achieved our aim; we are within budget". Is that fair? In other words, the contingency fund is over-generous and, as my colleague said, it is what I would do!

  Mr Stephens: I think it is a prudent, but realistic, attempt to manage the very significant and considerable risk around this project. This is—

  Q8  Chairman: So that is a yes, is it, as my colleague Mr Davidson would say?

  Mr Stephens: No, this is the equivalent of building something twice the size of Terminal 5 in half the time. At its height, there will be 20,000 workers on site and the spending will increase from currently just over £1million a day to more than £5 million a day; it is a very big and complex construction project. There will be a number of risks that we must expect to materialise over the course of the life of the project. This is a realistic and prudent way of managing those risks which over the last six months or so has been backed up and supported by a detailed and quantified risk analysis, so what we have done is, project by project, identify the risks that may arise on the individual projects at the level of the programme as a whole. External to the project is—

  Q9  Chairman: I will stop you there—

  Mr Stephens: Well, if I may just say, we have quantified each of these risks, then modelled them across all possible scenarios and, on top of that, we have sought to make an allowance for, what you might call, unknown unknowns, and all of this—

  Q10  Chairman: Why did you not do that originally? If you can do it so well five years before the Olympic Games, why not originally?

  Mr Stephens: Well, if I may just complete the point, all of this supports the contingency at £2 billion or so outside of the £500 million that has been allocated to the ODA already that is set out in the budget, so there is now a detailed and quantified analysis modelled against all the possible scenarios that supports this contingency.

  Q11  Chairman: It begs the question why we could not do it originally. You will resign if it now goes above £9.3 billion, will you?

  Mr Stephens: I am absolutely clear, this is the public sector funding package and it will not be exceeded, there will not be any more money for the construction of the Games and I am confident, on the basis of the risk analysis that has been done—

  Q12  Chairman: Anyway, you have not answered my question, so I will now go on to the next question about how you got it so incredibly wrong about the contributions from the private sector, and this is dealt with in paragraph 30. We were told £738 million and we are now told a measly £165 million. Why were these contributions from the private sector so wildly over-optimistic?

  Mr Stephens: Well, again this reflects the state of knowledge and development at the time. At the time, this was not an event that was certain and you could not approach individual private sector contractors with a specific proposition. The Department turned to its advisers, Partnerships UK, as the NAO records, and they actually identified potential opportunities of £1.3 billion and the Department discussed that and reached for the more conservative estimate of £730 million, but that was clearly at the time subject to a large number of uncertainties. What I would say is that, going forward, it is clear that the private sector will be making a very significant contribution. There will be the Village, which will almost exclusively be built and paid for by the private sector, there is the much wider Stratford regeneration, which would not have gone ahead at the scale and pace that it will without the Olympic Games, and, in addition, the budget takes no account of potential future land sales and development opportunities beyond the Olympic Games with the private sector, so the picture overall is that there will be a very significant private sector contribution.

  Q13  Chairman: Looking at Figure 7 again, why do you need a budget of more than £½ billion just for the Olympic Delivery Authority's programme management? This again has increased dramatically from £16 million to £570 million. The £16 million does seem to be very low estimate and we are now up to nearly £½ billion, but why do you need such a large budget and why did you get your estimate so wrong? Perhaps Mr Higgins might help me with that actually because it is his organisation.

  Mr Higgins: Figure 7, it shows actually that the £570 million is made up of a number of figures, the 344, which covers the Delivery Authority staff and the Delivery Partner costs. We did go out externally in May 2007 when Ernst & Young carried out a comprehensive review of the Delivery Partner's forecast costs and they confirmed that these fell within an acceptable range to enable the ODA to agree commercial terms for our task order. They did recommend that it be subject to periodic review and the next major review of the Delivery Partner costs will be next June.

  Q14  Chairman: Mr Higgins again, you might look at page 8, paragraph 13 of the Comptroller and Auditor General's Report. We are being expected to provide all this money and it seems to me that we have not really got a very clear statement from you as to what the budget will actually deliver. Is that a fair criticism? It is all very vague at the moment, is it not, and, if not, why have we not got it?

  Mr Higgins: We fully support the recommendation that comes through in section 13 and indeed the table on the following page sets out items (a) to (g) and we have worked through those now since the budget was announced and we are presenting them to the Funders Committee within the next few weeks, so that work has been carried out.

  Mr Stephens: And I can say that we expect, once the detailed scope has been signed off by the Funders Committee, to publish an account of that early in the New Year.

  Q15  Chairman: Mr Stephens, how are you going to make sure that LOCOG breaks even or, preferably, makes a surplus?

  Mr Stephens: We have a close relationship with LOCOG and we monitor their budget monthly. The Minister for the Olympics appoints one member of their board who is currently the Chief Executive of the Government's Shareholder Executive. We review their budget with them and their performance against it and of course they are, as the IOC reported, on track and on time. They have secured three major tier one sponsors, which is far in advance of previous Olympic Games which have been lucky to secure one major sponsor before the previous Olympic Games.

  Q16  Chairman: What worries me is that, judging by your record so far, I do not have any confidence in your ability to plan ahead. I think what is going to happen in the run-up to these Games in 2012 is that you are going to start panicking, things will be half-finished and you will start throwing money at it. Is that a fair criticism or an unfair criticism? It has happened in every previous Olympic Games, as far as I can see, and it will happen here and one of the reasons why I am asking the Comptroller and Auditor General to try and have these reports and these hearings now is so that this does not happen and that we do shine the spotlight on to you and Mr Higgins now.

  Mr Stephens: Indeed, and it has been very useful to have the NAO's engagement. Their Report says that the budget process leading up to the March 2007 announcement was thorough, that it was based on detailed analysis and expert input and that it represents a significant step forward in putting the Games on a sound financial footing, and that is one of the reasons why, alongside the NAO's own interest, Tessa Jowell invited the Comptroller and Auditor General to review the budget that she had announced. Indeed, we are keen that the NAO continues to review the further work that has gone on since the budget was announced, in particular, the work that follows through on all the recommendations on page 9, which means that we have now completed work on the cashflow analysis, but the detailed scope, as Mr Higgins said, is there and ready for consideration by the ministerial Funders Committee and the linking of the detailed budget breakdown with the scope is also there, ready and waiting, and with all of that we are happy for the NAO to continue to review.

  Q17  Mr Dunne: I would like to follow directly on the point you have just raised. Now that you have a budget which is set out to us in Figure 6, is it fair to say that you have each component by project, that each component of the plan has its own budget?

  Mr Stephens: Yes, that is the work that has gone on since then, the report which has gone to the ministerial Funders Committee which will provide the basis for a more detailed breakdown and budget which I hope will be published in the New Year.

  Q18  Mr Dunne: Is it phased by stages for each project?

  Mr Stephens: Yes, we have a detailed cashflow analysis year by year, and indeed that has gone into, and informed, what was published in the Comprehensive Spending Review as well as the basis for the requirements from the Lottery.

  Q19  Mr Dunne: Did I hear you right, that the cashflow is year by year? Do you have a month-by-month cashflow?

  Mr Higgins: Yes.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 April 2008