Select Committee on Public Accounts Fourteenth Report


2  Public funding for the Games

13. The March 2007 budget provided for an extra £5.906 billion of public sector funding. The Exchequer will meet the majority of the increase, with the revised funding package made up as follows:[14]

Exchequer        £5,975 million  (increase of £4,931 million)

National Lottery      £2,175 million  (increase of £675 million)

Greater London Authority    £925 million  (increase of £300 million)

London Development Agency    £250 million  (no change)

Total           £9,325 million (increase of £5,906 million)

14. The Government wants LOCOG, the organisation responsible for the operational and staging aspects of the Games, to be self-financing. LOCOG will not receive any funding from the £9.325 billion funding package, with the exception of a £66 million contribution towards the costs of the Paralympics. LOCOG had estimated its costs at around £2 billion; its sources of revenue included sponsorship, ticket sales and merchandising, and it had secured three major sponsors. As required by the International Olympic Committee, the Government is the ultimate guarantor of funding for the Games and this guarantee includes meeting any shortfall between the costs and revenues of LOCOG.[15]

15. While confident that the revised public sector funding package of £9.325 billion would not be exceeded, the Department had not produced a clear statement of what will be delivered for the revised public sector funding, setting out the time, cost and quality assumptions and the legacy benefits expected.[16]

16. We asked for a summary of the commitments made in the bid to host the Games and their costs. The Department subsequently explained that the development of more specific plans since the bid meant that it was not possible to reconcile current cost estimates to the original, relatively broad, formulation of commitments.[17]

17. The Department is responsible for securing the smooth flow of funds to the Olympic Delivery Authority so that work is not delayed and suppliers can be paid. The plan was to secure the £5,975 million Exchequer funding through the Government's Spending Reviews, which would confirm the spending allocations for individual departments. Some £4,028 million was secured in this way. The Department confirmed that the spending review commitments to date, which covered the period up to and including 2010-11, reflected the cash needs of the Olympic programme until then, and that the next spending review would cover the period beyond.[18]

18. As regards availability of other sources of funding, £1,085 million of the lottery contribution was dependent on legislation being passed. In addition, the £625 million to be provided by the Greater London Authority from the Council Tax precept was to be spread over the period up to and including 2016-17. The timing of the additional £300 million to be provided by the Greater London Authority remained to be agreed.[19]

19. Clarity about when funds will be needed and whether they will be available at the right time is key to making sure the delivery programme is not delayed. The Comptroller and Auditor General's report showed, however, that the Department was still preparing a forecast of the timing of expected funding needs, and that it was unclear how, when the Olympic Delivery Authority required funding, the requirement would be shared amongst each of the funders. The Department and the Olympic Delivery Authority confirmed that they now had detailed cash flow analyses, with monthly reporting to the Olympic Board.[20]

20. The final public sector contribution to the cost of the Games will depend on the public sector share of proceeds from the sale of assets after the Games. Land values in the Olympic Park are expected to increase, and the Government has agreed with the Mayor of London arrangements for sharing profits that may arise from future land and property sales, although this agreement is not legally binding. The Department estimated that £675 million would be available for repayment to the National Lottery, which is the amount of the extra Lottery contribution set out in the March 2007 budget. We calculate that to achieve this level of repayment to the Lottery, total proceeds from disposal of land and property owned by the London Development Agency would have to reach £1.8 billion (compared to the costs of some £650 million to purchase the land in the first place).[21]

21. The deal with a private sector developer to build the Olympic Village had not been finalised, but the Olympic Delivery Authority confirmed that if there was surplus profit it would be shared with the funders of the Games, including the National Lottery. The Delivery Authority expected that the funders would share the profits in ways that reflected each funder's contributions.[22]


14   C&AG's Report, para 37; Figures 7 and 8 Back

15   Qq 15; C&AG's Report, paras 22, 57-58; C&AG's previous report, Session 2006-07, Preparations for the London 2012 Olympic and Paralympic Games-Risk assessment and management, HC 252, para 61 Back

16   Qq 11, 14; C&AG's Report, paras 5, 13; http://www.culture.gov.uk/NR/rdonlyres/39358A28-98B7-42C0-A2EE-6D78E78905F3/0/dcmsgoeannualreportjan08vs2update.pdf; http://www.london2012.com/documents/oda-publications/programme-delivery-baseline-report.pdf Back

17   Q 79; Ev 19 Back

18   Qq 70-74; C&AG's Report, paras 69, 75-76; HM Treasury, 2007 Pre-Budget Report and Comprehensive Spending Review, Annex D14 Back

19   C&AG's Report, para 70; Olympic Funding: Revised Memorandum of Understanding between the Government and the Mayor of London, June 2007 Back

20   Qq 16, 21, 27; C&AG's Report, para 77 Back

21   Qq 39, 159, C&AG's Report, para 73; Calculation based on Olympic Funding: Revised Memorandum of Understanding between the Government and the Mayor of London, June 2007 Back

22   C&AG's Report, para 53; Qq 33, 88-89 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 April 2008