Select Committee on Public Administration Written Evidence


Correspondence with the Cabinet Office regarding the Winter Supplementary Estimate
2007-08


Letter dated 28 November 2007 from the Clerk of the Committee to Sir Gus O'Donnell

WINTER SUPPLEMENTARY ESTIMATE 2007-08

  The Committee has had a brief opportunity to consider the Winter Supplementary Estimates, which were laid on 12th November and will be considered in the House on 5 December, along with the accompanying Estimate Memorandum. I have been asked to seek further information from you on a few matters, and would be grateful if you could assist me by answering the questions set out below.

SCOPE PROJECT AND FUTUREBUILDERS

  The Resource Account states that the "main contract delivery phase" of SCOPE has been extended. What is the cause of the delay, and what are its consequences, both operational and financial?

  We note that the Cabinet Office's stock of end-year flexibility (that is, its cumulative prior-year under-spends) mainly appears to derive from a very large 2006-07 under-spend on its Futurebuilders scheme which is intended to improve capacity in the third sector. The capital under-spend was £99m (of £109m budgeted). The Resource Account says this is because of slower than expected demand for grants from the third sector. We would be grateful if you could explain the basis on which the Cabinet Office budgeted for Futurebuilders expenditure in 2006-07, and account for the significant discrepancy between predicted and actual uptake.

  With SCOPE capital funds coming from End-Year Flexibility funds, there is an issue that it (ie, SCOPE) might be funded by monies originally meant for the charities capacity-building programme. The Resource Account states that £46m of the under-spend has been "re-profiled". The remaining £67m is still potentially available for use under Futurebuilders although the timing of this is unclear. Do your accounts indicate that the Futurebuilders programme is being curtailed or down-graded? If so, how does this impact the Government's overall strategy for the third sector?

RFR 1—B OFFICE OF THE THIRD SECTOR

  The change in gross provision is stated as an increase of £7.87m. Some £3.235m is accounted for in the Estimate Memorandum (Children in Need £299K; V matched funding £3.3m; Invest to Save £399K; and a transfer to DCLG reducing administration expenditure minus £764). The remaining £4.635m is not clearly attributed. How is the £4.635m remainder allocated?

ADMINISTRATION BUDGET

  The latest Estimate Memorandum shows that administration expenditure was 73% of the limit in 2004-05, 81% in 2005-06, and 67% in 2006-07. The Memorandum states that the limit "included costs subsequently classified as other current/programme relating to depreciation and cost of capital largely in connection with Transformational Government assets".

What proportion of the administration limit is accounted for by Transformational Government-related items in each year?

What other factors are contributing to the Cabinet Office's underspend on its Administration Budget?

BBC MONITORING

  The Estimate also includes the transfer of BBC Monitoring to the Cabinet Office, with £3.3m of attached funding. There is also a draw-down of an extra £5m "to ensure funding is at the agreed level'. Why, if the CO has taken on responsibility for BBC Monitoring, is the cost being reassessed as £5m higher?.

  The £5m funding to provide budgetary cover for BBC monitoring is classified as a DEL Reserve claim in the Supplementary Estimate. Reserve claims should only be made for events that cannot be foreseen. When did Cabinet Office first become aware that BBC Monitoring would require extra budgetary cover in 2007-08?

  Please could you let me have a reply by 18 December 2007. This may be drawn on by the Committee in future evidence sessions and inquiries.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008