Select Committee on Public Administration Written Evidence


Letter dated 17 December 2007 from Sir Gus O'Donnell to the Clerk of the Committee

CABINET OFFICE WINTER SUPPLEMENTARY ESTIMATE 2007-08

  Thank you for your letter of 28 November 2007 requesting further information on matters reported in the Annual Report and Resource Accounts 2006-07 and in the Winter Supplementary Estimate 2007 and accompanying Estimate Memorandum.

  My responses are set out in the same order as your questions are raised in your letter.

SCOPE PROJECT

  The cause of the SCOPE project delay and operational and financial consequences can be explained as follows.

  SCOPE is a complex Programme and considerable time had to be set aside to review the proposed design for Phase 2. Whilst this has caused some delay, the resulting position is one whereby the total solution, including technology and working practices, is far better understood by government and suppliers significantly reducing the risk of an inappropriate solution being delivered.

  While necessary refinements to the supplier's solution over the last 6-9 months contributed to the overall timetable slippage for Phase 2, the contract price remains within the affordability envelope agreed by the Programme Board and the costs of extending the Programme have been absorbed without the requirement for additional funding.

  SCOPE funding is capped and ring fenced. Capital funding is provided by the Capital Modernisation Fund, Cabinet Office and the Foreign and Commonwealth Office. The contributions are fixed. The Programme continues to be well run and managed within its overall affordability envelope.

FUTUREBUILDERS

  The 2006-07 underspend on the Futurebuilders programme arises because the budget and outturn were calculated based on different accounting treatments and because the rate of take up of grants and loans by third sector organisations was slower than expected.

  When the Futurebuilders programme transferred to the Cabinet Office, it followed the same accounting treatment initially as that taken by the Home Office and therefore the Cabinet Office budgeted for the Futurebuilders programme based on the accounting treatment followed by the Home Office. The Home Office had recognised grant expenditure at the point commitments to make grants and loans were entered into by the delivery organisation, Futurebuilders England Limited. Commitments were initially forecast to use all funds allocated to the programme. In preparing Resource Accounts 2006-07, the Cabinet Office, with the agreement of the National Audit Office, changed the accounting treatment and now recognises grant expenditure at the point of cash disbursement to Futurebuilders England Limited. This accounting treatment more closely reflects the rate of operational delivery of the programme and consumption of resources.

  The Cabinet Office segregates its End Year flexibility by programme, so there is no danger that SCOPE may be funded by monies meant for charity capacity building.

  The Futurebuilders programme is not being downgraded or curtailed. The initial grant agreement is due to expire on 31 March 2008. Ministers have decided to re-tender the Contract for the management of the Futurebuilders Fund and it is anticipated that the retendered Contract will commence on April 1 2008 for a period of three years with an option to extend the Contract for a further three years to coincide with the Government's spending reviews.

  As set out in the third sector review, the Government will continue to invest in Futurebuilders, maintaining its commitment to bring the total investment in the programme to £215 million by 2011. Futurebuilders has so far made over £111 million of commitments to over 245 third sector organisations, however due to the innovative nature of the grant and loan finance available under the Futurebuilders programme, the disbursement of funding to the third sector organisations has been slower than expected.

  The £46 million underspend has been re-profiled and allocated to two new third sector programmes: the Community Assets Fund announced in the Pre-Budget Report 2006 and a new fund to stimulate risk capital investments in social enterprises as set out in the Social Enterprise Action Plan published November 2006.

  Government's overall strategy for the third sector is that it remains highly committed to supporting the third sector through the Futurebuilders Fund and other programmes.

RFR 1—B OFFICE OF THE THIRD SECTOR

  The increase in gross resource provision of £7.87 million comprises:
£ million
GrantChildren in Need 0.299
V Matched Funding3.301
Invest to Save0.399
Reclassify to non budget Grant in Aid to executive NDPB Commission   for the Compact Limited (1.430)
Red Cross1.000
Total increase in Grants 3.569
OtherVolunteering Health-offset by increase in AinA 0.065
CurrentFuturebuilders cost of capital-offset by increase in AinA* 5,000
Total increase in Other Current 5.065
AdministrationTransfer to DCLG (0.764)
Net increase in gross resource provision 7.870

*  The Charity Bank Limited maintains and manages a dedicated interest bearing bank account at the Co-operative Bank to hold the Fund—Futurebuilders Trust Account. Futurebuilders is managed under a tri-partite agreement between the Minister for the Cabinet Office, The Charity Bank Limited and Futurebuilders England Limited. This Trust Account attracts cost of capital charges of 3.5% on balances held. To cover this charge, balances are managed in order to generate sufficient interest income to offset this charge.

ADMINISTRATION BUDGET
£ millionOutturn TgovernmentProgramme UnderspendLimit
2006-07146.517.0 25.030.5219.0
2005-06158.228.6 3.06.0195.8
2004-05157.040.0 3.715.4216.1
PercentOutturn TgovernmentProgramme UnderspendLimit
2006-07678 1114100
2005-068115 13100
2004-057319 17100


  The proportion of the administration limit accounted for by Transformational Government depreciation and cost of capital and other programme spend is shown in the table above.

  Expenditure over the period 2004-05 to 2006-07 was subject to the 2004 Spending Review settlement. The settlement included headcount reductions, relocations and procurement savings targets. These are reflected in the under-spends in the three years and the Department's own efforts to create an appropriate departmental unallocated provision (DUP).

  In addition:

    2006-07    £30.5 million includes re-scheduling of accommodation and IT projects and various savings across the Department; and

    2005-06    £6 million income includes received by the National School of Government.

BBC MONITORING

  The Cabinet Office became the lead stakeholder for BBC Monitoring from April 1, 2006 and budget holder from April 1, 2007 and its forecast costs are in line with budget and have not been re-assessed as higher for 2007-08.

  When a decision was made to transfer responsibility to the Cabinet Office, it was recognised there would be a funding shortfall in 2006-07 and 2007-08 and HM Treasury agreed that the Cabinet Office would have access to £2.5 million in 2006-07 and £2.5 million in 2007-08 from a Special Reserve; this agreement is documented in a letter dated 5 April 2005, from Jonathan Stevens, Managing Director, HM Treasury to Sir David Omand, Permanent Secretary, Cabinet Office.

  Cabinet Office did not draw down £2.5 million in 2006-07 but has a need to draw down the full £5 million in 2007-08. The Chief Secretary to the Treasury has agreed to this claim and, given the special circumstances, has agreed the draw down will not carry implications for Cabinet Office End Year Flexibility Entitlement.

  I trust that this information provides the explanation you require.





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008