5 COSTS TO THE PUBLIC
70. The collapse of the Metronet PPP Agreements will
inevitably have an impact on taxpayers and Tube passengers. As
Tim O'Toole of London Underground told us:
I cannot sit here looking at a catastrophe of
this dimension and say, 'Don't worry, it is not going to cost
anyone anything'.[94]
None of our witnesses was able to provide an estimate
of the total public cost of Metronet's failure. However, on top
of liability for 95% of Metronet's overspend, which was projected
to reach some £2 billion by 2010, Transport for London has
made available a £900 million loan facility to Metronet's
Administrators to cover its operating deficit
of around £13 million
a week in
the absence of further funding from the banks.[95]
71. In September 2007 the Office for National Statistics
reclassified Metronet and Tube Lines from the private sector to
the public sector for the purposes of the National Accounts and
Public Sector Finances. Hence, according to the Secretary of State,
the entry into administration does not, of itself, change the
public expenditure treatment for Metronet's existing debt, and
so does not represent a net impact on the public purse.[96]
To the extent that the loan of £900 million is utilised (the
Administrator has previously indicated that he expects to use
the entire amount),[97]
this would also have been borrowed by Metronet anyway to cover
its operating deficit and would have been classified as public
expenditure, less the additional cost of administration.[98]
72. The additional costs to the public purse are
made up of Transport for London's liability for the additional
cost of administration and the cost of inefficient work by Metronet.
Otherwise, Transport for London's liability for Metronet's efficient
overspend and for the additional cost of administration represents
a transfer of liability from central Government to Transport for
London. In any case, the actual total cost overrun, whoever is
liable, is unlikely to amount to the figure that Metronet were
projected to overspend by 2010 if future work can be delivered
more efficiently than Metronet were expected to, and some of the
additional expenditure would have been necessary in any case,
even if the work had been delivered efficiently.[99]
As Mr O'Toole put it, "The issue is how much of that debt
did not deliver work that now has to be delivered by somebody
else and that is the cost to us."[100]
Additionally, the equity written off by Metronet's shareholders,
some £300 million to date, will contribute to paying for
its overspend.[101]
73. The Arbiter's report of September 2007 made public
the results of his initial analysis of Metronet BCV's Extraordinary
Review (subsequently suspended) and sheds some light on the likely
scale of inefficiently undertaken work.[102]
While Metronet BCV identified a likely overrun to 2010 of £1,047
million, the Arbiter's view was that the appropriate figure for
Net Adverse Effects for an efficient company would be in the range
£140-470 million. The Arbiter had also reviewed the financial
model for Metronet SSL, which shows a projected cost overrun of
some £1.15 billion to 2010, and considered that the potential
scale of recoverable Net Adverse Effects would likely be £230-600
million. The Arbiter's figures therefore put the cost of Metronet's
projected inefficient overspend to 2010 in the range of £1.1
billion to £1.8 billion.
74. Mr O'Toole told us that the Mayor of London has
asked for an assessment of additional costs and the resultant
impact to the future programme by late spring, although he noted
that the results will be partly dependent on negotiations with
the Government and other stakeholder as to the particular vehicle
to deliver Metronet's upgrade work.[103]
He was not confident that there would not be any scaling back
of the investment programme:
Everyone will do everything to protect the line
upgrades because to not deliver that is simply unthinkable. This
system, as I said, is bursting at the seams and it is becoming
ever more important to London and it has to be renewed. We already
know as a result of Trans4m just cancelling and walking off that
the stations programme has kind of sat down. We are trying to
continue the work that is on site right now so that at least there
is not a compounding of waste, but the starting of new jobs has
definitely fallen behind the original schedule, so at a minimum
some of that work is going to be pushed into the futureat
a minimum.
When we get into further analysis of the costs
and what can be done and when, the sort of things you have to
worry about is the completion of the stations programme, completing
the tunnel cooling programme [
], and the accessibility programme
and the congestion relief programme. [
] those are going
to be some very tough choices that will be faced in the future.[104]
75. On the delay to the station programme, Mr O'Toole
explained that, although the analysis was not yet complete, the
schedules for at least 50 station refurbishments have had to be
changed, which represents a separate cost in lost utility to passengers.[105]
He confirmed that he had only two potential sources of funding
to cover the costs of Metronet's inefficiency and other cost increases:
fares and a grant from central Government.[106]
Discussing a potential Government contribution to the costs of
Metronet's failure, he said that the Government had been "very
constructive" in its approach but had "not signed a
blank cheque".[107]
76. While expressing an aspiration to minimise additional
costs to the taxpayer or passenger,[108]
the Secretary of State would not confirm how much of the additional
cost central Government would be willing to cover:
[
] these issues were explored between myself
and the Mayor in the run-up to the Comprehensive Spending Review
and we were clear that the amount of money provided to London
as a settlement was appropriate to cover both the costs of Crossrail
and made appropriate accommodation for Metronet as well as delivering
for Londoners in other respects. Obviously within that envelope
the Mayor and TfL will have to make choices about priorities,
but I think it was an appropriate long-term funding settlement.[109]
77. It was always recognised that efficiently expended
increases in costsfor instance, due to the unexpected condition
of assetswould need to be assessed at the first Periodic
Review in 2010. Unless additional funding can be secured such
cost increases in the first review period will have to be offset
by reductions in scope in the second review period.
78. It was the Government that insisted on the PPP
structure for the modernisation of the London Underground in the
face of opposition by the Mayor of London. Now Metronet has failed,
it is unclear how much of the financial responsibility the Government
is prepared to bear. Both the Mayor and the Secretary of State
have insisted that transport in London will benefit from a favourable
settlement from the Comprehensive Spending Review but money for
Crossrail and the Olympics obscures the scale of central Government's
contribution to the cost of Metronet's collapse.
79. We recommend that the Government, as a matter
of urgency, make a full assessment of the additional costs that
have been incurred as a result of the failure of Metronetincluding
the cost of work that has been inefficiently undertaken and the
cost of administration. The Secretary of State should then come
to the House to make a statement on what proportion of these costs
are to be met by central Government and what proportion she expects
residents of London and Tube passengers to pay. The Government
should also consider its contribution to efficient increases in
costs as a result of the unknown condition of the infrastructure,
in order that London Underground is not forced significantly to
reduce the scope of the upgrade programme during the second Review
Period from 2010.
80. When Metronet entered administration on 18 July
2007, the Prime Minister told the House that, "If Metronet
pulls out, another company will be found to take its place"[110]
In August the PPP Administrators engaged an advisory investment
bank, N M Rothschild & Sons Limited, to carry out an independent
valuation of the Metronet companies in order that the market might
be tested for interest from potential purchasers. However, no
private sector interest was forthcoming. As Alan Bloom, Metronet's
PPP Administrator, told us
an active medium to long-term marketing campaign
for the business would have been fruitless. We would not have
generated any [
] interest in what we
had to sell.[111]
This negligible prospect of finding buyers persuaded
the Administrator that continuing with the Extraordinary Review
of Metronet BCV or requesting a Review of Metronet SSL, which
could have increased the companies' values by establishing London
Underground's liability for the cost increases, would have been
unproductive. The request for an Extraordinary Review was therefore
withdrawn on 31 October 2007.[112]
London Underground supported this withdrawal. The Review, in the
view of Tim O'Toole, was "a proceeding that was not going
to tell [London Underground] anything, seemed a complete waste
of time and, quite frankly, from our point of view, was vexatious."[113]
81. The failure to sell Metronet to the private sector
means that the costs of operating Metronet during administration
and of the overspend will ultimately be paid for entirely by the
public. Although we are not surprised that a buyer could not be
found, it is regrettable that the Extraordinary Review was not
completed, particularly because the Arbiter expected to publish
his results less than two weeks after the Review was called to
a halt. Not only did the cessation of the Review effectively eliminate
any private sector competition to London Underground's bid to
take over the Metronet Infracos, but it curtailed an in-depth
analysis by the Arbiter of exactly what led to Metronet's cost
overruns and eventual collapse. It is at least possible that the
Review could have pointed out some of the lessons that needed
to be learned from the experience. Nonetheless, the Arbiter's
September report,[114]
along with his draft determination on additional interim payments
of the Infrastructure Service Charge[115]
and the 2006 Metronet performance report,[116]
provide a useful commentary on Metronet's failure.
82. We hope that, in its discussions with Transport
for London as to the future of Metronet's PPP Agreements, the
Government makes full use of the Arbiter's analysis for the partial
Extraordinary Review of Metronet BCV and for a potential Extraordinary
Review of Metronet SSL, and that his insights are utilised to
minimise the chance that further unexpected and wasteful costs
to the public purse might be incurred.
94 Q 309 Back
95
Q 298 Back
96
Ev 74 Back
97 For example, at the London Assembly Transport
Committee evidence session of 11 September 2007. Back
98
Ev 74 Back
99
Ev 74 Back
100
Q 295 Back
101
Ev 74 Back
102
PPP Arbiter, Initial Thoughts, 21 September 2007 Back
103
Q 283 Back
104
Qq 284-285 Back
105
Q 311 Back
106
Q 303 Back
107
Q 305 Back
108
Q 318 Back
109
Q 347 Back
110
HC Deb, 18 July 2007, col 276 Back
111
Q 250 Back
112
"Metronet Rail BCV Ltd withdraws its reference for Extraordinary
Review", Office of the PPP Arbiter press release, 31 October
2007 Back
113
Q 242 Back
114
PPP Arbiter, Initial Thoughts, 21 September 2007 Back
115
Office of the PPP Arbiter, Draft directions on Interim Infrastructure
Service Charge for Metronet BCV, 16 July 2007 Back
116
Office of the PPP Arbiter, Annual Metronet Report 2006,
16 November 2006 Back
|