Select Committee on Transport Second Report


7  CONCLUSION

93. Contracts that were supposed to deliver 35 station upgrades over the first three years in fact delivered 14—40% of the requirement; stations that were supposed to cost Metronet SSL £2 million in fact cost £7.5 million—375% of the anticipated price.; by November 2006, only 65% of scheduled track renewal had been achieved.[125] They have ended in collapse and chaos. It was a spectacular failure.

94. The Secretary of State was adamant that the Government would be working in partnership with the Mayor of London to decide on how best to proceed with the maintenance and upgrade of the Tube system:

    We are not in the business of imposing anything on anyone. I think both the Mayor and I accept there will be private sector involvement in the future, and it is right that there should be, including an element of risk transfer. Quite what the appropriate way of doing that is, as I say, I am open-minded. We need to do the work, we need to understand the state of the assets, we need to understand the cost to the taxpayer and see what interest there is.[126]

It was, of course, the imposition of the PPP on Transport for London—before London Underground was released from central Government control when the contracts were signed—that led us to the present lamentable state of affairs. The future of most of London Underground's upgrade and maintenance work is in doubt and the public, whether as taxpayers or Tube passengers, must pay for the private sector's inefficiency and failure. Any reasonable person, looking at the current situation, would find scant evidence to sustain a dogma that the private sector will always deliver greater efficiency, innovation and value for money than the public sector.

95. While the Government and the Mayor of London negotiate over who should foot the bill for Metronet's collapse, the parent companies are left with relatively modest losses of £70 million each. Metronet itself was little more than a buffer-zone between its parent companies and the obligations of the PPP Agreement. The shareholders were able to reap the rewards of the PPP contracts while Metronet, a company with few assets and little real purpose beyond acting as an intermediary between London Underground and its owners, absorbed all the risk. The Secretary of State told us that the companies concerned had suffered significant "reputational" damage as a result of Metronet's collapse. The Government should bear the Metronet debacle in mind if and when its parent companies—Atkins, Balfour Beatty, Bombardier, EDF Energy, and Thames Water—next come to bid for publicly-funded work.

96. The Government should remember the failure of Metronet before it considers entering into any similar arrangement again. It should remember that the private sector will never wittingly expose itself to substantial risk without ensuring that it is proportionally, if not generously rewarded. Ultimately, the taxpayer pays the price.

97. If the Government is again tempted by a seemingly good deal from the private sector, it should recall Metronet's pathetic under-delivery and the deficiencies in the contracts that allowed it to happen. We recommend that the Government publishes a candid analysis of the events preceding Metronet's collapse and its consequences, both in terms of increased costs to the public and delays to the work programme.

98. It is doubly unfortunate that the product of Metronet's efforts bore such scant resemblance to the expectation of its contracts because information as to the efficacy in principle of this private sector management model has been thoroughly confused. Whether or not the Metronet failure was primarily the fault of the particular companies involved, we are inclined to the view that the model itself was flawed and probably inferior to traditional public-sector management. We can be more confident in this conclusion now that the potential for inefficiency and failure in the private sector has been so clearly demonstrated. In comparison, whatever the potential inefficiencies of the public sector, proper public scrutiny and the opportunity of meaningful control is likely to provide superior value for money. Crucially, it also offers protection from catastrophic failure. It is worth remembering that when private companies fail to deliver on large public projects they can walk away—the taxpayer is inevitably forced to pick up the pieces.

99. Finally, now that the Government is considering the future of the Underground upgrade programme, it should prioritise transparency and clarity to taxpayers and ensure that any future contracts result in clear accountability to national or regional Government, thereby providing the public with the opportunity of applying sanctions in the event of poor performance.



125   Office of the PPP Arbiter, Annual Metronet Report 2006, 16 November 2006 Back

126   Q 352 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008