Select Committee on Transport Written Evidence


Supplementary memorandum from the PPP Arbiter (PPP 01a)

INTRODUCTION

  1.  This submission supplements my initial submission of 27 September 2007 and my oral evidence given on 17 October. It addresses in particular the information available to me in 2005 about the performance of Metronet, and explains further why I consider that some of the subsequent problems could have been mitigated had I been asked to prepare an Annual Report on Metronet in 2005.

  2.  Such a report would have identified:

    —    the scale of the shortfall in delivery by Metronet, in particular on the stations and track programmes;

    —    the emerging projected overspend, which by late 2005 already exceeded the Materiality Threshold for Metronet BCV; and

    —    weaknesses in financial and risk management, and in management of the supply chain.

ROUTINE MONITORING INFORMATION

  3.  I set out my initial requirements for routine information from the PPP Parties in January 2004.[5] These requirements included:

    —    information to enable me to gain a high level understanding of the Infracos' actual and forecast costs and revenues (specifically, the financial models that the Infracos were required to provide to their lenders);

    —    additional information to provide updates of progress on capital works; and

    —    information regarding the performance of the Infracos under the PPP performance regime.

  In addition, I required the Infracos to provide me with the monthly reports prepared for their Boards and, in the case of Metronet, the reports produced for each of the main supply chain contracts.

  4.  During 2004-05 the provision of these items became routine, with information provided to me by the Infracos and London Underground on a 4-weekly cycle, as reported in the my 2004-05 Annual Report.[6] That Report included a high level review of Infraco performance which demonstrated, for example, that Metronet had not delivered into service any of the eight stations due to be completed by 31 March 2005. Additional detail was provided in London Underground's own report,[7] which concluded that "there has been some progress in the delivery of renewals but again this is inconsistent and significant parts of the capital programme are late, particularly for Metronet."

PREPARATION FOR 2005 METRONET REPORT

  5.  Metronet's PPP Agreements include an explicit provision for each Infraco to seek a "definitive statement" as to whether the Infraco has performed its activities to date "in an overall efficient and economic manner and in accordance with Good Industry Practice" or not, in each year apart from the first contract year. If, as originally expected, the contract had been signed before 31 March 2003, the first report by the Arbiter would therefore have covered the period to 31 March 2004; in the event, the contract was not signed until 4 April 2003, meaning that the first expected report would cover the period from Transfer to 31 March 2005.

  6.  The PPP Agreement does not itself require Metronet to make a reference for the annual report. However, under the terms of its agreements with lenders, a waiver is required if the reference is not made by 30 April in each year.

  7.  Given the original expectation was for a report to be produced in 2004, I proposed to Metronet that a "practice run" should be undertaken in 2004 to allow procedures and data availability to be tested in preparation for the 2005 reference. However, I was told by Metronet on 6 April 2004 that the Holdings Board (which principally comprised the shareholder representatives, then under the chairmanship of John Weight) had decided not to cooperate with this exercise as it would be "unhelpful in terms of our longer term objectives of improving Metronet as a business".

  8.  Preparations for the 2005 report continued through 2004, and on 30 March 2005 I wrote to Metronet setting out my proposed approach. This followed confirmation on 23 February 2005 from the then Chief Financial Officer that, subject to confirmation at the March 2005 Holdings Board meeting, it was "highly likely" that the reference would seek directions on Eligible Costs and Eligible Infrastructure Service Charge in addition to the definitive statement. Such a reference would therefore have required me to put a precise figure on the extent to which cost overruns (and revenue shortfalls) to date had been efficient and economic.

  9.  However, on 6 April 2005, I was invited to meet Tim O'Toole and John Weight and was told that they had agreed that Metronet should not make a reference at all. John Weight subsequently confirmed this in writing, attaching a letter to him from Tim O'Toole dated 4 April which set out London Underground's view that "the time and effort required of the contract parties to give [the reference] proper engagement would be better directed to normalising the relationship between us in terms of provision of information, AMS/AAMP[8] development, MPD[9] submissions and commercial resolution of outstanding issues."

  10.  Despite John Weight resigning as Executive Chairman of Metronet within a week of this meeting, the decision not to make the reference stood. Metronet confirmed to me in May 2005 that it had received the necessary waiver from its lenders.

WORK ACTUALLY UNDERTAKEN IN 2005

  11.  In place of the Annual Report reference, Metronet and London Underground agreed to work together during 2005, with my involvement, to prepare for a reference in 2006. I wrote to John Weight on 12 April (the day before his resignation), setting out my view that the agreed work programme should deliver "all the information required, not only by LUL but also by myself, to make an effective assessment of economy and efficiency in line with contractual provisions." My expectation was therefore that there would be a full "practice run", reviewing the whole of Metronet's activities and financial information.

  12.  In the event, the exercise was more limited than this, and concentrated on agreeing the basis for identifying variances in financial projections and reviewing some extracts from the expected 2006 reference submission. Nonetheless, on the basis of this work which was undertaken jointly with London Underground, it became clear by November 2005 that the apparent underspend in the 2005 Annual Asset Management Plan actually represented an overspend above bid levels when contractual variations were taken into account. The increase was well above the Materiality Threshold in the case of Metronet BCV. It was also clear that there were weaknesses in Metronet's financial and risk management, and in its management of the supply chain.

  13.  Had a reference been made for an Annual Report in 2005, it therefore remains my view that this would have identified many of the weaknesses that were set out in the 2006 report. In particular, a 2005 report would have made it clear at an early stage to shareholders and lenders that some of the costs to date had not been incurred by Metronet in an efficient and economic manner, and were not therefore recoverable from London Underground, and that early action was therefore essential if financial difficulties were to be avoided.

November 2007







5   Routine Provision of Information to the PPP Arbiter: Initial Requirements, 19 January 2004, at http://www.ppparbiter.org.uk/files/uploads/g-proceduralFrameWork/200621015756-Provision%20of%20Information%20to%20the%20Arbiter%20-%20Initial%20Requirements%20(19-01-04)%20DM6520v1.PDF Back

6   The PPP Arbiter: Annual Report and Accounts 2004-05, 2 August 2005, at http://www.ppparbiter.org.uk/files/uploads/a-annualReports/2006210163231-The%20PPP%20Arbiter's%20Annual%20Report%20&%20Accounts%202004-05%20(02-08-05)%20DM11266v1.PDF Back

7   London Underground and the PPP: the second year 2004/2005: Report for financial year ending 31 March 2005, 27 July 2005, at http://www.tfl.gov.uk/assets/downloads/LULPPP-Financial-Report-04-05.pdf Back

8   Asset Management Strategy and Annual Asset Management Plan. Back

9   London Underground's Master Projects Database. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008