Select Committee on Transport Written Evidence


Memorandum from the London Assembly Transport Committee (PPP 11)

1.  INTRODUCTION

  1.1  The London Assembly Transport Committee has followed the progress of the PPP contracts since their inception. It conducted two in-depth reviews of performance: "The PPP: Two Years In" and "A Tale of Two Infracos". It has recently questioned in detail the key players in the PPP Administration of Metronet.

  1.2  The Committee has set up a webpage with all the latest information it has gathered on the PPP Administration, and its previous work: http://www.london.gov.uk/assembly/scrutiny/transport_ppp.jsp

  1.3  This paper outlines the conclusions and recommendations that the Committee made in its previous reports, and summarises the information from its recent hearings about the PPP Administration.

2.  PREVIOUS PERFORMANCE REVIEWS

Initial findings—June 2005

  2.1  "The PPP: Two Years In", the Committee's first look at the performance of the PPP contracts, found that Infraco performance was inconsistent and varied. Whilst there were some improvements compared with pre-PPP performance, for example on availability of trains, much of the performance was well below target. Given the inadequacies of the Tube prior to the PPP, as well as the large sums of money made available through the contracts, the Committee was disappointed at the progress that had been made.

  2.2  The Committee identified several problems that raised concerns for the future of the contracts. The rate of asset renewal, which rapidly accelerates after the first 7½ year period, was behind schedule after only two years and subsequently scaled down. Asset renewal is the upgrading of major infrastructure, for example, signalling, lifts, escalators and track. For the planned renewal of lifts and escalators in the first 7½ year period, Metronet revised its figures from 58% to 44%, and Tube Lines from 65% to 51%.[57]

  2.3  Part of the problem arose from the asset knowledge base being so poor prior to the contracts being awarded and the work began: the actual state of the Tube was relatively unknown. Therefore the targets for many projects had to be revised, particularly for track and signalling work, and these have potentially the greatest impact on passengers.

  2.4  There were also early signs of poor project management. The rate of engineering overruns was far too high, 278 in the first two years. This had a frequent impact on the morning rush hour. Overnight and weekend work has been built into the PPP to minimise disruption to the network. However, the marked increase of overruns since the Infracos took over responsibility had the opposite effect. Metronet's former Executive Chair, John Weight, described his company's performance as "unacceptable"[58] to the Committee and resigned shortly afterwards.

  2.5  The Committee also expressed its concerns over the station refurbishment programme. Metronet's performance was particularly bad. Its station renewal programme was 15 weeks behind schedule after two years.[59]

  2.6  The Northern Line, Tube Lines' responsibility, performed particularly poorly for the first two years of the PPP. It had by far the most signal and point-related failures and track delays of any line, and its train availability was almost 40% below the agreed benchmark. The Northern Line's performance was so poor, that Tube Lines suggested full line/branch closures to accelerate the rate of renewal of the track and signalling. Ultimately this was deemed unnecessary, however, as performance on the line improved overall.

Emerging themes—January 2007

  2.7  The Committee's second performance review of the PPP returned to many of these themes. Four years into the contracts and a sharp dividing line between the performances of Tube Lines and Metronet seemed to be emerging. The Committee concluded "Tube Lines has demonstrated that the PPP can work. Metronet has demonstrated that the PPP can fail".[60]

  2.8  Though there were exceptions, Tube Lines management and delivering was generally impressive, and Metronet's was poor. Tube Lines completed its station renewal programme for the first 7½ years ahead of schedule and the Piccadilly Line performed 70% in excess of basic standards. Overall Metronet remained behind in its station renewal programme, though it did improve its rate of completion.

  2.9  The Northern Line, under Tube Lines' management, continued to perform poorly and the Committee found that these were due to a Private Finance Initiative (PFI) contract with Alstom agreed prior to the PPP. The Committee found: "Its terms and conditions are considerably less robust than those set on other maintenance contracts in the PPP".[61] The Committee understood that Tube Lines were renegotiating this contract with Alstom in order to overcome these problems.

  2.10  Many of Metronet's lines, such as the Bakerloo and Victoria Lines performed well below basic standards with frequent delays. There were inconsistencies in aspects of performance between different lines, such as the performance of fleets that were of the same age. For example, the Bakerloo Line had twice as many failures as the Victoria Line, despite the fact that the fleets are the same age. Work to prepare District and Circle Line track for summer conditions had not been adequately done, despite repeated warnings from London Underground.

  2.11  The Committee identified differences in the way that the two Infracos managed their contracts. Tube Lines aggressively pursued its targets through competitive tendering processes and additional spending, and demonstrated impressive results whilst making a healthy profit. Metronet appeared to be blighted by a poor management structure and a lack of market discipline. Much of their work was done by their own shareholders, without competitive tendering. There appeared to be a lack of incentive or a corporate structure to ensure work was done on time and to budget.

  2.12  The Committee found that both Infracos had difficulties over differences of opinion with London Underground over scoping and design for station refurbishments. Final costs were well over what had been forecast and projects were subject to long delays. Tube Lines' approach was to undertake the work that London Underground requested. At the completion of the project, Tube Lines used the arbitration process to negotiate over what they saw as differences to what had been initially agreed and reclaim additional costs. By contrast, Metronet did not start work on stations until all differences had been resolved, leading to lengthy delays. Tube Lines demonstrated that it was able to learn from early difficulties, Metronet did not.

  2.12  In November 2006, the PPP Arbiter delivered his first annual report on Metronet and discussed it with the Committee.[62] He found that Metronet was not operating in an efficient or economic manner and often not to Good Industry Practice (for example, the work done to prepare the District and Circle lines for summer weather). He also discovered a pattern that appeared to show that Metronet was paying its shareholder-suppliers for work that had not been done.

  2.13  The Chair and Chief Executive of the company were appointed from within its composite companies and therefore had a lack of independent oversight. The Committee strongly criticised the poor management structure of Metronet: "A clear line of responsibility and accountability needs to be established between the work done on the ground and those charged with overseeing that work".[63]

  2.14  The Committee made a number of recommendations to improve Metronet's corporate structure. The Committee had previously endorsed the PPP Arbiter's call for a non-executive Chair, which Metronet heeded. The Committee went further and called for Metronet's board to have a majority of independent members to ensure any casting vote was an objective one. It also recommended that Metronet should contract out its station and track work on a competitive basis.

  2.15  The Committee considered the implications of a possible Extraordinary Review. It emphasised that Londoners should not have to bear any additional costs if London Underground was found liable for any of the additional funding claimed by Metronet. Finally, the Committee recommended that the Government prepare for the possibility of stripping Metronet of some of its responsibilities on the basis that the management of nine out of the 12 lines was too much for any company to take on within the PPP contracts.

3.  THE PPP ADMINISTRATION AND THE EXTRAORDINARY REVIEW

  3.1  On 11 September, the Committee discussed the PPP Administration with Alan Bloom, joint PPP Administrator, Tim O'Toole, Managing Director of London Underground and Chris Bolt, the PPP Arbiter. The Committee's key findings from the meeting can be found on the Committee FAQs: http://www.london.gov.uk/assembly/scrutiny/transport_ppp_faq.jsp

  3.2  The Committee has also written to the Administrators for additional information in the light of emerging findings from the Administrators and Arbiter. A detailed breakdown of the drawdowns made on the loan facility are contained in the letter entitled "Further information on the funding costs of the Administration", found under the "related documents" section.

  3.3  The Committee recently wrote to the Administrators (letter dated 24 September which can be found under "related documents" on the website above) seeking further clarification of how the valuation of the companies would fully take account of the Arbiter's recent "initial thoughts" on the Extraordinary Review. In these, the Arbiter had stated that Metronet BCV could be due an increase in the Infrastructure Service Charge (ISC) of between £140 million and £470 million. The Arbiter also found that Metronet SSL could be due an increase in the ISC of between £290 million and £650 million.

  3.4  Such an increase in the income of the companies would appear to have an impact on their value and therefore whether they are attractive to potential buyers. The Administrator told the Committee that Metronet's PPP contracts were its main asset. It appears that an increase in the ISC, as proposed by the Arbiter, would increase the value of these assets. London Underground has stated that it does not believe the contracts will be marketable and that it would therefore like to take the management of the contracts in-house.

  3.5  The Chairman of the London Assembly Transport Committee would be happy to attend one of the Select Committee's meetings on this topic to discuss these issues further.

October 2007






57   "The PPP: Two Years In", London Assembly Transport Committee, 2005, para 2.15. Back

58   Ibid, para 3.6. Back

59   Ibid, para 2.17. Back

60   "A Tale of Two Infracos", London Assembly Transport Committee, 2007, p 3. Back

61   Ibid, para 3.48 Back

62   Available at: http://www.ppparbiter.org.uk/files/uploads/n_guidance/2006112012398LaMR%202006%20final%20guidance .PDF Back

63   Ibid, para 3.31. Back


 