Select Committee on Transport Written Evidence


Memorandum from Transport for London (TfL) (PPP 12)

1.  INTRODUCTION

  1.1  Transport for London (TfL) welcomes the opportunity to comment on the Committee's inquiry into the London Underground Public Private Partnership (PPP). Our response sets out an account of the performance of the PPP since its contract commencement in 2003 and provides some commentary on the recent PPP administration of two of the infrastructure companies, Metronet Rail BCV Limited and Metronet Rail SSL Limited (the Metronet Infracos).

2.  BACKGROUND

  2.1  TfL was created in 2000 as the integrated body responsible for the Capital's transport system. The primary role of TfL, which is a functional body of the Greater London Authority, is to implement the Mayor of London's Transport Strategy and manage transport services across the Capital. London Underground (LU) became part of TfL in 2003 and is responsible for operating the LU rail network. It owns (in part or whole) 250 stations and operates services on 12 lines.

  2.2  Today LU is carrying more passengers than ever before. On 8 December 2006, approximately 4 million passenger journeys were made, the highest number in LU's 144-year history; and in 2006-07 more than 1 billion journeys were made—the highest ever annual number of passenger journeys. Last year also saw the highest ever level of service with 69.8 million train kilometres operated. At the same time the pace of the investment programme continues to increase and is now much in evidence across the Underground network.

  2.3  With London's economic growth gathering pace we anticipate Tube demand to grow by around 25% over the next decade. The benefits of growth will only be experienced if investment is sustained. The direct customer benefit of PPP capacity increases is £12.5 billion with additional benefits to the economy of London as a whole of £20 billion over the contract life of the PPP.

  2.4  As the Committee is aware, despite TfL's concerns about the PPP structure, the Government adopted this as its preferred solution for investing in the Tube. These concerns are a matter of public record and will not be repeated again here. TfL has committed to make the best of the position it inherited.

  2.5  Under the 30-year PPP contracts, the Infracos are responsible for the maintenance, renewal and upgrade of LU's assets—its rolling stock, stations, track, tunnels and signals. LU continues to have ultimate responsibility for safety and is responsible for the delivery of all Tube services. LU manages the PPP contracts, demanding strong performance from Metronet and Tube Lines on behalf of the Mayor and the Government and ultimately the millions who rely on the Tube each day.

  2.6  Imperfect as it is, and despite the high profile failings, the PPP has delivered tangible benefits from the investment in the first four years.

3.  METRONET ADMINISTRATION

  3.1  On 18 July 2007 both Metronet Infracos entered PPP Administration. Metronet's performance had been an escalating concern for LU with the performance disparity between Metronet and Tube Lines becoming ever greater since 2003. In November 2006, the PPP Arbiter published his first Annual Metronet Report. LU's concerns about Metronet's performance were borne out by the Arbiter's findings, which were that "neither Metronet BCV nor Metronet SSL has carried out its activities, over the period from 4 April 2003 to 31 March 2006 as a whole in an efficient and economic manner and in accordance with Good Industry Practice". This conclusion was a major factor in TfL calling for Metronet to seek an Extraordinary Review in February 2007 as the only solution for getting clarity on the cost overruns issue.

  3.2  In June, Metronet requested an Extraordinary Review of the BCV contract, claiming an additional £992 million of cost overruns. Metronet further requested that £551 million of the £992 million be paid in the current period, prior to the conclusion of the Extraordinary Review because of its then current liquidity position. The Arbiter issued a draft direction on the latter request on 16 July to the effect that the Infrastructure Service Charge should increase by only £121 million based on his initial assessment of the appropriate level for the next 12 months for a company performing in an economic and efficient manner in line with Good Industry Practice, but no payment should be made before January 2008 by which time the Arbiter may well have reached a definitive position on all the evidence. TfL maintains that the Arbiter's initial decision assumed facts favourable to Metronet and does not represent a likely outcome based on all the evidence.

  3.3  In the days following this draft finding, both Metronet Infracos determined that they would not be able to meet its obligations as they fell due and the directors of each Metronet Infraco requested that the Mayor applied for the Metronet Infracos to be placed into PPP Administration under the provisions of the GLA Act, which status was granted on 18 July.

  Three of the most serious of Metronet's failings are set out below.

  3.4  First, their basic maintenance performance, which reduced Metronet's expected revenues. In 2006-07 all but two Metronet lines (apart from the Central and Waterloo & City lines), showed deterioration on 2005-06 availability performance (lost customer hours). Performance in lost customer hours across half the Metronet lines were below Metronet's bid expectation.

  3.5  Metronet failed to heed the numerous warnings from LU over basic maintenance. Since 2003, LU had repeatedly called on both Tube Lines and Metronet to focus on basic asset maintenance and reliability in order for the system to withstand the stress brought on by upgrade works. The Victoria line for example has suffered from insufficient attention to maintenance and this has resulted in one of the most reliable LU lines   becoming one of the worst performing.

  3.6  As a result of Metronet's spiralling performance problems, in 2006-07 both Metronet Infracos incurred sizeable financial penalties for their performance against contractual measures (£22.4 million in total). Since the start of the contracts, the two Metronet companies have incurred net abatements of £23.9 million compared to a bid expectation of net bonuses totalling £83.5 million for this stage in the contract. Therefore total Metronet performance adjustments are over £107 million worse than their original plan.

  3.7  The second major failing was Metronet's inability to plan and execute works effectively, as evidenced by their high-profile track failures eg in summer 2006 when they did not prepare the tracks for the summer heat, leading to speed restrictions. This was one of Metronet's most prominent failings which contributed to LU taking the extreme step of issuing an Emergency Direction to Metronet in order to get this and other matters resolved.

  3.8  In addition, Metronet's performance in delivering its station programme was seriously behind schedule and substantially over budget by the end of 2006-07. In both 2004-05 and 2005-06, Metronet BCV failed to complete any of the stations projects due by the original contract date. Only two of the seven projects due in 2006-07 were completed in the year. For the sub-surface contract, whilst eight stations were completed in 2005-06, they were on average 34 weeks late, and the seven stations delivered in 2006-07 were on average 28 weeks late.

  3.9  Thirdly, there were significant structural issues in Metronet's management, that were the root cause of the above and that prevented Metronet from recovering its situation. Metronet's contracting strategy for stations and civils (through the conglomerate "Trans4m") had been the source of criticism for some time due to the lack of competitive pricing and Metronet's subsequent inability or unwillingness to apply the appropriate pressure when programme milestones were missed and costs escalated. Another fault in the contracting strategy, for example, in relation to track and trains, was that the payment provisions did not adequately incentivise performance—in some instances, fixed payments were made which were neither linked to performance nor achievement of milestones. With a myriad of sub-contractors and shareholders involved in the Trans4m organisation and supply chain, effective project management was vital, and fatally lacking. TfL believes that this was one of the fundamental factors behind the companies' cost overruns and ultimate collapse. Metronet was not in charge of delivery of its obligations in any conventional sense, and it lacked even the most basic financial controls and information to address the situation.

  The key events leading to Metronet's insolvency are set out in Appendix 1.

  3.10  Moving forward, the Mayor and the Government are now considering options for ensuring delivery of the commitments set out in the PPP contracts. TfL believes that it is in the best interests of all parties for Metronet to exit administration as soon as possible. TfL believes that this is the best way to maintain the continued safe operation of the Tube network and to mitigate possible performance and financial risks. To achieve this goal, on 24 August TfL lodged with the PPP Administrators a formal Expression of Interest for bidding for the assets of the Metronet Infracos in order that TfL may take control of the operations of the Underground. This would ensure stability for the day-to-day running of the Tube and the ongoing upgrade programme, whilst options for the long-term commercial structure are carefully considered.

4.  OVERALL PERFORMANCE OF THE PPP

  4.1  The Committee noted in its report of March 2005 that "it would be wrong to claim that the PPP had produced no benefits for the Tube". This remains the case. Despite the failings of Metronet and the many frustrations in managing such complex contracts, the PPP has delivered an improvement in the Underground. Since the Committee last considered the Tube PPP and in the last year in particular, the fruits of the investment programme have begun to be seen by passengers and at the same time as there has been a dramatic increase in passenger numbers.

  4.2  61 stations have been completed ("delivered into service") and a further 30 have been declared complete by the Infraco and are under review by LU. In the last year, works to provide step free access at Brixton have been completed, new escalators at North Greenwich have been installed in time to support the opening of the O2 venue, and the new station at Wembley Park proved a showcase, coping admirably with its first FA cup final in May 2007. Over 40 km of track were renewed during the year, the first new Victoria line train arrived on the line for testing and three-quarters of the District line train fleet has been refurbished.

  4.3  It has been well-documented that Tube Lines has been more successful at delivering its investment programme to date. The station programme is on schedule and the Jubilee line 7-car project, adding 17% more capacity to the line, was delivered on time and on budget. This has been followed up by tangible progress on the Jubilee and Northern line upgrades and an improvement in Piccadilly line performance. Some elements of the infrastructure renewal plan are running ahead of schedule. While Tube Lines has been significantly more successful than Metronet, its performance record is not unblemished. In particular, performance of the Northern line has been of concern, leading LU, in December 2005, to issue a Corrective Action Notice (CAN) to Tube Lines. Since issue of the CAN performance on the Northern line has seen some improvement.

5.  CONCLUSION

  5.1  The PPP was not the vehicle of TfL's choosing for the upgrading of London Underground. Imperfect as it is, and despite the failings and frustrations, it has provided a vital investment stream for the Underground.

  5.2  The performance of Tube Lines tells us that the PPP contracts are not unworkable and we believe that Metronet's collapse was predominantly due to that organisation's fundamental flaws rather than failure of the PPP contract per se.

  5.3  As the Committee noted in its last report, ensuring competition within the PPP is crucial in ensuring it can deliver the improvements originally envisaged. Lack of competitive pricing and inadequate contractual incentives within Metronet's own supply-chain was one of the critical factors leading to the cost overruns and ultimate collapse of the two Metronet companies. This will be an important lesson for the future.

  5.4  TfL's first goal in the Administration process which started on 18 July was the continued safe and reliable operation of the Tube network. This has been achieved. TfL expects to submit a formal bid for the assets of the two Metronet companies in order to ensure stability for the day-to-day running of the Tube and mitigation of performance and cost risks. This period will enable the Mayor and the Government to consider options for taking forward the PPP contracts.

  5.5  Tackling the legacy of under-investment is a complex and long-term task which has only just started. It is critical that at this time, when it would be easy to be distracted by the details of the arrangements that will succeed the Metronet Infracos, that the bigger picture is not forgotten. The ultimate goal, and the overriding concern of all of those who rely on it everyday, is the investment in and modernisation of the Tube. Regardless of the vehicle used to achieve this, it is vital that funding for the programme is sustained and that all stakeholders continue to support the aim of a renewed Underground system. Without this commitment, London will not be able to sustain population and job growth to the detriment not only of the Capital but the rest of the UK.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 25 January 2008