Select Committee on Transport Minutes of Evidence


Examination of Witnesses (Questions 65 - 79)

WEDNESDAY 17 OCTOBER 2007

MR BOB RIXHAM, MR BRIAN HARRIS, MR GERRY DOHERTY AND MR ANDY YOUNG

  Q65  Chairman: Good afternoon, gentlemen. Thank you very much for coming. I am sorry to say that Mr John Leach—not the John Leech who graces this Committee but the John Leach who should have been with us from RMT—has unfortunately been taken ill, so we will have to proceed without him. Gentlemen, can I ask you firstly to identify yourselves for the record, starting on my left?

  Mr Young: I am Andy Young, Regional Organiser for the TSSA with responsibility for Metronet.

  Mr Doherty: Gerry Doherty, General Secretary, Transport Salaried Staffs' Association.

  Mr Rixham: Bob Rixham, National Officer for Unite Amicus, section railways, buses and ferries.

  Mr Harris: Brian Harris, Regional Officer for Amicus Unite. I look after Metronet at the moment.

  Q66  Chairman: Thank you very much. Do any of you have anything you wanted to say briefly, or may we go directly to questions?

  Mr Doherty: I understand the inquiry is into PPP, but having listened to the last witness you interviewed and having been back over the research that we have had, can I just say at the outset that we wholeheartedly agree with comments which you yourself made in respect of the last investigation this Committee had, and I do quote: "I welcome the fact that the Government is at last putting real money into the Tube, but I cannot see why it needs the PPP to do it." Nothing has happened since then to have changed their minds, and indeed with the Metronet debacle has only served to confirm our view that PPP was poorly conceived in the first place, it was inappropriate, it was unable to deliver the improvement to the London Underground system and we think what has happened in recent times just bears out our view, and yours.

  Q67  Chairman: Thank you very much. Can we just explore some of the aspects of this? What has happened to safety levels on the network since our last inquiry in 2005?

  Mr Doherty: We have certainly got concerns that safety levels are being undermined by the very structure of PPP itself. Only last month we had emergency brake problems which led to the suspension of the Hammersmith, City, Circle and District lines, and in July hundreds of passengers were stranded and 11 were taken to hospital when three carriages came off the rails between Mile End and Bethnal Green on a westbound Central line tube train. We have sought the views of our workplace representatives with regards specifically to safety and the feedback we have had from one indicates that the main problem is that the contractors do not comply with safety regulations on the Underground, and indeed the auditing by LUL is limited and pressure is put on management and staff to allow the contractors to get on with things and to turn a blind eye. To give you one specific example, one of our safety representatives came across the storage of explosives in Golders Green Station. This is Tube Lines, it is not under the remit of Metronet, but these explosives were stored without any permission and this was resolved following an HMRI investigation, but what we actually found was unauthorised storage of detonators at Golders Green Station without licence. Our concern is not that specific incident, because I am certain that the media—and I did some media interviews this morning—is concerned that in light of the terrorist attacks in recent times on the Tube that is a danger in itself. We do not think in itself it was a danger, but what it does do is it says to us that safety standards are slipping under PPP—and this is not Metronet, this is Tube Lines.

  Q68  Chairman: Unite actually said in their evidence that a lack of "joined up thinking" could have been to blame for the incident on the Central line on 4 July 2007. Do you want to tell us a bit about that?

  Mr Rixham: Yes. Some debris was left on the line by contractors. I think the reports we are getting back about that incident and others is the lack of communications between the various contractors undertaking the work. This repeats itself over and over again.

  Q69  Chairman: What are we talking about, Mr Rixham, when you say something like "over and over again"?

  Mr Rixham: We are told by the shop stewards that you have got companies which work in isolation and they tend not to share information with the other companies or communicate with other sectors of workers, and that seems to be a general problem not with just one of the groups but, as I say, across the range of contractors.

  Q70  Chairman: Mr Doherty, I should have asked you, what length of time was there before you got an immediate response to your Health & Safety officer on that particular one at Golders Green?

  Mr Doherty: It was discovered on 17 September, so we are a month away from it now, and I have to say that Tube Lines have dealt with it. Our concern is what else is out there that we have not found.

  Chairman: I am sure that is an interesting point.

  Q71  Mrs Ellman: In the evidence we have got from the Office of Rail Regulation they say that as a result of the PPP rail defects are now more likely to be detected before they become rail breaks and that there is no indication that the PPP has had a detrimental effect on rolling stock maintenance. Is that a finding you would agree with, or is it something which surprises you?

  Mr Rixham: I do not think we would oppose that on rolling stock maintenance. We have said in our evidence that we have not provided anything on that, so we would accept that to be the case. Just going on to our evidence, before we move off to Health & Safety, we have also indicated the incidents in March 2007 when 12 electricians were actually found on site to be working over and above—they had been working all week and then coming on to Tube Lines to actually do additional work, and they were thrown off, so it is a lack of control over people working on the contracts.

  Q72  Chairman: Can we establish what the circumstances were? Are you saying they were working beyond the hours they would be expected to work?

  Mr Harris: It was a group of individuals who had done already a shift of work on day shift for a company and had then been found to have come on for another subcontract company to work the night shift on the Underground, and for us that breaks any Working Time Directive, the length of time, it breaks safety regulations, et cetera, and that for us is not acceptable.

  Mr Doherty: Just to answer your specific point, Mrs Ellman, on the train maintenance, I did indicate that it was only last month that emergency brake problems led to the suspension of the Hammersmith & City and the Circle and District lines, and that is directly attributable to maintenance of the trains, not of the track.

  Q73  Chairman: Is there any other incident? That is a major incident, but is there any other incident which comes to mind at the moment?

  Mr Doherty: Not that comes immediately to mind, Chairman.

  Q74  Mrs Ellman: Are there any problems with communications on reporting concerns or faults with the Infracos or the Underground?

  Mr Harris: I think the basic problem we have with the structures that exist is that the structures with the Infracos themselves, with Tube Lines and with Metronet, on safety are set up as per the London Underground systems previously and where those are working—I say that in a loose form—it takes an awful lot of time to get minor concerns driven through and safety changed quickly because of the disjointed nature of management within the companies. Where there is an emergency situation, such as the brake failures, then that is dealt with quickly because quite clearly that is a major safety concern and it is in the public eye, but where we have a major problem is in the systems which are in place. They just do not work. The lack of communication between the companies and the contractors where you may have a gang who are a contract gang working on a repair who are not employed and under the control of the foreman from Metronet or Tube Lines and there seems to be a lack of communication or communication systems to enable safety to be taken seriously.

  Q75  Mrs Ellman: Is that problem being addressed?

  Mr Harris: That problem in terms of the problems with Metronet, in my experience of working with the company on a day to day basis, no, because if you look at the history over the past six to eight months of what we have been doing as a body of employees working within the company is that we have lurched from one crisis to another in terms of issues which the company raised. First of all, we had an issue with the fleet transfer, which basically was a transfer of up to 1,000 people initially to Bombardier, who then lurched from that, once that was resolved, to a reorganisation which could have resulted in over 700 people losing their jobs. We then lurched from that and in the middle of that straight into PPP, which is where we find ourselves now. So we have been trying to work these things through, but I think the management's priority has been elsewhere and what has resulted is that safety has been put on the back burner and has been let go in the medium term.

  Mr Young: There were just two quick points I was going to make. Firstly, to go back to the explosives detonators issue at Golders Green, the safety rep for a TSSA who was looking to deal with that situation, when he came upon it, actually had some real problems about who to address the issue to because it was a Tube Lines storage area, if you like, but on a London Underground station. So there were real issues about who to report it to and ultimately resolution was by him writing to the HMRI, which cut through those kinds of problems.

  Q76  Chairman: Has anybody done an audit of similar circumstances where the lines of communication are not clear?

  Mr Young: Not to my knowledge. The other point I was going to make is that it struck me—and I am relatively new to the industry—at the Health & Safety committees for London Underground the Infracos are not represented at the highest level at the company Health & Safety committee.

  Q77  Chairman: You have made that point, presumably?

  Mr Young: Yes. There are inevitably some issues there. That lack of communication is almost built into the system.

  Q78  Chairman: Has there been a report from the HMRI on that?

  Mr Young: There was into the Golders Green situation, yes, which made recommendations for Tube Lines.

  Q79  Mrs Ellman: But on the other point of not being represented, has anything happened on that?

  Mr Young: I think the argument that LU and the Infracos would make is that they are involved in different structures, but it has struck me that when we go there—and one of the issues we were discussing, for example, last week at the Health & Safety Council, and that is the highest level within London Underground—a lot of the issues related to lack of consultation, lack of involvement of our safety reps, related to issues with Tube Lines or Metronet, and obviously London Underground management then have to undertake to go away and talk to them, et cetera. So it is bound to add in an extra element of complication.


 