Sub-Committee II visited the University of Durham to look into the challenge of achieving energy efficiency in a historically sensitive and fragmented estate. Members attending were: Lord Lewis, Lord Paul, Baroness Perry (Chairman) and Baroness Sharp. In attendance: Dr Christopher Johnson (Clerk) and Dr Jonathan Radcliffe (Specialist Assistant).

Sir Kenneth Calman, Vice-Chancellor, welcomed Members to the University of Durham. Peter Robinson, Director of Estates and Buildings, and Dave McCaffery, Engineering Services Manager, gave a presentation to the Sub-Committee, followed by a tour of parts of the University, including Durham Castle, Palace Green Library and Hatfield College. During the day, significant points raised included:

The University Estate was spread over 212 hectares, consisting of 217 buildings built between 1076 and 2004, with Durham Castle designated as a World Heritage Site. The large size and the fragmented and historical nature of the estate imposed limitations on the energy efficiency measures that could be implemented. They also meant that the task of upkeep was hugely expensive—the total cost of the Estates backlog maintenance was estimated at over £80 million.

The University's efforts to improve energy efficiency had largely been pursued in isolation. If anything, the attitude of the Local Authority and other agencies had been unhelpful. The Local Planning Authority and English Heritage had imposed severe restrictions on changes that could be made to some historic buildings to increase their energy efficiency. Secondary glazing has not been permitted as it would alter the external appearance. There had also been objections to the installation of roof insulation in some areas, although in less sensitive areas it had, where possible, been applied. In addition, the Sub-Committee was told that the Heritage Lottery Fund would not support refurbishment of the Castle, on the basis that the building was used for student accommodation.

The district heating scheme, which dated from the 1950s and 1960s and served buildings on the Peninsula, was being decommissioned due to high running and maintenance costs. The high cost of laying modern pipe work to carry hot water, and the very limited demand for heat within the confines of the Peninsula, had ruled out a new district heating or combined heat and power scheme. Instead, high efficiency gas boilers were being installed locally.

The Estates and Buildings Department of the University had introduced an energy efficiency improvement plan. An energy management system was used to monitor electricity and gas consumption, with most buildings covered by a sub-meter. Case studies showed significantly reduced energy use and costs. For example, the regulation of fans drawing gases from fume cupboards in the Chemistry Building had saved £6,000 a year, with a payback period of 10 months; the upgrade and improvement to the lighting system in the Main Library Building had a projected annual saving of £24,000 and a three-year payback period.

The University, with energy costs of £3.5 million, had made budget provision (subject to approval) to employ a dedicated Energy Manager. The Engineering Services Manager, currently responsible for energy, could only dedicate about 20 percent of his time to these matters.


 