Examination of Witnesses (Questions 200
- 219)
200. MR ELVIN: Mr Thornely-Taylor, would
it be worth jumping ahead because you have got two slides that
illustrate this? If we come ahead to slide 48, we have got an
example of resilient rail support.[75]
(Mr Thornely-Taylor) This is a form of rail
support that is becoming more and more popular. I am not saying
necessarily Crossrail will use it, but it is a good example of
modern rail support. Instead of the rail sitting with the foot
resting on a wooden block, there is an air space underneath the
rail foot and the rail is supported by means of rubber blocks,
one either side of what is called `the web', and those blocks
are held in place by shoulders. The sheer stiffness of the rubber
blocks is low, so the rail deflects under the passage of a train
and there is no rigid mechanical connection whatever between the
rail and the supporting concrete beneath. For most railways, for
most receivers of groundborne noise, that alone is enough to bring
noise levels well below the 40 figure that I mentioned previously,
but there are circumstances where you need to do better than that
if you are either running under a very sensitive building, like
an important concert hall or a recording studio or MPs' offices.
Portcullis House has the District Line running through its basement
because, when the Jubilee Line Extension to Westminster Station
was constructed, the District & Circle Line was completely
reconstructed and the District & Circle Line station is completely
new and is in fact a large bridge suspended over the huge void
of the Jubilee Line Extension station. Through Westminster Station
there is floating slab track where the rails are attached to the
concrete block which itself is supported on rubber bearings.[76]
That one was my design. I regret one thing which is that I chose
to omit additional resilient support between the rail and the
concrete block and, if you stand on Westminster Station when trains
come in, they do rumble as they run onto the floating slab. They
would not do that if there were also resilient support between
the rail and the concrete as well as the bearings between the
concrete and the structure, but I have failed to find anywhere
in Portcullis House where you can hear trains. I hope that is
still the case. There was a very exacting specification for that
piece of work and, unless I am informed otherwise, it continues
to be extremely successful. There are obviously engineering cost
consequences to floating slab, but there are important sections
of Crossrail that will have it for reasons which we will go into
later in the proceedings.
201. LORD YOUNG OF NORWOOD GREEN: As
one supplementary to that, and that was very helpful, but this
is the Thornely-Taylor floating slab actually!
(Mr Thornely-Taylor) It is actually.
202. The one other question I wanted to ask
you was about the design of the tunnel itself in terms of preventing
transmission of noise and vibration. Is that a factor? Can you
do anything with that?
(Mr Thornely-Taylor) It is not a very large factor. Many
of the old tunnels are made of cast iron and modern tunnels are
bolted concrete segments and the additional mass and rigidity
of the concrete is beneficial, but most of the improvement is
in the resilient support of the track.
203. LORD SNAPE: If we followed the French
example, Mr Thornely-Taylor, and put rubber tyres on some of the
trains, would it put your future job prospects in peril?
(Mr Thornely-Taylor) It would. I actually think my job prospects
are in peril anyway because it is now quite normal for an urban
underground railway to use resilient rail support, and you will
have very low groundborne noise levels without trying so long
as you do not mess it up. I used to spend vast amounts of time
predicting noise levels from underground railways where it is
no longer really necessary because it is a foregone conclusion
that levels will be very low.
204. LORD SNAPE: And the French rubber
tyres?
(Mr Thornely-Taylor) French rubber tyres do almost eliminate
groundborne noise, but have a massive cost and engineering penalty
attached to them, not least that it is difficult to run them to
Reading and Shenfield and Abbey Wood.
205. MR ELVIN: I was going to ask about
how you put rubber tyres on the Great Western! When you say that
your job prospects are in peril, unless the resilient rail is
messed up of course, there are design issues also in that it requires
proper maintenance and inspection?
(Mr Thornely-Taylor) Yes. It is quite possible to mess it
up and there are some examples of non-functioning resilient rail
support. I will not actually give them, but it is also possible
through neglect to let the rails acquire surface roughness which
is so great that noise levels rise quite dramatically and it is
of great importance that, along with the basic engineering design
of the railway, there is a maintenance policy to grind the rails,
for example, when the roughness grows. My Lord Chairman was kind
enough to credit me with devising the London City Airport noise
conditions, and I also wrote the noise policy for the Docklands
Light Railway which has a system for detecting when it is necessary
to grind the rails and when it is necessary to turn the wheels.
I will be guided by Mr Elvin as to how we are doing for time and
whether I should go back to the slides we have bypassed.
206. You are 20 minutes over estimate and on
slide 37, but let us just see how we go.[77]
(Mr Thornely-Taylor) Slide 37 is continuing
the story of the maximum noise level. I explained earlier on that
there were two types of LAmax, slow and fast, the fast in the
days when we were looking at a moving needle and the needle was
jiggling about, and with the slow the needle was damp to make
it easier to measure a single figure. For an underground train
passing under a building, if you measure it in both units, you
will find that they are two different, so, if you measured 40LAmax,S,
it would come out at about 42LAmax,F, and that compares with the
LAmax,F guideline value for bedrooms at 45, coupled with the advice
that it should be lower for low-frequency noise.
207. If we just put up the actual page of the
guidance, I hope that is legible at least on the screens, if not
the main screen.[78]
(Mr Thornely-Taylor) This is an extract from
those guidelines and I will read from paragraph (c): "Sources
with low-frequency components. Disturbances may occur even though
the sound pressure level during exposure is below 30dB(A). If
negative effects on sleep are to be avoided, the equivalent sound
pressure level should not exceed 30dB(A) indoors for continuous
noise. If the noise is not continuous, sleep disturbance correlates
best with LAmax", and it becomes clear later that it is LAmaxF
that is being referred to, "and effects have been observed
at 45 dB or less. This is particularly true if the background
level is low. Noise events exceeding 45 dB(A) should therefore
be limited, if possible. For sensitive people, an even lower limit
would be preferred. It should be noted that it should be possible
to sleep with a bedroom window slightly open", and this is
irrelevant for groundborne noise because obviously it does not
come in through windows, but for surface noise, "(a reduction
from outside to inside of 15 dB). To prevent sleep disturbances,
one should thus consider the equivalent sound pressure level and
the number and level of sound events. Mitigation targeted to the
first part of the night is believed to be effective for the ability
to fall asleep." There are lots of passages of that kind
of detail in the guidance which one can refer to, but I think
that sums the current topic up for present purposes. Slide 38,
if we are talking about underground trains passing during the
night period, we are interested in LAeq as well as LAmax, as those
guidelines were suggesting we should be.[79]
A typical example for the Crossrail case would be 78 trains in
the night period and they will be 200 metres long. If we assume
we are going, as they will be in a lot of areas, at 80 kph, 40
LAmax,S comes out as about 24 LAeq 8 hour, whereas the eight-hour
LAeq in the WHO guidance table we have been looking at is for
30, or BS 8233 says 30LAeq 8 hour is a good standard and 35 is
a reasonable standard.
208. So, if it comes out at 24, that indicates
that it is doing better than good?
(Mr Thornely-Taylor) It is indeed.
209. What if it said that for at least a proportion
of that eight-hour LAeq it is unlikely that trains will be running,
ie during the night?
(Mr Thornely-Taylor) We then have a difficulty in that we
do not know what guidance to turn to because the only guidance
on night-time LAeq in both the World Health Organisation document
and BS 8233 is in terms of the eight-hour value, but, if you double
the number of trains or compress all those trains into half the
time, it would go up from 24 to 27 and, if you compress them all
into quarter of the time, it would go up to 30. I think the current
intention is that Crossrail trains, revenue trains, will cease
at about 12.30 and start again at about 5.45 with some empty trains
going to and from the depot in between, so, of the eight-hour
night, about two and three-quarter hours are normal revenue service
with some trains in between, so, even if you did find guidance
which dealt with night in hour periods other than eight, we still
would be significantly below 30. If we move on to slide 39, we
see what the Environmental Statement bases its conclusions on.[80]
The significant threshold in the Environmental Statement is 40
dBLAmax,S and the conclusion is that there is no significant effect
from groundborne noise. It draws on a specialist technical report
which includes a full set of contours of groundborne noise from
tunnel portal to tunnel portal. This particular example is for
Central London, and that is Soho Square there, Tottenham Court
Road Station, so, as trains are travelling relatively fast between
stations, the lowest contour plotted is 25, though it is quite
hard to see, but the outer contour is 25 and the most we get up
to is in the 30s and, as the trains slow down, the contours disappear
off the map, so to speak. The essential thing is that the same
track form is assumed from end to end, except for locations where,
for the reasons I have alluded to, we need floating slab, but
it is not going to be the case that the track form will be degraded
wherever the prediction is for much less than 40, so we will not
suddenly go back to rigid rail support just because we are well
below 40. A track form will be used for the same kind, chosen
to achieve 40 in as many places as possible, as a result of which
in a lot of other places these contours show much, much lower
levels than the overriding 40, design A.
210. LORD BROOKE OF ALVERTHORPE: Forgive
me, just very quickly to go back to the previous slide, 38. The
running time is 12:30?
(Mr Thornely-Taylor) Revenue service trains, the trains with
passengers on them, I think it is true to say, taking Tottenham
Court Road as an example, the last one will have gone by about
half past midnight and there will not be another one until about
5.45. During that period half a dozen or so trains will be moving
to and from depots.
211. LORD BROOKE OF ALVERTHORPE: We are
planning ten years ahead not to change anything?
(Mr Thornely-Taylor) I am not an expert on those matters,
my Lord.
212. MR ELVIN: To some extent the level
of service will be predicated on the Access Option in due course.
(Mr Thornely-Taylor) We move from underground operational
noise to the operation of plant on the surface. If we go to slide
40, here we bring in a new standard called "4142" which
is used for all kinds of noise of an industrial or commercial
nature.[81]
To be specific, it applies to noise from factories, industrial
premises, fixed installations or sources of an industrial nature
in commercial premises. The most important application of it for
Crossrail is for what is called loosely "fixed plant tunnel
ventilation fans". Being the biggest example of fixed plant,
the fans on all underground systems are very large. Those on Crossrail
will be substantially larger than they are for underground lines
because we are dealing not with an underground line, we are dealing
with a main line in a tunnel with major consequences from that.
There is a procedure set out in this British Standard. It is intended
for predicting the likelihood of complaints and it does it by
using LAeq but with a penalty of five notional decibels added
to the physical level of LAeq if the noise has special characteristics.
One of those characteristics is what is known as "tonal characteristics"
and you almost always get tonal characteristics with sources such
as fans. You compare it with a completely new index that I have
not talked about yet called LA90, so the same family as the L10
I touched on in the context of highway noise, it is the level
of noise exceeded for 90 per cent of the time. It is really measuring
the quiet bits between noise events. If you are standing out in
the street and it is not heavily trafficked, vehicles going by,
aircraft going overhead and you wait for a quiet moment and you
measure it, that is probably close to L90.
213. MR ELVIN: Is that what is sometimes
loosely referred to as background noise level?
(Mr Thornely-Taylor) It is and it is illustrated in slide
41.[82]
If you perform a statistical analysis on this varying ambient
level, the L90 comes out more or less a typical low value, it
is not to say occasionally it gets quieter than L90, but it is
a typical low level and it is against that level that the LAeq
plus five, if it is a tonal noise, is compared in the BS 4142
process. In slide 42 the standard concludes that if LAeq plus
five, called the rating level, should differ from the L90 plus
ten that is an indication that complaints are likely.[83]
If it should differ from LA90 by plus five it is marginal as regards
complaints and, going to the other extreme, if it is ten below
the L90 it is a positive indication that complaints are unlikely.
The reason for that is if a sound is ten dB less than a background
level it is effectively inaudible. Moving on to slide 43, we come
to construction noise as the first of the sequence of slides I
have on mitigation, the ways in which noise is controlled and
reduced.[84]
Starting again with construction noise, it is controlled primarily
by methods of working and modern plant. Construction plant has
fallen in noise level significantly in the past couple of decades
since BS 5228 was first written and extensive use of noise barriers,
enclosures of noisy machinery, monitoring and management of construction
noise is vital, but if all that still leaves levels above the
relevant thresholds there is a noise insulation policy and the
temporary re-housing policy. The line at the bottom is crucial,
the Control of Pollution Act 1974 introduced a system of controlling
construction noise. Section 61 of that Act provides for the voluntary
application for a consent for construction works, which is devised
to bring about the use of the best practical means to minimise
noise, and a local authority can grant consent or grant it with
conditions and, having done that, it becomes an offence to exceed
or to contravene the terms of the consent. It is part of the Crossrail
scheme that all construction sites will be subject to section
61 applications and, therefore, controlled in this way.
214. LORD BROOKE OF ALVERTHORPE: If it
cannot be kept, can people be compensated?
(Mr Thornely-Taylor) The only form of compensation is through
the payment for the installation of noise insulation or financing
the cost of temporary re-housing.
215. LORD BROOKE OF ALVERTHORPE: Not
for disturbance?
(Mr Thornely-Taylor) There is no simple --- There is another
session on compensation, I would not presume to be a compensation
expert, but I can say within the noise scheme there is no payment
of money other than for physical mitigation of the kind that I
have described. Slide 44 deals with vibration.[85]
The vibration is not susceptible to noise barriers and enclosures,
it can be controlled by methods of working, the timing of events
that might cause vibration annoyance and particularly monitoring
and management of any vibration that might cause harm to buildings
or sensitive equipment. Interestingly, vibration is considered
as noise as far as the Control of Pollution Act is concerned and
the section 61 consent will deal with vibration in just the same
way as it does noise. Moving to slide 45 surface railway noise
will be mitigated by noise barriers, noise insulation where eligibility
arises and, of course, given my comments about the importance
of the rail running surface and the wheel tread condition, maintenance
is also an important method of mitigating operational noise.[86]
Going underground again, slide 46 [87]
216. MR ELVIN: I think we have already
anticipated
(Mr Thornely-Taylor) We have just about done that, I think,
and slide 47.[88]
It is important to bear in mind that all the predictions show
vibration that is perceptible not by the hearing but by the technical
sense of touch, it is body movement we are talking about, disappears
altogether in modern underground railways. The old fashioned railways
with the direct fixed rails often produce both rumble and physical
vibration, you either feel it or if there is a chair with its
back against the wall and you hear the chair buzzing against the
wall as the structures vibrate, that kind of vibration is universally
predicted to disappear from the environment above modern underground
railways as a consequence of the improvement in the track support
system. We have seen the next two slides, the picture of the rail
support and the floating slab, so we jump to slide 50 and we are
very nearly at the end.[89]
The fixed plant I was talking about, the mitigation is by the
fitting of things known as "noise attenuators", loosely
called "silencers" on fans. They are very large units,
particularly for the enormous fans that we find on Crossrail and
the acoustical engineering of plant installations is a well understood
discipline and it is possible to reduce noise by design. That
brings us to an end of the mitigation section. I have just got
a few slides to talk about prediction methods and the uncertainty
associated with them, given that we do rely on prediction in the
planning of the railway. Slide 51, construction noise being an
important potential impact, it is important to have an idea as
to how accurate the predictions one makes will be and when the
Crossrail scheme was first promoted in the early 1990s the Jubilee
Line Extension was under construction and there were some major
work sites, not just Westminster that I have already referred
to but Canada Water and Canary Wharf.[90]
The then Crossrail project financed a study of those sites to
compare measured construction noise levels with predictions made
using a variety of different approaches. The uncertainty was found
to be confined within a limit of about 3 dB(A), which is actually
a reassuring conclusion, and given that DS 5228 includes some
basic noise information which is now very old, it is quite common
to find construction sites that are much quieter than predicted.
Slide 52 again is about prediction methods, this time surface
noise.[91]
There is a statutory procedure for doing that, produced to accompany
the railway noise insulation regulations. Because of the importance
of track quality, as we have been discussing, Defra commissioned
a study to look at the influence of track conditions on the predictions
you get and that recommended what it calls "a back end correction"I
see that I failed to get the "n" into "speed dependent"it
suggests that there should be a correction of two and a half dB
for 100km/h for average variation in the acoustic quality of the
track. Slide 53, the fixed plant I have been talking about.[92]
There are standard procedures in the mechanical services industry
for predicting received noise level at sensitive locations and
the uncertainty associated with that process is built into the
base assumptions and the prediction method that is used. Penultimately,
slide 54, underground noise is predicted by simulating the running
of the train in the tunnel numerically.[93]
When Mr Elvin introduced me he referred to a finite difference
computer package called "Findwave" which has been used
in the preparation of the Environmental Statement and all predictions
of groundborne noise which actually in a numerical form simulates
with the passage of time in very tiny increments of small time
steps the movement of a train over the rails on their resilient
supports on the concrete in the base of the tunnel, including
the tunnel wall, the different kinds of soil around the tunnel
and the nature of the buildings above. There is uncertainty associated
with it, there is a validation report in the specialist technical
report, but the important consideration is that, although in detail
there can be uncertaintyand slide 55 continues this topicthe
prediction can come up with a peak in the noise at slightly the
wrong frequency.[94]
There can be uncertainties of that kind, but because we use high
level indicators like dB(A) or NC curves when we are dealing with
recording studios, they effectively remove the sensitivity of
the results to small errors in the prediction such as peaks being
at the wrong frequency, you still end up with a very similar high
level index value such as a dB(A) level. We did extensive studies
on the uncertainty of this prediction method, as a result of which
the actual model outputs used for the Environment Statement and
subsequent predictions have all had five dB(A) added to them for
uncertainty so where, for example, there is a prediction of 40
dB LAmax the computer output actually said 35. That, my Lords,
completes all my slides. I hope I have covered everything that
is of interest, but I would be glad to expand on anything that
I have not.
217. CHAIRMAN: Do any of my colleagues
have any further questions?
218. BARONESS FOOKES: Could I raise very
briefly something totally different. You referred to the impact
on the human ear and its range of sounds; it is quite different
for animals. I am wondering about the impact on domesticated animals
and maybe living with human beings affected or not affected by
these noises?
(Mr Thornely-Taylor) It is true to say that animals are affected
in slightly different ways from humans, their hearing organs are
different. Some of them can hear to higher frequencies, as we
all know. In general, all the research into the effect of noise
on animals shows them to be remarkably unaffected by noise unless
there is a startle component to it. Sudden noises cause fright
but, as you approach Gatwick Airport, you see a field of sheep
grazing quietly in the field on the left as you go down the road.
It is quite difficult to find any research results other than
startle effects on animals. I think, in general, there is not
a particular need to treat them differently from humans in that
respect.
219. BARONESS FOOKES: That is all I needed
to know. Thank you.
75 Crossrail Ref: P4, Mitigation-Operation-Groundborne
Noise and Vibration-Resilient rail support (example) (LINEWD-RTT01-048) Back
76
Crossrail Ref: P4, Mitigation-Operation-Groundborne Noise and
Vibration-Floating Slab (example) (LINEWD-RTT01-049) Back
77
Crossrail Ref: P4, Standards-Operation-underground railway (LINEWD-RTT01-037) Back
78
Crossrail Ref: P5, World Health Organization 1999, Guidelines
for Community Noise , p46 (SCN-20080219-001) Back
79
Crossrail Ref: P4, Standards-Operation-underground railway (LINEWD-RTT01-038) Back
80
Crossrail Ref: P4, Crossrail contours of predicted groundborne
noise LAmax,s (LINEWD-RTT01-039) Back
81
Crossrail Ref: P4, Standards-Operation-Fixed Plant (LINEWD-RTT01-040) Back
82
Crossrail Ref: P4, Standards-Operation-Fixed Plant (LINEWD-RTT01-041) Back
83
Crossrail Ref: P4, Standards-Operation-Fixed Plant (LINEWD-RTT01-042) Back
84
Crossrail Ref: P4, Mitigation-Construction Noise (LINEWD-RTT01-043) Back
85
Crossrail Ref: P4, Mitigation-Construction Vibration (LINEWD-RTT01-044) Back
86
Crossrail Ref: P4, Mitigation-Operation-Surface railway noise
(LINEWD-RTT01-045) Back
87
Crossrail Ref: P4, Mitigation-Operation-Groundborne noise and
vibration (LINEWD-RTT01-046) Back
88
Crossrail Ref: P4, Mitigation-Operation-Groundborne noise and
vibration (LINEWD-RTT01-047) Back
89
Crossrail Ref: P4, Mitigation-Operation-Fixed Plant (LINEWD-RTT01-050) Back
90
Crossrail Ref: P4, Predictions (LINEWD-RTT01-051) Back
91
Crossrail Ref: P4, Predictions (LINEWD-RTT01-052) Back
92
Crossrail Ref: P4, Predictions (LINEWD-RTT01-053) Back
93
Crossrail Ref: P4, Predictions (LINEWD-RTT01-054) Back
94
Crossrail Ref: P4, Predictions (LINEWD-RTT01-055) Back
|