Examination of Witnesses (Questions 360
- 379)
360. Slide 10 illustrates the effect of depth
of tunnels.[43]
What is plotted here is the settlement in millimetres down on
the left-hand scale. We can see here the difference between two
tunnels and each of them for this example are five metres in diameter.
The tunnel at 20 metres depthshown in pinkfor a
volume loss of one per cent would produce a maximum settlement
of eight millimetres at the ground surface. The form of the settlement
trough is shown shaded in pink. If the tunnel was deeper, at 30
metres rather than 20 metres, then the magnitude of settlement
reduces to a maximum of five millimetres settlement at the ground
surface but a wider trough. The effect of the settlement is over
a wider area albeit a smaller magnitude of settlement.
361. Slide 11 illustrates the effect of tunnel
diameter.[44]
If we consider two tunnels at the same depth, in this case 30
metres, this is the same plot of settlement in millimetres, we
see here that if it was a five metre diameter tunnel, which was
what we used in the previous example, the maximum settlement would
be five millimetres at the ground surface, but if it was a seven
metre diameter tunnel the maximum settlement would be higher,
it would be doubled to ten millimetres. It is still a very small
amount of settlement, but this illustrates the difference between
a five metre diameter tunnel and a seven metre diameter tunnel.
362. Slide 12 moves on to tunnelling methods.[45]
This is a photograph of a tunnel boring machine abbreviated as
TBM. This was a machine used for the Channel Tunnel Rail Link.
It is an eight metre diameter tunnelling machine. The typical
running tunnels for Crossrail would be seven metres, somewhat
smaller than this but of similar size. This is a closed face earth
pressure balance machine. I will be describing that in more detail
shortly. What this really means is that the soil at the tunnel
face is always supported at all times. This is the big cutting
wheel that is turning with cutting teeth on it to actually cut
the soil, but all the time there is a pressure maintained on the
soil.
363. Slide 13 indicates the way in which many
of the running tunnels will be lined.[46]
This is using pre-cast reinforced concrete segmental linings.
In other words these are made up of a number of pieces, all of
which are produced in a factory and then brought to the tunnel
site and are erected in the tunnel to form a ring to support the
ground. This is a view of the eight metre diameter completed tunnels
for the Channel Tunnel Rail Link.
364. Slide 14 goes into a bit more detail and
I will explain this.[47]
What you will see here is a longitudinal section through a typical
modern closed face earth pressure balance machine. Number 1 on
the left-hand is the cutter head, that is the big wheel that I
showed on the photograph just a few minutes ago. I want to draw
your attention to number 3 which is the TBM, the tunnel boring
machine skin. That is effectively a cylindrical steel shield within
which much of the operation of the tunnelling is carried out.
So it is a protective cylindrical steel skin that goes all the
way back to this position here. The soil and the water under high
pressure come through the cutting head into a chamber behind in
which the pressurised soil and water passes into that chamber
and then the way in which the pressurised soil and water is extracted
is by means of the screw conveyor shown here as number 5. In effect
this is a steel cylinder, typically about a metre in diameter,
within which there is something rather like a tight fitting corkscrew.
The pressurised soil and water passes up the screw conveyor and
emerges at this position 7 onto a conveyor belt and is taken off
down the tunnel. This is a very crucial part of the operation
of the earth pressure balance machine. It allows the high pressure
soil and water to be removed and then to emerge at ordinary atmospheric
pressure. You also see in this same slide the lining segments
which are shown in position. You will see that the most recent
lining segment is actually erected inside the tunnel boring machine
skin, the steel shield I described earlier.
365. The next slide, Slide 15, shows a view
looking from further back towards the front of the tunnelling
machine operation.[48]
You will see here some tunnel lining segments waiting to be taken
up to the machine to be erected. To give you an approximate idea
of the size, this would be about three metres from left to right
in this photograph. The segments are large pieces of reinforced
concrete.
366. The next slide shows the segments actually
being installed during a tunnelling operation for the Channel
Tunnel Rail Link.[49]
What you can see here on the left-hand side is a completed ring
of segments and then to the right you can see one of the segments
that has been placed inside that steel TBM skin I described and
there are jacks here which are used. The machine is actually pushing
itself off the recently erected tunnel lining segments. As it
moves forward then the ground comes into contact with the tunnel
lining.
367. Slide 17 shows a quite different means
of supporting the ground and this is using the technology of sprayed
concrete.[50]
In cases where the ground is competent and strong enough, as in
the London Clay area, to stand at least temporarily unsupported
this is a very versatile technique. Out of this nozzle you can
see a mist and coming out of that nozzle is concrete which is
being sprayed onto the ground surface that has just been exposed
due to the excavation and it is operated by the operator back
in the cabin who has control of many aspects of the spraying process.
The essence of the process is that the concrete goes hard extremely
quickly, it has special additives to make it do that and it means
that within a matter of some minutes after being sprayed onto
the ground surface it starts to go hard and it gets hard very
quickly and within an hour or two it is reaching really a substantial
strength. The tunnels no longer need to be circular as they are
for tunnel boring machines. This technique is particularly appropriate
for station construction because it allows stations to be a different
shape from perfectly circular.
368. Slide 18 shows a view of the sprayed concrete
method being used for the Jubilee Line Extension.[51]
This is a tunnel of approximately ten metres in diameter. You
will see that it is being constructed in two halves. The left-hand
half is a sort of egg-shaped tunnel which is constructed first
and there is a temporary central wall here which, when the right-hand
half has been constructed, will be removed thereby completing
the entire tunnel shape.
369. I am going to just take you through a typical
excavation sequence that that previous slide illustrated.[52]
On the left-hand side we have a cross-section which was rather
similar to the photograph in the previous slide. You will see
that temporary central wall that I described. On the right-hand
side we are looking at a longitudinal section, that is if one
was standing to the right of the tunnel, on the left here and
looking towards it, this is in effect what one would see. The
tunnel direction is from left to right. The completed part of
the tunnel is shown in dashed lines here and in white. We are
going to be looking at how the new sections are excavated in the
following slides just to take you through a sequence to give you
a feel for the process.
370. Slide 20 shows that the left-hand top heading
is being excavated, shaded in yellow here, and the sprayed concrete
on the left-hand part here, shown in green, is a part of the permanent
sprayed concrete lining, but the part shown in blue here is that
part of the central wall that is only temporary and will be demolished
fairly soon.[53]
371. The next slide, Slide 21, shows a progression
of this process and now the left-hand bench area is being excavated
down here and there is more sprayed concrete being applied both
on the left-hand side for the permanent lining and on the right-hand
side for the temporary central wall.[54]
372. Slide 23 shows how the process is complete
right down to the bottom and now we have the completed left-hand
half of the tunnel, the egg-shaped tunnel I described earlier
in the photograph, so we have that completed part, that is now
done.[55]
373. If we go to Slide 24 we see the process
begin in a very similar way for the right-hand side.[56]
Again, the first bit is the top heading and that is shown now
as a sort of brown colour and that is being excavated.
374. Slide 25 takes us to the next part down,
which is the right-hand bench part and that is being excavated
as well.[57]
375. Slide 26 completes the process where we
go almost to the bottom.[58]
We are nearly at the point of completing the right-hand tunnel,
Slide 27 will show that.[59]
The central wall that I described, that temporary one, is being
demolished. The bottom part of the right-hand tunnel is being
completed. Slide 28 shows the whole process completed.[60]
So now we have the complete removal of the temporary central wall
and the entire permanent sprayed concrete lining with the large
full-sized tunnel completed. That is a sequence. It illustrates
the versatility of being able to do this kind of tunnelling in
pieces in a very controlled and very satisfactory way.
376. Slide 29 summarises the advantages of sprayed
concrete linings, SCL.[61]
Firstly, it is possible, as I have explained, to excavate large
tunnels in smaller parts. It provides an early application of
support to the ground by means of spraying the concrete immediately
after the ground is excavated. It enables construction of non-circular
tunnels which has many advantages. It also allows construction
of openings between tunnels for passageways and so on. It provides
a means of rapid mobilization of the plant and equipment. It is
a highly mechanised method. The programme and the sequencing has
a flexibility which I hope has been illustrated by that sequence
that I described earlier. There are variations that can be provided
to that which provides a lot of advantages. There is considerable
experience of this technique. It was used widely for the Jubilee
Line Extension, principally at Waterloo and London Bridge Stations
and it was also used on the CTRL, the Channel Tunnel Rail Link.
377. Slide 30 shows diagrammatically other forms
of construction that can also cause settlement other than tunnelling.[62]
The excavation of boxes or circular shafts for stations, tunnel
boring machine launch chambers, tunnel portals, all of those involve
walls supporting the ground and essentially vertical excavation
and there will be some settlement associated with such excavations.
The extent of that settlement will depend on the shape and on
the depth of those excavations. The magnitude of the settlement
is related to the dimensions of those excavations, the stiffness
of the props illustrated in this slide and also on the type of
ground.
378. Slide 31 introduces the damage assessment
process.[63]
This is done in three phases. In the first phase, Phase 1, we
use simple criteria based on predicted settlement and slope at
the ground surface to eliminate buildings which are subjected
to minimal effects. By that we mean any buildings subjected to
settlements of less than ten millimetres are judged to be only
experiencing minimal effect. Ten millimetres is a very small amount
of movement. Phase 2 considers all other buildings. Phase 2 is
a conservative assessment of the potential damage to buildings
through the distortions the buildings might experience based on
"greenfield" displacements. I should explain what we
mean by greenfield. We mean that we ignore the presence of the
building and simply make the prediction of what the ground surface
would do if it were greenfield, in other words, with no buildings
present, and we then subject the building to that kind of movement
and we calculate how much the building might distort. Then we
have a further phase, Phase 3, which would be a detailed assessment
for every building to determine the risk of potential structural
damage and design of protective measures, if they are necessary,
but the important point is Phase 2, which is a screening exercise,
so a lot of buildings are eliminated at Phase 2 and they only
go through to Phase 3 if there is a calculated indication that
that is necessary. All of the experience on the Jubilee Line Extension,
the JLE, has confirmed that the results of the Phase 2 exercise
are conservative, and that is deliberately so.
379. Slide 32 introduces the different damage
risk categories and these are adopted from the very well-known
categories the Building Research Establishment have defined, and
you will see here that there are three categories shown, category
risk damage 0, 1 and 2 down the left-hand side, and the descriptions
relating to each of those categories are "negligible",
"very slight" and "slight".[64]
For each of those three categories of damage, there are descriptions
of the typical damage. These are mainly applicable to masonry
buildings and brick buildings and it is important to appreciate
that the negligible damage category is hairline cracks at the
worst, less than about 0.1mm, so very, very fine indeed. Very
slight, the next category, is fine cracks with typical cracks
up to about 1mm, just about possible to get a fingernail into
the crack. Then the next category above that, slight damage, is
slightly greater. All of these three categories are of potential
aesthetic significance and there is no structural significance.
This is merely an aesthetic appearance and in all cases can be
very easily repaired, and that is a very important point to make.
43 Crossrail Ref: P6, Volume loss-effect of depth
(LINEWD-RJM01-010) Back
44
Crossrail Ref: P6, Volume loss-effect of diameter (LINEWD-RJM01-011) Back
45
Crossrail Ref: P6, Tunnelling Methods-Closed Face Earth Pressure
Balance (EPB) TBM (LINEWD-RJM01-012) Back
46
Crossrail Ref: P6, Pre-cast reinforced concrete segmental lining-Channel
Tunnel Rail Link (LINEWD-RJM01-013) Back
47
Crossrail Ref: P6, Tunnelling Methods-Closed Face Earth Pressure
Balance (EPB) TBM (LINEWD-RJM01-014) Back
48
Crossrail Ref: P6, Pre-cast reinforced concrete segmental lining-Channel
Tunnel Rail Link (LINEWD-RJM01-015) Back
49
Crossrail Ref: P6, Tunnelling Methods-Closed Face Earth Pressure
Balance (EPB) TBM (LINEWD-RJM01-016) Back
50
Crossrail Ref: P6, Tunnelling Methods-Sprayed Concrete Lining
(LINEWD-RJM01-017) Back
51
Crossrail Ref: P6, Tunnelling Methods-Sprayed Concrete Lining
(LINEWD-RJM01-018) Back
52
Crossrail Ref: P6, Tunnelling Methods-Sprayed Concrete Lining
(SCL) Excavation Sequence (LINEWD-RJM01-019) Back
53
Crossrail Ref: P6, Tunnelling Methods- SCL-Excavate left hand
top heading-1m advance (LINEWD-RJM01-020) Back
54
Crossrail Ref: P6, Tunnelling Methods-SCL -Excavate left hand
bench-1m advance (LINEWD-RJM01-021) Back
55
Crossrail Ref: P6, Tunnelling Methods-SCL-Excavate left hand
invert-2m advance (LINEWD-RJM01-023) Back
56
Crossrail Ref: P6, Tunnelling Methods-SCL-Excavate right hand
top heading-1m advance (LINEWD-RJM01-024) Back
57
Crossrail Ref: P6, Tunnelling Methods- SCL-Excavate right hand
bench-1m advance (LINEWD-RJM01-025) Back
58
Crossrail Ref: P6, Tunnelling Methods- SCL-Excavate right hand
top heading and bench-1m advance (LINEWD-RJM01-026) Back
59
Crossrail Ref: P6, Tunnelling Methods- SCL-Demolish temporary
centre wall (LINEWD-RJM01-027) Back
60
Crossrail Ref: P6, Tunnelling Methods- SCL-Excavate left hand
invert-2m advance (LINEWD-RJM01-028) Back
61
Crossrail Ref: P6, Advantages of SCL (LINEWD-RJM01-029) Back
62
Crossrail Ref: P6, Other forms of construction that cause settlement
(LINEWD-RJM01-030) Back
63
Crossrail Ref: P6, Potential damage assessment-3 phases (LINEWD-RJM01-031) Back
64
Crossrail Ref: P6, Definition of Damage Risk Categories-Potential
aesthetic significance only (LINEWD-RJM01-032) Back
|