Examination of Witnesses (Questions 380
- 399)
380. CHAIRMAN: I see that you are referring
to tensile strain here, but what about compressive strain?
(Professor Mair) I was coming to that, thank you for reminding
me. That is a most important point, that masonry is extremely,
as we have known for many centuries, good in compression. Stonework
and brickwork have great strength in compression, but are much
more fragile in tension, so it is tensile strain that is important
in the context of potential damage, so what we do in the assessment
process is calculate the maximum tensile strain that the building
could potentially experience. Depending on the magnitude of that,
we assign it to these different risk categories shown on the slide,
so the tensile strain is an absolutely critical factor because
that is illustrating the potential cracking a building could experience
and that enables us to assign a potential damage category.
381. Slide 33 has higher risk damage categories.[65]
These go, as you will see in the left-hand column, to damage risk
category 3 and damage risk categories 4 and 5. Category 3 is described
as "moderate" and categories 4 and 5 are "severe"
or "very severe", and you will see on the right-hand
side that these correspond to higher magnitudes of tensile strain
than the previous damage categories. These damage categories all
would indicate potential structural damage. The difference between
these and the previous ones is that there could be potential structural
damage as opposed to aesthetic damage, and the important point
to emphasise is that these categories shown on this slidein
other words, categories 3, 4 or 5are not permitted to occur
and that is the fundamental point about this whole staged assessment
procedure.
382. Slide 34 shows an example.[66]
This example is for the Liverpool Street Station area and you
will see what is shown here are predicted settlement contours
at the ground surface and where you see minus 10, for example,
that means that the predicted settlement is 10mm for that particular
contour, and everything outside the yellow area is eliminated
at Phase 1. As I described earlier, if the buildings are assessed
to experience less than 10mm, they are eliminated. Inside the
yellow area, all buildings inside the yellow area proceed to Phase
2 which is the next stage of the assessment process. I think it
is important to emphasise that all of those buildings inside the
yellow area, although they are proceeding to the Phase 2 stage
of the assessment, it does not mean that they will actually experience
significant damage; it is simply taking them to the next stage
of assessment.
383. Slide 35 indicates what we do in the Phase
2 assessment.[67]
This is, I emphasise, a highly exaggerated picture here of a building
undergoing the distortion corresponding to what is predicted for
the greenfield case, as I described earlier, so you have to tunnel
below causing the settlement trough that I described earlier,
and you will see that the building is subjected to two kinds of
movement. There is what we call a `sagging zone' to the right
of the building where, as the name implies, the building is feeling
a sagging kind of deformation, and to the left-hand side it is
going through a `hogging' sort of deformation, and I will say
a bit more about the significance of those two kinds of deformation
in the next slide, slide 36.[68]
The important point to illustrate is that buildings, if they settle
completely uniformly, really are unlikely to experience any damage
because uniform settlement does not lead to any strain. They only
experience strain if they have differential settlement, and that
is illustrated in both these two cases here. On the left-hand
side we see the sagging mode that I just referred to and there
you can see that at the bottom of the wall there tend to be cracks
opening up at the bottom, whereas higher up it is actually in
compression, if you can visualise that brick wall going through
the sagging deformation. Correspondingly, on the other diagram,
you see the reverse happening in the hogging mode, that the compression
is at the bottom of the wall, but the top of the wall is experiencing
the tension, the tensile strain that I described earlier. This
means that the buildings are more prone to damage in the hogging
mode than they are in the sagging mode because there is no restraint
preventing the tensile strain higher up in the wall of the building
in the case of the hogging, whereas in the sagging case the foundations
themselves tend to restrain and restrict the tensile strain that
might be developing close to the bottom of the wall.
384. CHAIRMAN: These are brick buildings,
but what about buildings made of other materials?
(Professor
Mair) The broad principles that I have described would also be
applicable to concrete buildings and most buildings, if they are
old buildings, they are almost certainly brick buildings and masonry,
but, if they are modern buildings, they may well be reinforced
concrete, they may be steel frame, but very often there is brick
cladding or masonry cladding in some form or other, so what I
have described here has a very wide applicability to most buildings
in fact, but it is specifically appropriate for masonry buildings
which form a very large number of the buildings that we would
be considering.
385. Slide 37 shows the results of a Phase 2
assessment.[69]
In the Liverpool Street Station area, it is shown here as an illustration
only and what you see now, as I said earlier, is that all buildings
within the yellow zone were all considered as part of the Phase
2 assessment and the ones shown in the red shaded zone within
that have been identified as needing to proceed to Phase 3. In
other words, the damage category that has been identified as potentially
being possible for those buildings is such that they need to go
to the next phase of assessment where really much more detailed
work is done. It is also worth noting that all listed buildings
and special case buildings with deeper foundations will automatically
proceed to Phase 3 if they are anywhere within the 10mm contour,
so listed buildings have a very special status.
386. Slide 38 summarises the volume loss experiences
on recent tunnelling projects, and you will recall that volume
loss was defined.[70]
This is the same diagram as we saw earlier shown here on the right-hand
side and it represents the total amount of the settlement trough
expressed as a percentage of the total tunnel volume. For earth
pressure balance machines on the Channel Tunnel Rail Link, these
volume losses were typically in the range of 0.5 to 1 per cent.
For the Jubilee Line Extension the same figures applied and also
for the more recent Docklands Light Railway Woolwich extension.
Those figures are applicable for earth pressure balance machine
tunnelling which will be used for all of the running tunnels on
Crossrail between the stations. For spray-concrete linings, the
Jubilee Line Extension experience was that the volume losses were
a little higher, typically between 1 to 1.5 per cent. Now, for
the Crossrail assessments in the Environmental Statement, that
is the assessment of all the potential settlement effects, the
assumed volume losses were 1.7 per cent for all the running tunnels
and 2 per cent for the stations, so you will see that these are
conservative figures used in the Environmental Statement, significantly
higher than almost all of the cases actually experienced on other
tunnelling projects.
387. LORD BROOKE OF ALVERTHORPE: What
was the diameter of the Jubilee Line Extension?
(Professor
Mair) The Jubilee Line Extension running tunnels are typically
5 metres, so smaller than Crossrail.
388. Smaller, but more compression?
(Professor Mair) Certainly smaller, yes. The station tunnels
were much bigger of course, up to 10 metres in diameter. Slide
39 really summarises the general conclusions from the Phase 2
potential damage assessments.[71]
The first point is that for buildings affected by the running
tunnels for Crossrail, the potential damage category is in almost
all cases negligible to slight. For buildings close to shaft sites,
and there are of course a number of shafts planned for Crossrail,
the potential damage category is generally slight, occasionally
some buildings are in the moderate damage category and at the
stations a proportion of the buildings are in the moderate or
indeed the severe potential damage categories and, for those,
Phase 3 assessments will determine the need for protective measures.
I should emphasise that what we are seeing here is that the overall
conclusion is that the buildings near the stations require more
attention than elsewhere, so buildings affected only by the running
tunnels are unlikely to experience any damage of significance.
389. Slide 40 summarises the protective measures
that would be contemplated.[72]
There are really three categories, three quite distinct categories
of protective measures. At-source measures mean that actions can
be taken from within the tunnel or from within the excavation
process to minimise settlements. This is particularly appropriate
for spray-concrete lining kind of tunnelling where there is more
versatility and more opportunity for varying the tunnel process,
but one can actually take measures from within the tunnel to reduce
movements to a minimum. The second category are ground treatment
measures which involve improving or changing the engineering response
of the ground, usually by grouting. Grouting means usually the
injection of liquid cement into the ground either to strengthen
it or to minimise the settlement effects and I will be describing
that a little bit later on. The third category are structural
measures which involve actually increasing the capacity of a building
itself to resist, modify or to accommodate movements, and a typical
example of that would be the use of tie-rods for masonry buildings.
It is not a terribly common measure, but it is sometimes used
and it can be very effective to minimise the tensile strain that
might be induced in a piece of masonry by putting tie-rods in
the masonry.
390. Slide 41 illustrates a ground treatment
measure, a protective measure, known as `compensation grouting'.[73]
This was developed just before the Jubilee Line Extension project
and it was used very extensively on that project with great success.
Its principle is summarised on this slide. If the construction
of a tunnel beneath a building is potentially likely to cause
a severe settlement trough, as illustrated in the red trough here,
then the purpose of compensation grouting is to put a shaft down
into the ground outside and away from the building, this is before
the tunnel is constructed, and from that shaft drilling is done
to insert steel tubes, grouting tubes, into the ground and each
of those tubes are known as `sleeved grouting tubes'. There are
typically holes in each one of those tubes at half-metre centres
and it is then possible to inject liquid cement from any one of
those holes in a very controlled manner, defining precisely the
amount of grout that is injected. The principle is that, when
the tunnel is being constructed, there is very careful measurement
of what is happening to the building, instrumentation is placed
on it, surveying is done, and, depending on the response of the
building, grout is injected from any one of these various tubes
in such a way as to compensate for the movement of the ground
that is being caused by the tunnel construction, hence the name
`compensation grouting'. With this technique, if it is used in
its best way, you can end up with only very slight settlement
of the building as a result of this process, so it is a way of
actually injecting grout and effectively preventing the building
from experiencing the larger settlement that might have occurred
in the absence of this process.
391. Slide 42 illustrates various ways in which
those grout tubes can be installed.[74]
I described in the previous slide how a shaft is put into the
ground and tubes are installed from the shaft, but there are alternative
techniques from much shallower excavations, as shown here, or
indeed from the ground surface itself, as shown on the right-hand
side. There is even the possibility of using existing tunnels
to install these grout tubes, so there are four different ways
here in which those grout tubes can be installed into the ground.
392. Slide 43 gives two photographs of the actual
equipment being used.[75]
The lower photograph shows an operative inside a shaft actually
installing what is called a `packer'. This is pushed right down
through the grouting tube and it may be pushed many tens of metres
to the point of location where the grout needs to be injected
and it is then inflated in such a way that it isolates that particular
injection point and then the grout is injected and it only goes
into the ground from that one hole. It is a very controlled process
and it means that we can very accurately decide which bit of the
ground requires the grouting.
393. Slide 44 illustrates a particularly well-known
site to all of us.[76]
This was the use of compensation grouting to protect the Houses
of Parliament and, in particular, to protect Big Ben, the clock
tower, from leaning during the construction of the Westminster
station for the Jubilee Line Extension which we all know. That
was a very deep excavation and, in addition to the very deep excavation
which went almost 40 metres below the ground surface, there were
also two new platform tunnels constructed along Bridge Street.
Now, the combination of the deep excavation and the platform tunnels
would potentially have caused Big Ben to lean by an amount that
would not have been acceptable, so the process of compensation
grouting was used and a shaft was constructed, a vertical shaft,
in Bridge Street, shown circled here on the right-hand side, and
the left-hand side shows a photograph taken at night of a drilling
rig being lowered into that shaft from which horizontal steel
grout tubes were installed into the ground right beneath the foundations
of Big Ben. Grout was then injected for about a period of 18 months
to two years throughout the construction of the station in response
to very carefully observed readings of what Big Ben was doing,
how much it was moving, and it was a very successful operation.
It was controlled, Big Ben was kept in a suitably vertical position
and the compensation grouting for this project was an excellent
example of how well controlled the process can be. It was also
used for many other buildings on the Jubilee Line Extension, but
I have chosen this one to demonstrate how effective it can be.
394. Slide 45 shows a settlement example of
a building, Elizabeth House.[77]
This a 1960s building, a reinforced concrete frame building. It
is sited along York Way immediately adjacent to Waterloo station.
This is a building which was subjected to a significant amount
of tunnelling for the Jubilee Line Extension beneath it and I
am going to describe what happened to the building and how the
assessment was made. Slide 46 shows a plan view of the building.[78]
Here you will see the building shaded in purple and you will see
the running tunnels for the Jubilee Line Extension shown, but
of particular significance is a crossover tunnel which was sited
right beneath the building which involved much bigger tunnelling
which potentially would have caused, and did cause, more movement.
What we are going to look at is a section through about a 100-metre
length of the building in the next slide, slide 47.[79]
Slide 47 is a plot of settlement shown on the left-hand scale
in tens of millimetres and on the bottom scale over about a 100-metre
length of the building. The green line is the prediction from
the Phase 2 assessment and you will remember that I explained
earlier that, because this was like a station tunnel, in fact
it was a crossover tunnel, the volume loss assumed was 2 per cent,
so the 2 per cent was used for that prediction, and it was predicted
that the building would experience a maximum settlement of 53mm.
Then closer to the start of the actual project, a project prediction
was undertaken and that is shown as the red line, and the project
prediction was in effect the best estimate of what we actually
predicted would happen to the building, so it was using slightly
smaller volume loss figures because, as I said earlier, the 2
per cent used for the Phase 2 assessments is deliberately a conservative
figure. Therefore, the red line represents what we predicted,
our best estimate of what the building would do, and the third
line on the plot, which is the plot with the purple squares, is
the actual observed settlement of the building after all the tunnels
had been completed. You will see that there is, on the whole,
a fairly good agreement between what the building actually did
and our best estimate of what we assessed that the building would
do just before the project began, and the actual maximum settlement
was just a little less than 40mm, as shown here. This building
was predicted by the Phase 2 assessment process to experience
no worse than negligible damage and that in fact proved to be
the case and, despite experiencing nearly 40mm of settlement,
the building experienced no damage of any significance at all.
395. Slide 48 is another kind of building and
I thought this would be appropriate to also show you.[80]
This is a three-storey brick building. This was built in the 1930s
in the East End of London and this was potentially a much more
fragile kind of building, being entirely one of brick, and slide
49 shows a plan view of the building.[81]
The building is Neptune House and you can see Neptune House shown
here shaded purple. One of the tunnels goes right underneath it
and the other tunnel goes to one side of it. The building is about
40 metres long and we are going to look at the whole length of
the building as to how it performed in the next slide, slide 50.[82]
Rather as in the case of Elizabeth House, what we see here is
a comparison of different predictions and comparing that with
what actually happened, so plotted on the left-hand side is the
settlement scale, and you will see here that the settlements are
very much smaller than the settlements we were looking at for
Elizabeth House. This is because the tunnels were running tunnels
using earth pressure balance machines, five metre-diameter tunnels,
and we are looking at the settlement over the entire 40-metre
length of the building. The green line, as before, is the Phase
2 assessment using the volume loss assumption of 1.7 per cent,
and you will see that the maximum settlement predicted there was
about 17mm. The red line is the project prediction; the best estimate
of what the greenfield would be if there were any building there.
That is showing rather smaller settlements using a smaller volume
loss that was actually estimated to be likely to take place. Then
the project prediction of what the building would do is this line
here, this dark blue line, which is a straight line going all
the way across from one end to another. The actual observed performance
of the building is shown as the purple squares which you will
see here, which, again, are very similar, slightly different from
the project prediction for the building. So here is another example,
a very different kind of building from Elizabeth House, of a good
agreement between the project prediction and the actual observed
performance.
396. CHAIRMAN: Did you do any grouting
for that?
(Professor Mair) No, there was no grouting for that because
it was the project prediction and, indeed, the Phase 2 assessment
indicated that it would experience only negligible damage. The
final slide really summarises what I wish to present about ground
settlement and its effects.[83]
Firstly, to say that there is considerable experience in the London
area from the Jubilee Line Extension and, also, from the Channel
Tunnel Rail Link. For both those projects very little building
damage has been reported. I believe I have explained to you the
very robust and, indeed, conservative methodology that is used
for settlement assessment, and that we also have protective measures
that are available. I outlined compensation grouting, particularly,
but the protective measures that are available have been well-proven
and they are very effective. That completes what I wish to present.
397. MS LIEVEN: I just have a couple
of follow-up questions I wanted to ask Professor Mair. First of
all, can you explain the degree to which buildings settle naturally
regardless of tunnelling going on underneath themfor example,
by seasonal factors?
(Professor
Mair) Yes. It is well-known to house owners and, indeed, to insurance
companies that sometimes, depending on where the building is in
the country and what kind of soil it is on, very hot summers can
cause problems. That is because clay soils, in particular, are
sensitive to seasonal changes in moisture content. If there is
a change in moisture content there is an accompanying settlement
or reverse heaving of the soil that takes place. It is well-known
from many measurements that we have taken that buildings can quite
easily experience movements of the order of 10 millimetres just
seasonally from effects such as hot summers followed by wet winters.
398. To some degree, is that something that
should be picked up in the background monitoring that we intend
to do before the works commence?
(Professor Mair) Yes, it is a crucial
part of the monitoring process for a project like Crossrail that
there would be surveying and there would be measurements being
taken well in advance of any actual construction. So one would
have, as you say, background readings for a significant period
before construction starts as to what buildings are doing simply
due to other effects, such as seasonal effects.
399. The other thing I wanted you to expand
on a little bit was when we were looking at slide 40 you talked
about "at source measures" that could be taken to protect
buildings, but that was particularly in the context of spray-concrete
lining. Can you give us a very brief outline of what at source
measures can be taken in respect of the tunnel-boring machine
operation? I think concerns about this were raised in the other
place, so I just want Professor Mair to touch on it.
(Professor Mair) The first point I should,
perhaps, make is that, as I said earlier, all the buildings along
the whole Crossrail project affected by the running tunnels are
likely to experience no worse than negligible or very slight.
So the need to take special additional measures from within the
running tunnel construction is very unlikely. However, to answer
your question, if it was necessary then there are ways in which
the higher pressures can be used at the tunnel's face to minimise
volume loss, and there are established ways of ensuring that.
65 Crossrail Ref: P6, Definition of Damage Risk Categories-Potential
structure damage (LINEWD-RJM01-033) Back
66
Crossrail Ref: P6, Phase 1 settlement contours-Liverpool St Station
(LINEWD-RJM01-034) Back
67
Crossrail Ref: P6, Deformation of a building above a tunnel (LINEWD-RJM01-035) Back
68
Crossrail Ref: P6, Assessment-Deformation Types (LINEWD-RJM01-036) Back
69
Crossrail Ref: P6, Phase 2 Assessment Results-Liverpool St Station
(illustrative only) (LINEWD-RJM01-037) Back
70
Crossrail Ref: P6, Summary of Volume Loss Experience (LINEWD-RJM01-038) Back
71
Crossrail Ref: P6, General conclusions from Phase 2 potential
damage assessments (LINEWD-RJM01-039) Back
72
Crossrail Ref: P6, Protective Measures (LINEWD-RJM01-040) Back
73
Crossrail Ref: P6, Ground Treatment Measures: principles of compensation
grouting (LINEWD-RJM01-041) Back
74
Crossrail Ref: P6, Compensation Grouting: Methods of grout tube
installation (LINEWD-RJM01-042) Back
75
Crossrail Ref: P6, Grout injection equipment (LINEWD-RJM01-043) Back
76
Crossrail Ref: P6, View of Houses of Parliament and compensation
grouting equipment (LINEWD-RJM01-044) Back
77
Crossrail Ref: P6, Settlement Example: Elizabeth House (LINEWD-RJM01-045) Back
78
Crossrail Ref: P6, Location of tunnels and monitoring section
(LINEWD-RJM01-046) Back
79
Crossrail Ref: P6, Elizabeth House: Assessment, Prediction and
Observations (LINEWD-RJM01-047) Back
80
Crossrail Ref: P6, Neptune House (LINEWD-RJM01-048) Back
81
Crossrail Ref: P6, Location of tunnels and monitoring section
(LINEWD-RJM01-049) Back
82
Crossrail Ref: P6, Neptune House: Assessment, Prediction and
Observations (LINEWD-RJM01-050) Back
83
Crossrail Ref: P6, Ground settlement and its effects-Summary
(LINEWD-RJM01-051) Back
|