Select Committee on the Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 1420 - 1439)

  1420. So, if one was looking at it on that qualitative basis that you gave evidence on this morning, it would be comparative with the Forest Gate situation, would it not?
  (Mr Berryman) A similar ratio, yes.

  1421. Looking at the question of the feasibility of undertaking those works that would have to be undertaken, and you gave evidence on that this morning, you are not saying, are you, that it is unfeasible to undertake those works in engineering terms? I think, from what Ms Lieven said yesterday, you never do say that it is unfeasible.
  (Mr Berryman) I never do say that it is unfeasible; it is always a question of how much it costs.

  1422. Indeed, and you have obviously given the evidence of £4 million. Tell me, the £1 million, if I have understood it correctly, would be needed for the lifts themselves? Have I understood that correctly?
  (Mr Berryman) For the actual fabric of the lift, yes, that is £1 million in round figures, but to install lifts obviously involves a lot of things other than the fabric of the lift. You have to build a lift tower, you have to provide power, you have to provide various other bits and pieces that they need, you have to have the foundations for the lift tower and you have to have a landing at the top. The overall cost of just over £4 million includes those elements as well as for the actual lift car and mechanism itself.

  1423. What is the total amount then that is referable to the lifts please?
  (Mr Berryman) Well, it is about a million out of the 4.5 billion.

  1424. I thought it was a million. It is about a million?
  (Mr Berryman) Yes.

  1425. So 3.5 million, then, is referable to the ramp, is that right?
  (Mr Berryman) No. I thought I had just explained a moment ago that the cost of putting lifts in is not just a function of the cost of the car and the lift mechanism; there is also the tower which is needed to support the rails on which the lift runs, there are the foundations for that tower, there is the landing at the top, the provision of power for the lift and various ancillary services required for lifts to deal with things like alarms and so on, which all add to the cost. What I am saying to you is the total cost of doing everything at Maryland to put lifts in would be about £4.5 million, and I do not have a breakdown of that figure as to how much would be the ramp but I would be surprised if the ramp was more than half a million, very surprised.

  1426. CHAIRMAN: It is £4.5 million per lift?
  (Mr Berryman) No, my Lord. £4.5 in total for two lifts plus the ramp.

  1427. BARONESS FOOKES: And all the stuff you need to go with it.
  (Mr Berryman) I do not have the figures to hand but if the ramp is more than a few hundred thousand pounds I would be very surprised.

  1428. MR REED: Let's be clear, that is a cost that is necessarily going to be incurred at any station that has a lift system put in, is that right?
  (Mr Berryman) If it has to have two lifts and a footbridge, yes, that would be the case.

  1429. Because what one is dealing with at Maryland is the simplest situation for dropping a lift down on to the platform?
  (Mr Berryman) No. The simplest situation is where you have an island perform. A good example is at Brentwood where you have one platform with two tracks, one on either side. In those cases you only need to put one lift down. Where you have platforms on either side of the tracks you have to put two lifts down.

  1430. I see. It is the simplest of the two lift situations, can I put it like that?
  (Mr Berryman) Yes, it is.

  1431. Thank you very much. Can we turn now to the question of distance to other stations in the context of Maryland? You, of course, have pointed to the relationship of Stratford to Maryland. First, have you done the walk from Maryland to Stratford?
  (Mr Berryman) No, I have never walked that.

  1432. Have you taken a bus trip from Maryland to Stratford?
  (Mr Berryman) Yes, I have done that.

  1433. Did you do that in the peak hour?
  (Mr Berryman) I do not think so. I cannot quite remember what time of day it was. Probably not in a peak hour.

  1434. Stratford, can we be in agreement please, is an extremely busy station?
  (Mr Berryman) Yes, we can.

  1435. And if we look at slide 019 again, please, we can see the scale of difference between the stations that are there identified and Stratford.[35] It is way off the scale at some 50,800 in the three hour am peak.

  (Mr Berryman) That is right.

  1436. Can we also be clear that there are going to be a good many people coming to this station because of the Olympics?
  (Mr Berryman) Well, assuming that the Olympics takes place in 2012 it will be a long time over by the time anyone comes to use Crossrail or this station, because we do not expect to open until 2017.

  1437. I mean the Olympic Village. I should have been clearer.
  (Mr Berryman) You mean the legacy from the Olympics?

  1438. Correct.
  (Mr Berryman) I see. That is taken into account in those figures. As I say, when we do our modelling we take into account proposed developments in the area of the station as far as we practically can, and in this case it certainly takes into account the new shopping centre that is going to be constructed at Stratford, which is very large, and also what is currently proposed to be the Olympic Village, which will become a residential area, so that is already taken into account.

  1439. Can you tell me, please, whether the fact that Stratford is a busy station, as we agreed, is a relevant matter to take into account when understanding the degree to which it would be an attractive location or mode for the disabled or mobility-restricted?
  (Mr Berryman) It is a relevant consideration but I think it is important to say that the station has been sized to take account of the anticipated passenger flows, and I cannot remember whether I used the bus from Maryland in the peak or the off-peak but I can tell you I have used Stratford station in the peak many times and Stratford bus station in the peak many times, and it copes very well with the already high flows of passengers.



35   Crossrail Ref: P8, 2016 AM Peak 3 Hour Passenger Forecast (Excluding internal interchange movements (NEWMLB-53_04-019) Back


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008