Select Committee on the Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 9740 - 9759)

  9740. Is it your concern to ensure that the introduction of Crossrail services does not disadvantage your rail freight and the growth of rail freight services?
  (Mr Smith) We want a solution that enables the freight services, the Crossrail services and the other passenger services to be accommodated on all the routes in question.

  9741. Can we then move on to the capacity enhancements in the Bill and we are going to come to a number of exhibits dealing with this matter. I think first you have a comment to make generally?
  (Mr Smith) I think the only way, to follow on from my previous statement, that we can ensure that Crossrail services, other passenger services and rail freight can co-exist in the future is through the provision of additional infrastructure to cope with the increased demand for all kinds of rail activity. This is a high level problem that, as a rail industry, we are facing with growth in passenger numbers, the highest for 50 years, the highest level of freight activity at the moment we have had for 30 years and expectations of growth supported and endorsed by government in all sectors. Providing the appropriate infrastructure is the way that growth can be accommodated.

  9742. Can you just tell the Committee briefly about the Acton Yard dive-under?
  (Mr Smith) The Acton Yard dive-under is important. It will be used by Crossrail services travelling to London that will effectively leave the surface and dive underneath a line which will enable freight trains leaving Acton Yard and travelling away from London both to operate without conflict. We were very pleased when the Promoter gave a commitment to provide the Acton Yard dive-under; without it, it would have been a major conflict on that part of the Great Western Main Line.

The Committee suspended from 4.15 pm to 4.26 pm for a Division in the House

  9743. CHAIRMAN: Mr George, shall we see if we can finish Mr Smith's evidence-in-chief this afternoon?

  9744. MR GEORGE: Yes, my Lord. If we could go straight, then, to exhibit 22, that, I think, lifts the totality of the freight works which are included in Schedule 1 of the Bill.[69] Is that right?

  (Mr Smith) In Schedule 1 of the Bill, correct, and, also, in the Environmental Statement which assessed the effects of Crossrail on the basis that these enhancements to the rail network would be constructed. Not only has provision been made by the Promoter in both the Bill and the Environmental Statement for infrastructure works, the timetabling work has also assumed that nearly all of these capacity enhancements will be constructed by the time Crossrail services become operational.

  9745. Just pausing there: their Lordships will be able to see in the right-hand column there that you have explained the position as to whether they were included in the timetable work, and in the case of most of them there is a straight "yes"; in the case of some of them there is a "partially", in which case there is a note at the end of the table dealing with it, and in, I think, just one case a "no" appears. We can see that so far as most of them are concerned, they were in the timetabling, and so far as the five, in effect, of which you are seeking an undertaking, they are all within the category which has been timetabled.
  (Mr Smith) That is correct.

  9746. Can we turn to the position about the ORR?
  (Mr Smith) Yes. During the Bill's passage through the House of Commons, it was made very clear that the Promoter was not prepared to commit to Parliament to undertake the infrastructure works for which powers are being sought. The Promoter did offer one commitment, and that was to build the new dive-under at Acton. The Promoter suggested that the appropriate mechanism for addressing infrastructure requirements would be through the imposition of conditions by the Office of the Rail Regulator, upon the grant of any access option to the Promoter. When we first appeared in the House of Commons, the Promoter's counsel, Nathalie Lieven QC, told the Committee (I am quoting from the transcript here): "If Petitioners, through the Crossrail Bill, remain concerned about access option issues after it has been considered by the ORR then they will have the opportunity to raise that in the House of Lords Committee. I do, therefore, say that it would be both premature and probably pointless to spend time on that at this stage."

  9747. That was Day 51, 11 July 2006, paragraph 14651.
  (Mr Smith) It seems to me that the Promoter's message at that time was this: these infrastructure discussions are for another day. The Committee will appreciate the unfinished nature of these discussions, and this was reflected in the final report of the House of Commons Select Committee at paragraph 141, which says: "We look to the Committee in the House of Lords to ensure that the access option and any other remaining issues relating to the freight industry are adequately evaluated."

  9748. We come on to the ORR's decision.
  (Mr Smith) As the Committee knows, the ORR has now decided to approve the Crossrail track access option. The ORR's approach was not to make the grant of the Crossrail access option conditional upon the construction of specific enhancements to the rail network. Instead, its approach was to focus upon outputs—that is, the number of train paths the network ought to be able to accommodate when Crossrail services became operational. We understand why the ORR has adopted this approach; it is the duty of the ORR to regulate the use of the rail network to ensure that the cake is sliced up fairly, so to speak. The ORR can only ensure each operator is given a portion; it cannot determine the size of the cake itself. That, in this case, is a matter for Parliament, and that is why provision has been made in the Bill for the construction of network improvements.

  9749. Do you see any reason why the Promoter should not be required to construct at least some of the infrastructure works?
  (Mr Smith) I think it is perfectly reasonable to be required to; it is not as if these infrastructure works are only going to benefit one party. When we look at the detail, all the users of the network will benefit from the infrastructure works. I should also make the point, of course, that the capacity enhancements are assumed in the timetabling work that has been carried out. I am referring to the timetabling work done a couple of years ago now, but, also, and more importantly, the more recent timetabling work carried out by Network Rail and relied upon by the ORR in reaching its final decision on the access option.

  9750. What is the latest position so far as train paths are concerned?
  (Mr Smith) Network Rail's performance and systems modelling report that 357 out of the 396 freight paths that were needed by 2017 could be accommodated although, as has been raised a number of times, this could only be done at this stage with a public performance measure of 71 per cent.

  9751. CHAIRMAN: I am sorry, Mr Smith, whose model is that?
  (Mr Smith) This is Network Rail's performance and systems modelling report. Network Rail, effectively, has—

  9752. Submitted to the ORR?
  (Mr Smith) Indeed, yes. Now that the ORR has concluded that the Crossrail off-peak service ought to be reduced, all 396 freight paths ought to be able to be accommodated. But that will only be the case if the capacity enhancements upon which the timetabling work relied are actually constructed.

  9753. MR GEORGE: How long has this timetabling work been going on for?
  (Mr Smith) It seems like forever but it is actually only two-and-a-half years, with at least two different groups convened by the Promoter. This is not a swift process. I think our concern is that the Promoter's unwillingness to commit to construct the infrastructure is only going to result in more and more timetabling runs taking place, with the uncertainty continuing as to whether the paths for all operators—freight, other passenger and Crossrail—will be accommodated on the routes in question. However, if the Promoter agreed to build the infrastructure, or just some of the infrastructure—we are not arguing for all of it, by any means—then this would provide a firm basis upon which to complete the timetabling work; rather than assuming that the capacity and the modifications will be there, we actually know they will be. It just seems to us it would be extremely frustrating and fruitless for the Promoter to realise in nine years' time that the timetabling does not work and that they really ought to have constructed the infrastructure in the first place. I suppose, really, our concern here is the ORR has proposed a mechanism which if, nearer the time, the model were to show that the Crossrail paths and freight paths could not be accommodated, then there are solutions available, but there certainly, by that time, would not be enough time for the infrastructure improvements to be put in place to correct the problems found in nine or ten years' time. Now, we hope that in the circumstances where there was a conflict or there was too much traffic for the capacity available that the decision would be made that the rail industry's freight paths would be retained. However, the ORR has made it very clear that we cannot rely on any freight paths. The ORR goes out of its way, in its final conclusions, to say that the capacity that it is calling "freight" in its conclusion does not belong to the rail freight industry and might not be used for rail freight industry purposes. Indeed, it is possible they could be used for the restoration of the two off-peak paths that have currently been caused by the ORR to be withdrawn. So we have no guarantee that the ORR will hold Crossrail to the decision that has been made. We need some assurances that new infrastructure will be constructed because that way, rather than saying to our customers: "Don't worry, there is an industry model in place, there is an objective test and there are lots of administrative mechanisms to protect your interests", the building of the infrastructure says we can go to our customers now (and operating freight by rail is not something that is done overnight, it is something that requires some planning) and say: "In the future we will be able to operate your services on the Great Western Main Line. Without the commitment on the infrastructure we are left relying on a process that is untested and uncertain. Of course, it is going to be eight or nine years from now before it is put to the test, by which time it is really going to be too late.

  9754. What do you say about the Promoter's argument on flexibility?
  (Mr Smith) Certainly, the Promoter mentions flexibility quite a lot, but what is curious about this is that the Promoter says: "We are not sure about the infrastructure or the design or whether we want this bit here or that bit there", but we have not yet got any evidence to suggest that the infrastructure works which the Promoter is seeking powers for are anything other than absolutely necessary. The Promoter has not identified alternative works, he has not environmentally assessed alternative works. Although we talk about flexibility the only game in town seems to be the infrastructure that is presumed in the Bill.

  9755. Has the Promoter got the power to construct alternative works unless they are within this Bill?
  (Mr Smith) He does not have that power.

  9756. If we then go to exhibit 23, please, I think you have sought to put up a summary, really, of the argument.[70] Perhaps you can quickly take the Committee through EWS 23.

  (Mr Smith) We believe that the current timetabling position produces a very low performance on the network. So, therefore, it is in everybody's interests—in fact, need—to increase the planned performance to 92 per cent to match that which the Government requires for the whole railway anyway by 2014. Therefore, there is going to be a need to increase capacity on the network and on the Great Western Main Line anyway. There are no alternatives. The works in the Bill are, as we say, the only game in town. The Bill has been deposited for three years and no alternative works have been suggested. Nobody has yet said, despite the Bill having been lodged for three years, that any of the works in the Bill, other than the switch of the depot from Romford to Old Oak Common, are unnecessary. There is flexibility in the Bill to vary the works within their limits. The Environmental Statement assumes the work will be constructed. The Environmental Statement has not assessed the effect of a reduction in freight capacity—in fact, the Promoter has said there is no effect on freight. The ORR has come up with a series of novel, clever mechanisms to create assurances for all users of the network. As mechanisms, those do not, in themselves, increase capacity; they merely work out who gets that capacity if there is a problem. So, agreeing and deciding now that some of those infrastructure works should be put in place gives more certainty to the Promoter, to the Petitioners, to the current users of the network and the future users of the network; it reduces the chance of delay to the project and reduces the chance of cost overruns if at the last moment people are having to rush around to do things in an emergency to cover shortfalls in capacity on the network. To repeat the point I made earlier, the ORR's role is to cut the cake. This Committee can make it larger. How is that? Because the role of the ORR is to allocate capacity amongst competing users of railway, whereas this Committee, in its planning permission role, can balance the interests of the Promoter with the private interests effected by the Bill and can ensure that capacity is increased by requiring an undertaking that certain works are committed to be built.

  9757. We then come to Exhibit 24, there are listed the six works which you regard as most important, is that right? [71]

  (Mr Smith) That is correct.

  9758. The first of those is the Acton dive under in respect of which the Promoters have already given an undertaking, which I have already referred to. Can we have on the screen EWS-24.
  (Mr Smith) We looked at the works that are contained in the Bill and we have identified six which we believe are crucial for the capacity for all users of the Great Western Main Line. The first has already been committed to by the Promoter, the Acton dive under that we have discussed before, the others, West Ealing, Southall and Hanwell Bridge, Airport Junction, West Drayton and Iver are the others. Perhaps I should make the point that we are not the only people arguing for the importance of these works; Mr Berryman also presented these works to the Committee on day 21 and spoke to each of them. The paragraph references where Mr Berryman described the benefits of each of these works is in the right-hand column of this exhibit.

  9759. That may be of assistance for doing some cross-checking if your Lordships feel it appropriate. Could we then turn to a brief look at these particular works and could we first of all go to EWS 25.[72] We start with the new West Ealing platform. Could we put that on the screen? I apologise to the Committee that there were two plans which have needed a small revision to them and that is now being handed around, but the revision does not apply to the first couple we are going to look at. It is EWS 25, starting with the new West Ealing platform. Could you talk us through this?

  (Mr Smith) The new platform at West Ealing allows the service from Greenford to terminate at West Ealing. At the moment they travel through to Paddington and take up space on the relief lines in both directions. By going into the platform of West Ealing it creates more space on the relief lines. It is not just for freight services, it is for the Crossrail services as well. Again, this is something which is of benefit to all the users of the route by cutting short a little used service compared with the others in West Ealing and allowing more capacity on the main relief line.



69   Committee Ref: A57, List of Promoter's enhancements (LINEWD-103_05A-004 to -005) Back

70   Committee Ref: A57, Justification for key railway infrastructure works (LINEWD-103_05A-008) Back

71   Committee Ref: A57, Key railway modifications in the Crossrail Bill (LINEWD-103-05A-009) Back

72   Committee Ref: A57, New West Ealing Platform (LINEWD-103-05A-010) Back


 