The Economics of Renewable Energy - Economic Affairs Committee Contents


Memorandum by Mr Colin Gibson

  The author has more than 40 years' experience in the electricity supply industry, including five years as Power Network Director of National Grid Group (1993-97). This post carried responsibilities covering the electricity transmission system of England and Wales for Commercial Development, System Design, Asset Management, and System Operation. The author was General Manager of the generation business of National Grid through the period of privatisation up to his joining the main Board. Prior to this he held various posts in planning, design, and operations in the electricity supply industry in Scotland.

SUMMARY

  The evidence presented proposes that the extra system costs caused by the intermittency of renewables should be for the account of the renewable owners and thus part of the competitive generation market. These system costs occur in both the short-term operational time scale, and in the long term planning time scale. An alternative market structure is suggested which will ensure that long term risk to Security of Supply is contained.

  Whilst the author believes the costs given to be of the correct order, it is more important that the principle be established that all the costs imposed on the system by a development are carried by that developer within the competitive generation market.

1.  FITTING RENEWABLES INTO THE GB SYSTEM

  1.1  GB is essentially an "islanded" system—the only major interconnection is the link to France. This is important since electricity cannot be stored in any meaningful and practical manner on a large scale, so GB must ensure that it can match demand in an operational timescale (frequency control); and match demand in a planning timescale (contain the risk to Security of Supply).

  1.2  Some forms of renewables present problems for both frequency control and Security of Supply risk. Wind farm output is both intermittent and unpredictable: tidal power is intermittent but predictable.

  1.3  The link to France is limited in both capacity (2GW), and by virtue of its being direct current and, therefore, limited in its ability to contribute to frequency control. On the other hand, North America and the European mainland are strongly interconnected over a large land area with varying weather patterns. They are, therefore, better positioned to accommodate a larger proportion of renewables such as wind turbines with intermittent and unpredictable output.

2.  TECHNICAL LIMITS TO RENEWABLE ENERGY

  2.1  In an operational time scale, these limits are dictated by the capability of other operating plant to provide frequency control to compensate for the intermittency of wind. In a planning time scale, the low probability of wind farms generating at the time of system maximum demand would require the construction of `back-up' plant to contain the risk to Security of Supply.

  2.2  The former (frequency control) requires that extra `response and/or reserve' plant is carried on the system. The cost of this (taken to be some £3/MWh of wind output) is not attributed to the wind farm as part of the competitive generation market, but it becomes part of the cost of running a stable system. This cost should be charged to the wind farms.

  2.3  The latter (containing Security of Supply risk) is not recognised in BETTA as a separate requirement, nor is it the responsibility of a particular party. There appears to be an assumption that the market in energy [MWh] will provide sufficient incentive for new plant capacity [MW] to be built to provide the necessary plant planning margin to contain the risk. However, the addition of wind farms, compared to thermal plant, will, because of intermittency, increase the risk. The capital costs of building "back-up" plant (open cycle gas turbines, say) to contain the risk should be, in principle, part of the competitive generation market and charged to the wind farms. These costs could amount to some £20/MWh on the basis that 100MW of wind would have to be supported by 80MW of gas turbines.

  2.4  Initially, the extent to which renewable plant can be connected to the system will be limited by the amount of "response and reserve" and "back-up" plant available and for which the customer is prepared to pay. Ultimately, the large amount of renewables proposed would make the system frequency very difficult and expensive to control. If all these costs were charged to the generator then the market would decide the limits for renewables.

  2.5  An alternative to the provision of "back-up" plant would be to recognise power capacity [MW] as a separate product to be met by competitive tender for long term contracts. Generators would receive fixed annual payments for providing assured capacity at peak demand times effectively covering their capital charges. The greater the generator's confidence of delivering power capacity at times of peak, the greater the proportion of installed capacity it would commit. This arrangement leaves the energy market free to optimise operational costs. Because the capacity payments would be "high quality earnings" and the energy market would be operating more efficiently than at present, the overall costs will be lower, and the Security of Supply risk contained.

3.  TECHNOLOGICAL ADVANCES

  3.1  Given the differences in total costs (see 7 below) it is unlikely that further technological advances will make renewables economically competitive. Other types of generation could also make technological advances thus maintaining the differential.

4.  SUPPORT AND SUBSIDIES

  4.1  Currently, in the main, subsidies to renewables are being provided by the electricity consumer—not by Government. This comprises not only ROCs but also the costs imposed by intermittency and the costs of extra transmission plant if the wind farms are located remotely eg north west Scotland. In a properly competitive market these costs would be met by the wind farm developer.

  4.2  Policy should be directed towards providing a competitive market which is equitable to all types of generation without subsidies and without preferential treatment.

5.  TRANSMISSION NETWORKS

  5.1  The amount of investment in transmission will be dictated by the location of the renwewables. In an endeavour to achieve higher load factors, it is proposed to build wind farms in remote locations and offshore. Building in north west Scotland, for example, will require not only reinforcement of the local system but also reinforcement of the GB system all the way to the south of England. This is evident from examination of National Grid's Seven Year Statement.

  5.2  However, account should be taken of the low load factor of wind farms and their probable output at the time of winter maximum demand in deciding on transmission reinforcement. Therefore, in many cases, justification on technical requirements will not be established, and a decision will need to be made on economic grounds based on "constrained off payments".

6.  EXTERNAL COSTS

  6.1  No comments.

7.  GENERATION COSTS

  7.1  A useful source for these costs is "The Future of Nuclear Power" which uses the concept of "levelised cost". This gives the costs of nuclear, clean coal, and gas generation at around £40/MWh. It gives the costs of offshore and on shore wind as £85/MWh and £55/MWh respectively. However, these wind costs do not appear to include the extra costs of intermittency of wind nor the extra costs of transmission. Also, the specific capital costs for wind farms have increased since the data for this study were collected.

  7.2  The costs for the intermittency of wind generation could add some £25/MWh making the costs of offshore and onshore £100/MWh and £80/MWh respectively. The costs of extra transmission requirements are difficult to calculate but the cost of the Beauly-Denny line alone which was proposed to accommodate about 2GW of wind in north west Scotland would add £8/MWh. Extending this to cover the GB system (see 5.1 above) could easily incur costs of the order of £20/MWh. This would make the total cost of onshore wind generation as seen by the customer about £100/MWh—an increase in cost of £60/MWh compared to a mixture of nuclear, coal, and gas. So, for say 10GW of wind, the extra cost would be £1.6 billion p.a.

  7.3  For the Severn Barrage, the capital charges and operating costs would be some £73/MWh, the cost of containing the risk to Security of Supply some £12/MWh, and extra transmission £3/MWh, giving £88/MWh in total. Because this scheme is predictable (though intermittent), it could make a contribution to stabilising system frequency and voltage, worth say £7/MWh giving a net cost of £81/MWh. To make the scheme competitive with nuclear, coal, or gas, credits for flood control and road usage would have to sum to £40/MWh.

8.  COMPARISONS WITH TRANSPORT AND HEATING

  8.1  No comments.

9.  EU TARGETS

  9.1  No comments.

10.  COSTS OF CARBON

  10.1  The cost comparisons given above include the cost of carbon.

11.  BIOFUELS

  11.1  No comments.

9 June 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008