The Economics of Renewable Energy - Economic Affairs Committee Contents


Annex A

FACTORS INFLUENCING COMPARITIVE COSTS OF RENEWABLE ENERGY

  A1.  Quoted cost estimates for future renewable energy generation vary widely and comparisons can be meaningless unless the costs quoted are based on the same input assumptions. Particularly misleading results can be obtained by comparing the quoted costs of renewables already in commercial production with indicative costs of those still at the research stage.

  A2.  Below we set out the factors that need to be taken into account when estimating future costs of renewable energy technologies. We also discuss the factors influencing the cost of alternatives which are necessary for comparison in a holistic energy policy.

COSTS OF ELECTRICITY OR HEAT FROM RENEWABLE SOURCES

  A3.  Costs of electricity or heat from renewable sources are affected by:

    (a) Capital costs of equipment.

    (b) Other capitalised costs of producing complete working power or heat plant.

    (c) Capital costs of necessary infrastructure to export the power or heat to where it can be used.

    (d) Quality of the primary energy resource being converted into energy or heat.

    (e) In some cases, the cost of providing primary energy resource at the point of use.

    (f) Costs of operation and maintenance.

    (g) Costs of finance and equity return expectations.

    (h) In some cases, costs associated with intermittency of output.

  We explore each of these in turn below:

Capital costs of equipment and construction

  A5.  The capital cost of equipment for energy production depends on a wide and sometimes surprising range of factors. At one level there is variability from site to site (for example different wind farm layouts to suit different landscapes and ground conditions require different expenditures on cable lengths and foundation requirements; different biomass fuel types require different storage, handling, combustion and emission control solutions).

  A6.  However, at least as significant is pricing pressure in global markets for all types of equipment depending on supply and demand balance, and raw materials costs, for example copper and steel prices. At the moment almost all power equipment is supply constrained globally, and we have seen price rises over the last two to three years of 50-100%. In turn this signals investment to increase supply capacity and potentially new entrants to the market, creating the possibility of downward price corrections in the future. It also may cause developers to defer projects in the hope of securing better pricing and availability later.

  A7.  You are therefore likely to be presented with data showing very wide ranges of equipment capital costs. Also the pricing prevalent today is unlikely to represent a long run average price.

Other capitalised costs

  A8.  Other costs associated with building new power plant include land acquisition, environmental and social assessments, permits, engineering costs, legal fees, costs of planning gain, and the internal costs to organisations of having staff devote effort to developing projects. In aggregate these tend to be in the range of 5-20% of the capital costs of equipment and construction, and are proportionally higher for smaller projects, "first of a kind" projects, and projects with unusual characteristics.

Infrastructure capital costs

  A9.  For power plant these costs include the connection to the grid and any necessary reinforcement of the grid necessary to allow the plant's output to be exported to a point of consumption. This can include anything up to major new transmission lines and substations. Infrastructure investment is as complex as power station investment and is subject to many of the same constraints. In particular the costs of gaining planning consent for new transmission lines can be very substantial, and transmission infrastructure costs are highly influenced by global commodity prices (steel, copper, aluminium).

  A10.  Infrastructure costs also vary hugely depending on plant location. At one extreme a wind farm in southern England close to an existing major substation may have very low infrastructure costs, whereas a similar wind farm in northern Scotland may incur infrastructure costs of the same order as the costs of the wind farm itself.

  A11.  For renewable heat the same issues apply, but at a more local scale, as heat degrades in long distance transport. The costs of a district heating network can be substantial, especially if it is to be used to supply existing premises rather than a new development.

Quality of primary energy resource

  A12.  Many renewable technologies harvest a primary energy resource made available free of charge by nature. However the cost of a unit of energy production depends substantially on the extent to which the resource is available to be harvested. This can vary significantly from site to site. For example achieved capacity factors for onshore wind farms range from 10% to 35%.

  A13.  In assessing claimed costs it is important to understand the underlying assumptions used.

Costs of providing the primary energy resource at the point of use

  A14.  Further costs arise where the primary energy resource requires intervention to be made available in a form suitable for use at the power station location. This is a particularly important issue for biomass and waste.

  A15.  Some biomass and waste projects are located adjacent to a ready supply of waste material (eg woodchips from a wood processing plant). Others can be paid to take a feedstock (eg municipal solid waste which would otherwise attract landfill tax). However those which take feedstock from energy crops, or distributed sources of waste, will incur a transport cost (which can be substantial) and may have to compete for alternative uses for the feedstock such as food production, or alternative biomass power plants. There is already substantial import of biomass for power production. It should be noted that individual plants are designed for particular types of biomass—it should not be assumed that a plant designed for woodchips can burn chicken litter for example.

  A16.  Calculating the cost of the delivered feedstock is not only dependent on the particular circumstances of each plant but is also very vulnerable to future supply and demand balances, both locally and internationally. The UK's relatively small land mass means that a heavy dependence on biomass will imply substantial imports. Other countries in Europe and beyond are considering major roles for biomass. Hence in the future costs of feedstock are likely to rise, perhaps substantially. Transport costs are also likely to increase with increasing oil prices, and the transport has its own emissions implications.

Costs of operation and maintenance

  A17.  These costs include staff salaries, overhauls and repairs, rates, insurance and use of grid charges. They vary with technology (eg onshore wind requires almost no staff and limited maintenance, whereas biomass is relatively labour and maintenance intensive). However, for a given technology they are generally reasonably predictable. An exception to this are the offshore technologies, where there is as yet limited experience of long term maintenance and hence less certainty.

Cost of finance and equity return expectations

  A18.  Unit electricity costs vary depending on financing costs, and the return expectations of developers. Both of these depend on the perceived risk of the investment. The risks involved include engineering performance but also perceptions of risk of change in regulatory environment or other uncertainties. For the established technologies these are well established, but less so for new technologies.

Costs associated with intermittency

  A19.  Intermittent technologies such as wind and wave power impose costs on power system operations around the provision of replacement capacity. These costs are negligible when the amount of intermittent generation is small, but could be substantial at levels of intermittent renewables implied by the EU targets for 2020, especially if dedicated power plant has to be provided as back-up. Alternative options such as intelligent load management are developing, these in turn will incur infrastructure costs for control and metering systems. Concentrations of intermittent generation in particular geographic regions, eg Scotland, will also create a need for investment locally to ensure the stability of local and regional grids.

ALTERNATIVES TO RENEWABLE GENERATION

  A20.  When assessing renewable generation costs against other options it is important to understand the uncertainties in:

    —  other generation options; and/or

    —  non-generation options such as demand reduction and energy efficiency.

Alternative Generation Options

  A21.  The alternative generation options are gas and coal fired power plant and, potentially, nuclear energy. All the same issues as for renewable plant affect the cost of providing the physical generation assets. Market pressures worldwide affect pricing in just the same way, over time this will increase supply capacity and may ease pricing. However, barriers to entry are generally higher in the gas, coal and nuclear power plant equipment markets and their responses are likely to be more sluggish, meaning that higher prices may persist for longer. However a large unknown at present is the impact of low cost Chinese plant entering world markets, particular coal fired. This is something that is currently gathering momentum rapidly.

  A22.  The major issue governing cost of alternative generation options however is global fuel prices. Recent oil price increases have been well publicised, and the consensus is that we have entered a prolonged period of much higher oil prices. Gas prices are linked to oil prices through indexation clauses in long term gas supply agreements in Europe, and we can therefore expect a prolonged period of high gas prices. Coal prices are set more globally, and are currently high driven by demand in emerging economies and high oil and gas prices. A major global recession could soften this, but the general picture is of energy becoming much more expensive. However there seems little consensus over how much primary energy prices will increase over a 10, 20 or 50 year horizon.

  A23.  A further uncertainty is carbon price, especially over the long term. To date this has had limited impact; it seems certain this will change, but only limited progress has been made on the international commitments that will give this clarity.

  A24.  This backdrop increases substantially the attractiveness of non-generation options such as demand management and energy efficiency.

Demand Management and Energy Efficiency

  A25.  A whole spectrum of these is available, ranging from home insulation to the redesign of cities to minimise car usage. Many of these options are low cost (even negative cost), but have not proved popular owing to their transaction costs or lifestyle implications.

  A26.  Heavily rising energy prices are likely to change this and it is interesting to speculate on possible consequences. An early sign is the reduction in motoring that seems to have occurred between January 2007 and January 2008.

20 June 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008