Select Committee on European Union Written Evidence


Memorandum by Scottish and Southern Energy

INTRODUCTION

  Scottish and Southern Energy (SSE) is grateful to have this opportunity to submit evidence to the Committee's inquiry into the EU's 20% Renewable Energy Target. SSE is determined to play its part in meeting the renewable targets and, already the largest renewable generator, SSE has an internal company renewable energy objective of 4,000MW set for 2013 in the UK and Ireland. Over £2.5 billion capital investment will be made in renewable energy in UK and Ireland up to 2013, with around £500m equity investment in renewable energy in new markets and technologies in the same period. It is also involved in the generation, supply, transmission and distribution of electricity and in the supply, storage and distribution of gas.

  Looking forward, renewable energy has a vital role to play in delivering secure and low-carbon energy supplies in the UK. Put simply, the benefits of moving to a more renewables based generation portfolio will allow the UK to benefit from reduced greenhouse gas emissions; reduced reliance on energy imports, particularly from unstable regimes; reduced exposure of the energy system to fuel price volatility; and expanded business opportunities right the way along the renewable energy supply chain.

  That said, renewables alone are not the solution to tackling Climate Change sustainably. Politicians, policymakers and others should not underestimate the role that non renewable low carbon generation can play in reducing global emissions, whether through more efficient use of fossil fuels, nuclear new build, or carbon capture and storage. If the world is to tackle Climate Change, all low carbon generation will have to be considered as part of the energy mix.

  It is also vital to stress that overall energy demand reduction will be crucial in tackling Climate Change and meeting European energy targets. Successful demand reduction reduces the overall scope of the challenge.

  In this response, SSE has not responded to every question posed but taken a whole-approach to what the targets mean in practice, the implications for meeting the target and what can be done to resolve the current barriers.

WHAT COULD THE TARGET LOOK LIKE IN PRACTICE?

The UK share of the European target

  To meet its allocated share of the EU renewable energy target, the UK will need to deliver 15% of its energy from renewable sources by 2020.

  An initial high-level assessment, conducted by SSE in partnership with the United Kingdom Business Council for Sustainable Energy (UKBCSE) supports the developing view that this could translate to:

    —  10% heat (an increase of almost 70 TWh from current levels);

    —  10% land transport (an increase of over 45 TWh from current levels); and

    —  up to 40% of electricity from renewable sources (an increase of over 125 TWh from current levels).

Modelling demand and consumption

  For illustrative purposes, SSE has modelled a scenario looking at the impact of the draft Renewables Directive while assuming that energy demand across heat, electricity and transport remains at 2006 levels. While this does not reflect current and future energy demand projections, it provides an insight into the scale of the increase in renewable energy needed to meet the target, and the implications for the supporting infrastructure.

  However, before analysing this information, it is important to understand that the electricity sector may have to deliver more than 40% renewable energy if there is a significant increase in electricity demand; and/or the heat and transport sectors do not realise their renewable energy potential. In addition, as technologies develop, there is likely to be an increased pressure on electricity demand created by the emergence of mains powered electric cars, which would need to be charged up from buildings overnight. In addition, given the lack of any Government policy on incentivising renewable heat, assuming a constant electricity demand and a significant contribution from renewable heat or transport is far from certain.

  Anyway, while assuming a demand level based on 2006 for 2020, the below table shows the breakdown of expected heat, electricity and transport energy consumption by 2020
Consumption (TWh) 20062020 (based on 2006 levels)
Electricity (conventional)375 248
Electricity (renewable)18.78 (4.8%) 145 (36.9%)
Total Electricity393 393
Heat (conventional)730 661
Heat (renewable)4.52 (0.6%) 73.5 (10.0%)
Total Heat735735
Land Transport (conventional)478 432
Other Transport (conventional)173 173
Land transport (renewable) (% of all land transport) 2.09 (0.4%)48 (10.0%)
Total Transport653653
Total Energy (conventional)1,755 1,514
Total Energy (renewable)25 (1.4%) 267 (15.0%)
Total Energy1,7811,781


  This information is displayed below graphically:



Expected renewable electricity mix

  To deliver the target, it is expected that the UK will need to generate a total of around 145 TWh of electricity from renewable sources by 2020, from less than 20 TWh generated in 2006.

  SSE has made a preliminary estimate of the expected technology mix that could make up the renewable electricity component if is delivered entirely in the UK. SSE expects that the bulk of the new renewable electricity generation (around 75%) is likely to come from onshore and offshore wind. This information is displayed graphically below:



  SSE does not expect that the Severn Barrage could be delivered by 2020. However, we understand that demonstrable progress towards delivering the targets will be looked on favourably, so have included it in projections. If the Severn Barrage does not get built, wind will likely fill the gap.

IMPLICATIONS OF DELIVERING THE RENEWABLE ENERGY TARGET

  The above information gives us an idea of where the UK needs to be, but the key is, of course, how to get there, and whether it is possible to get there, and in time. In the following section, SSE addresses the barriers that need to be overcome in order to achieve these targets. However, before doing this it is necessary to stress that without the bulk of the following barriers being overcome, the UK will not reach these targets.

Renewables Obligation

  The Government has a range of initiatives already in place that are making progress in encouraging the uptake of renewable energy. For example, the Renewables Obligation (RO) has successfully underpinned renewable electricity development in the UK, and will continue to be the key support mechanism for onshore and offshore wind energy and biomass projects, and possibly marine projects in due course. SSE is also confident that the RO, with a higher target, and extended time period, will be an effective mechanism to stimulate investment in renewable electricity to 2020 and beyond. However, the key is for Government to refrain from excessive tinkering with the RO, in terms of banding and other parts of its operation. Investor confidence is paramount for this mechanism to work long term.

Planning

  The current planning system takes too long and is applied inconsistently and unpredictably, undermining the UK's ability to address the challenges of security of supply and climate change. While we clearly do not expect a positive decision on all planning projects, we feel it is essential that planning decisions are made in a timely, transparent and accountable manner. With the sheer amount of renewable infrastructure needed to meet the targets, and the fact that wind will be responsible for achieving the bulk of the 2020 targets, the current planning regime is, quite simply, not fit for purpose.

  For example, under the current regime, analysis we have undertaken indicates that a new onshore wind farm could require around 2-3 years of preparatory work, and currently the planning process can take up to 5 years, which will be followed by a further 1-2 years of construction. This does not take into account the time associated with building new transmission infrastructure, which could in parallel take 3-4 years preparation, plus 2-4 years to construct, and again up to 5 years in planning.

  As these indicative timescales show, new renewable projects, and the associated infrastructure, must be initiated in the next year or two in order to make a significant contribution to the 2020 targets. We should not revisit those matters that are already in train through a lengthy consultation process, but ensure that the critical decisions can be made expeditiously.

  It is for the reasons outlined above that SSE has supported the Government's Planning Reform Bill and believe that the Bill's proposed approach is a potentially significant step in the right direction, appropriately balancing concerns over environment, the economy and local communities, while providing the required level of expertise needed for ruling on these complex inquiries through the vehicle of the Infrastructure Planning Commission (IPC).

  The reform package comprises enhanced community engagement; the establishment of an independent Infrastructure Planning Commission to determine all nationally significant infrastructure projects; National Policy Statements setting out the policy framework against which decisions should be made; and simplification of the energy consents and the Town and Country Planning regimes.

  Overall, the proposed system offers a better way of dealing with applications to build key national infrastructure, at a time when we need it most. There are still issues to be ironed out in the Bill, such as the need for end to end timescales for applications, and how the National Policy Statements will be applied in devolved administrations (where much of the renewables capacity will likely be located), but one thing is for certain: if the planning system is not reformed adequately, the UK will not reach its renewable targets.

NETWORK ISSUES AND FLOWS

  Electricity transmission infrastructure will be key to enabling the increased levels of renewable generation estimated throughout this response. Working with the UKBCSE, and the other two GB electricity transmission licensees, SSE has examined the capacity of the existing GB transmission system to accommodate new renewable generation without the construction of new overhead line routes. This is an initial view with just the broadest of assumptions and without undertaking detailed system studies.

  The diagram below is intended to give a general indication of the levels of renewable generation that could be accommodated on the GB transmission system by 2020. It assumes completion of transmission upgrades already in train (eg the Beauly-Denny rebuild and south west Scotland works) as well as completion of those works expected to be achieved without protracted planning issues, eg relatively uncontentious re-conductoring and re-insulation work on existing tower routes, and substation extensions.

Capacity of the Transmission System to Accommodate Renewables



Levels of renewable energy generation that could be accommodated in 2020
Scotland10,000 MW[12]
England and Wales8,300 MW
Total18,300[13]


  There may be scope for this to be higher subject to further examination of generation scenario assumptions in England and Wales. Rounding the indicative figure up to 20 GW for the amount of renewable generation that could be accommodated in 2020 still however highlights a significant shortfall against the likely requirement for some 60 GW of renewable generation derived to meet the 15% overall target.

High level assumptions used in analysis
1. DemandSevern Year Statement user demand data extrapolated out to 2020.
2. Generation Scotland: No contribution from Hunterston or Cockenzie power stations. All other Scottish generation contributory. England and Wales: All contracted generation proceeds and no closures (apart from Magnox nuclear and LCPD opted-out plant)
3. Planning StandardApply current GB SQSS.


  The intention is to give an indication of the potential for the existing GB transmission system in 2020 (ie including upgrades that do not carry a high consenting risk) to accommodate additional renewable generation, and for that number (approximately 20GW) to be set against our estimate of the total volume of renewable generation (some 60GW) that we anticipate will be needed to contribute to meeting the 15% overall target for renewable energy.

  While there is considerable capability in the potentially achievable 2020 transmission system there is still nevertheless a substantial shortfall compared with what would be consistent with the 15% renewable energy target. Detailed and coordinated study work by the three transmission licensees is therefore required to identify appropriate reinforcements to deliver a transmission system capable of accommodating some 60 GW of renewable generation in 2020. In particular this work would quantify the trade-off between more costly offshore transmission capacity versus more onerous barriers to associated with new onshore transmission routes (see indicative unit costs below).

  In short, indications are that with appropriate funding mechanisms to enable the transmission works to progress, and appropriate access and charging arrangements to ensure they are fully utilised, the transmission works in hand should be capable of accommodating some 20GW of renewable generation in 2020. A co-ordinated study by the three transmission licensees should be supported to identify the further optimal reinforcements necessary to accommodate some 60 GW of renewable generation in 2020 and the future funding requirement for those works should be recognised now.

  However, SSE must stress that the consenting and completion of the Beauly-Denny transmission re-build is absolutely key to releasing the upgrade potential of the existing Scottish transmission system. By rebuilding the weakest leg of a north of Scotland transmission ring it allows the other elements of that ring to be re-conductored and re-insulated (ie no new overhead line routes) to increase the capability for renewable generation in the north to some 6.4GW (cf 2.2GW already connected). The reinforced ring facilitates collection of the output from onshore developments and the subsea island links are planned for connection onto the reinforced transmission ring.

Back-up plant and demand response

  By 2020, we will need some changes to the energy system to ensure that it can manage the increased amount of intermittent renewable energy electricity generation. SSE believes that there will be a need for some form of back-up for those times when renewable resources are not available. This could take the form of additional thermal supply capacity, or more innovative approaches such as demand side management, or storage.

  SSE estimates that at 2006 levels of energy demand, a total installed capacity of 130 GW would be needed as against the 76 GW currently installed today. We estimate that 61 GW of renewable energy generating capacity in 2020 would need to be supported by:

    —  around 9 GW of nuclear plant, and 31 GW of thermal plant to meet energy demand; plus

    —  a further 18 GW of capacity to manage intermittency at peak periods; and

    —  a further 10 GW of plant would be needed to provide a 20% plant margin.

  The below diagram illustrates this data:



  The UK currently has around 76 GW of electricity generation capacity, which means that there is currently a healthy plant margin. Over the coming decade, as a result of the Large Combustion Plant Directive, and plants coming to the end of their life, over 22 GW of existing power stations are expected to close by 2020. This could result in a need for 75 GW of new build by 2020.

  The location of the necessary backup plant, and the capacity of the network to allow connection need also to be considered.

The importance of reducing energy demand

  As discussed earlier, the 2020 projections for the amount of renewable energy to be delivered across each sector are highly sensitive to the assumptions made about demand growth.

  Although SSE will not focus on the detail in this submission, the extent to which energy efficiency policies are implemented in the UK will have a significant impact on the amount of renewable energy that will be needed to meet the target. It is worth noting that the biggest opportunity for energy efficiency is in reducing heat consumption, and is less likely to impact on future demand for electricity.

Addressing heat policy could be critical in meeting the targets

  Given that heat is responsible for over 50% of energy usage, compared to electricity being responsible for around 20% of energy usage, for each extra percentage of heat we make from a renewable source, we take 2.5% off the renewable electricity target we need to get to in order to meet our European renewable targets. Given that there is at present no incentive for encouraging renewable heat but there is an Renewables Obligation (RO) for electricity, SSE believes that the Government must take action quickly to change this. While not wedded to a particular solution, SSE sees Government action here as a real opportunity to ensure a fairer share of the burden for heat, in line with that of electricity and transport.

  Making sure that effort is equally distributed across all sectors of the economy is critical to ensuring the most cost efficient solutions are uncovered and to avoid creating market distortions. In the future, the three main energy markets for electricity, heat and transport should become increasingly inter-related. A harmonised approach will be essential to allow loads to shift between these markets. For example if electricity is to play a part in decarbonising the heat and transport sectors it must not be unequally burdened with the cost of carbon mitigation since this will distort this market and potentially prevent this solution from being developed.

MEETING THE TARGETS AND BEYOND

  If the above recommendations are implemented, SSE believes the UK has a fighting chance of reaching its targets. However, it is imperative that Government action is clear, targeted and ambitious. Where there is a need to consult on new areas, it is right that this is done, but it is important that consultations do not cover old ground, particularly if it delays action.

  In the immediate term, we believe that there are a number of measures in train that are critical to delivery of the target, and it is important that the Government maintains a focus on implementing these, such as the new arrangements for the Renewables Obligation, and the current planning reforms.

  SSE, also believes that there are potentially a number of measures that Government could implement expediciously to facilitate progress towards the target. These include:

    —  expanding the end date of the RO beyond 2027 to ensure investor confidence is maintained;

    —  developing clear guidance to Ofgem from Government about facilitating renewable energy development; and

    —  prompt delivery of transmission access reforms, including physical access and dispatch regimes that allow achievement of the renewable energy targets, while maintaining a parallel focus on security of supply.

  A key area of focus must be realising opportunities to encourage timely new investment in the relevant transmission infrastructure.

Emerging issues for further consideration

  This paper provides a very high level assessment of the implications of delivering the renewable energy target in the UK. However, SSE believe it vital that policymakers give full consideration to the following areas:

    —  Ensuring adequate network infrastructure:

      (a)  Transmission.

      (b)  Distribution.

    —  Ensuring the supply chain can deliver.

    —  Ensuring sufficient skills.

    —  Managing and communicating public acceptance of a significant increase of renewables.

    —  The technology, scale and location of peaking plant.

    —  The role of demand side management and storage to balance an increased proportion of intermittent generation.

    —  The availability, cost and sustainability of biofuels.

    —  The use of renewable electricity for heat and transport.

    —  The cost of implementing the renewable energy target for consumers.

    —  The uncertainties around the cost, availability and sustainability of biofuels, and how any shortfall in the biofuels area would be made up across the other sectors.

    —  The range of energy demand projection scenarios looking forward, and the implications for the renewable energy targets, including possible trends for an increased use of electricity for heating and transport.

23 April 2008







12   11,500 MW less 1,500 MW pre-1990 hydro. Back

13   Includes some 2,000MW of existing installed renewable generation capacity connected since 1990. Back


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008