Select Committee on European Union Minutes of Evidence


Supplementary memorandum by E.ON

  1.  The Committee asked for supplementary evidence on the remit of Ofgem and whether this was consistent with delivering the transmission investment needed to support delivery of the EU's renewable targets in the UK.

  2.  The principal objective of the Gas and Electricity Markets Authority (the formal statutory body which governs Ofgem), in carrying out its functions under the Electricity Act 1989, is "to protect the interests of consumers.. , wherever appropriate by promoting effective competition." Consumers include both existing and future consumers.

  3.  The Authority also has to have regard to guidance from the Secretary of State on the attainment of any social or environmental policies, in carrying out its functions under the Act. This guidance has to be laid before both Houses of Parliament before it can be issued. The last guidance was issued in February 2004 and refers to the 2003 Energy White Paper and the policies in existence then.

  4.  Other obligations are also relevant including its duty to contribute to sustainable development and to secure a diverse and viable long-term energy supply.

  5.  We support this approach which gives Ofgem a clear focus on the interests of consumers and helps avoid it having to make judgements about competing energy and environmental policy objectives, which we believe are more appropriately matters for political judgement. This also helps create a regulatory framework where companies operating within it know how the Authority is going to approach regulation. However, in determining how best to protect the interests of consumers, the Authority has to have regard to other social and environmental goals.

  6.  The key question is whether these duties permit the Authority to allow transmission companies to recover through their transmission charges the funding they need to construct the new transmission assets required to facilitate the delivery of the UK's renewable energy targets, where some of this expenditure may be needed before specific projects for connection to the grid have been identified. We believe they do permit this if the right conditions can be met.

  7.  In Great Britain, transmission licensees operate a very "shallow" connection policy which means that most revenue is recovered through Transmission Network Use of System (TNUoS) charges. Only the costs of very local connection assets are recovered through connection charges with the generator concerned. The Authority allows transmission companies to recover revenue through charges if it can be shown that there is a need and that the investment is efficient. This is a valuable discipline to ensure that large amounts of capital expenditure are not committed abortively with customers ultimately carrying the cost.

  8.  At present the transmission companies meet this requirement by building their networks in order to meet the offers for connection that they have made to generators, and do not build strategically to meet a predicted demand for generating capacity, as the Authority does not allow them to recover the relevant revenue on that basis because there is a risk that the need for that capacity might not materialise.

  9.  We see no reason why the Authority's duties would preclude a more strategic approach. The Authority would need to be persuaded that the proposed expenditure would in fact be required to connect the renewable generation needed to meet the EU targets and that the expenditure needed to be committed before some or all of the required renewable generation asked for a connection.

  10.  This should be possible provided there is a clearer understanding of where and when the expected generation would be built than exists at present. Transmission companies should be able to provide this evidence by reference to the Government's own intentions for example to make available areas offshore for renewable development under the "Round 3" Crown Estate leasing process. Although the identity of successful bidders will not be known until later in the process, the sites designated for leasing and the level of generation they can accommodate will be apparent earlier on. The Government's renewable strategy to meet the proposed EU renewable targets to be published in 2009 could provide a more comprehensive basis for such a strategic approach and should go further in identifying the required levels and general locations of renewable investment and the required transmission reinforcement. Reform of the planning system along the lines of the Planning Bill would also assist in providing more predictable timescales for renewable and indeed transmission development.

  11.  This approach would be further supported if the Secretary of State were to issue updated and more specific Social and Environmental Guidance which would refer specifically to the Government's policy for delivery of the EU renewable targets, which the Authority would then have to have regard to in considering the investment requirements of the transmission companies.

May 2008




 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008