Select Committee on European Union Minutes of Evidence


Supplementary memorandum by Centrica

INTRODUCTION

  The Committee has asked for further information on Ofgem's[7] remit with regards to transmission investment necessary to meet the EU's 2020 renewable target. The question is whether Ofgem's remit would require changes to allow transmission owners ("TOs") to take a more strategic approach to network investment.

TRANSMISSION INVESTMENT

  TOs have a statutory duty to build, develop and maintain efficient, co-ordinated and economic networks and to facilitate competition in the generation and supply of electricity. The process of setting the TO allowed revenue means that TOs can only recover cost deemed efficient and economic by Ofgem. Therefore TOs will generally only undertake transmission investment when generators have signed a connection agreement and have made a financial commitment to underwrite the network investments.

  Strategic investment carries the risk of stranded assets because generation projects that were anticipated may not materialise. Stranded assets result in additional costs to TOs or consumers (the former if the investment is not considered efficient and economic).

  Although user commitment is an important principle for avoiding creation of stranded assets, because the network is reactive, it can result in a piecemeal and delayed approach to network reinforcement. This may appear cheaper in the short-term, but may be more costly in the long-term. Because of the long lead time of infrastructure projects, timing of investment is key, in particular when there are only 12 years left to meet the EU's 2020 renewable target.

OFGEM'S REMIT

  Ofgem's primary duty is to protect the interests of consumers, by promoting competition where appropriate and regulating monopolies. In addition to its primary—overriding—duty, Ofgem also has a number of secondary duties, relating to sustainable development, the environment, security of supply and vulnerable customers.

  Part of Ofgem's secondary duty is to have regard to Social and Environmental Guidance ("Guidance") as issued by the Secretary of State.[8] In short this means than when carrying out its duties Ofgem should take into account the social and environmental targets set out in the 2003 Energy White Paper. However, the Guidance is not prescriptive—as the market is said to be best placed to deliver cost effectively the outcomes sought—and does not cover implementation of specific social or environmental measures that would have significant financial implications—as these will be implemented by Ministers.

A CASE FOR CHANGE?

  Centrica is not convinced that a change in Ofgem's remit is required to allow TOs to take a more strategic approach to transmission investment, although a different interpretation of the existing criteria regarding "economic and efficient investment" and "interest of consumers" may be necessary to take account of short-term as well as long-term costs.

  Firstly, the existing framework (TO licences and Ofgem's duties) allows for better co-ordination between TOs and developers. A good example is National Grid's recent initiative to introduce a co-ordinated connection application window for Mid-Wales. This has meant that a group of developers could come forward within a specific timeframe to underwrite the transmission investment which probably would not have happened if individual developers had applied for a connection within different timescales.

  Secondly, we believe that under the existing framework a more strategic approach is already possible by allowing TOs to apply for planning consents and pay for public inquiries before receiving firm commitments from generators. The cost of this preparatory work is small compared to the actual cost of the infrastructure project and is far outweighed by the potential time savings. It should therefore—under certain conditions—be considered economic and efficient and in the interest of consumers.

  Finally, we are not convinced that the existing framework prevents Ofgem from agreeing to actual strategic investments as well as associated preparatory work where there are clear indications that projects will come forward in due course, even if connection agreements have yet to be signed. For example, offshore wind is allocated to specific coastal zones. The Crown Estate has recently released its round three leasing programme which details the size and the location of the next round of offshore wind projects. Potential parties still have to bid for development zones, but as these projects are key to meeting the government's renewable targets they are likely to go ahead and additional network capacity will be required. Clearly under these circumstances strategic network investment will be economic and efficient and in the interest of consumers from both an environmental and a long-term cost perspective though the challenge of minimising costs remains.

  We recognise, however, that Ofgem may be restricted with regards to certain strategic network investment. As mentioned above, under the current Guidance, environmental measures which would have significant implications for consumers or regulated companies will be implemented by Ministers. It is our understanding that the Guidance will be reviewed as part of the Renewable Energy Strategy ("RES") consultation, expected later this month. A final RES document setting out how the EU's 2020 renewable targets will be delivered, is expected to be published in spring 2009. This document could be the basis of strategic network investment to be sanctioned by the government and/or Ofgem.

June 2008


7   Formally the Gas and Electricity Markets Authority, the body that governs Ofgem. Back

8   Social and Environmental Guidance to the Gas and Electricity Markets Authority, DTI, 23 February 2004. Back


 
previous page contents

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008