Select Committee on Public Accounts Fourteenth Report


Conclusions and Recommendations


1.  There is no individual within the Department with full responsibility for ensuring that the Bowman CIP project meets its objectives. In 2006, the Department belatedly appointed a senior officer to act as Senior Responsible Owner. But he lacks the authority and time to effectively discharge this onerous responsibility and is only supported by a small staff. In applying the Senior Responsible Owner concept, the Department should equip those appointed to such challenging positions with the funding, authority and trust to fully discharge their responsibilities in line with the guidance issued by the Office of Government Commerce.

2.  The Department took nine months to approve the revised deal struck with General Dynamics UK in October 2005. Time is money for the Department and its contractors, and delaying delivery of a much needed capability could also cost lives. The Department intends to action the relevant recommendations from its Enabling Acquisition Change review to improve its in-house approvals processes. The Department should also engage the Treasury and other relevant government departments in developing a leaner, more responsive approval process so that decisions can be made in a more timely manner.

3.  The Bowman CIP project timescale was clearly unrealistic, and the inherent complexity and technological challenges were under-estimated. The Department should re-design its scrutiny processes and better align these and its assurance processes so that they are fit to deal with the challenges of modern defence acquisitions and to take into account the culture of over-optimism endemic in much defence procurement.

4.  The vehicle conversion challenge posed by the unexpected variation in the land vehicle fleet could have been predicted if the fleet had been properly surveyed before contracts were placed. The problem was compounded by the absence of good data on vehicle configurations, and the practice, particularly in the army, of modifying vehicles without managing and tracking the modifications. Until the Department obtains adequate standing information on vehicle condition and configuration, it should re-emphasise to Users the importance of maintaining standard configurations wherever possible and should survey representative samples of vehicles before commencing modification work.

5.  Complex new systems such as Bowman CIP are more expensive to support and will require more on-going training than their simpler predecessors. To encourage more serious consideration of Through Life Management issues and better inform future investment decisions, the Department should validate the quality of the key data underpinning decisions on the delivery of through life management capability including measures of financial maturity, and clarity about the capability needed.

6.  Bowman CIP was accepted in service in March 2004 with 27 major provisos that reflect the limited operational capability of the initial system. The Department should only accept that General Dynamics UK has cleared the provisos on the basis of robust trials-based evidence and should not pay any outstanding amounts until it is satisfied that the Armed Services are getting the capability they asked for.

7.  The Department has removed several important capabilities from the existing Bowman CIP programme. The Department has developed plans which it is confident will now deliver the most vital aspects of capability without further delay. The capabilities being delayed, such as the ability to communicate with allies, remain important, not least to reduce the risk of further friendly fire deaths. The Department is confident that, to date, no lives have been lost due to this deferral. It should, within the next year, develop a realistic forward plan to ensure the Armed Forces do not have to forego these capabilities for longer than is absolutely necessary.

8.  In addition to the timescale slippage, the Department has agreed to pay a further £121 million to General Dynamics UK to deliver Bowman CIP, despite a much reduced number of platforms to be converted, and some aspects of the requirement being shuffled to another project. Securing value for money in the long-term will require the Department and General Dynamics UK to work together collaboratively to cost-effectively deliver and sustain the capability required by the Armed Forces. To support this objective, the Department and General Dynamics should regularly assess the strength of their relationship.


 