Select Committee on Environment, Food and Rural Affairs Written Evidence


Memorandum submitted by the River Dene Action Group—Wellesbourne (FL 153)

SUMMARY

  The River Dene Action Group—Wellesbourne represents a group of people in Warwickshire who have suffered major flooding twice in the last nine years.

  This note assumes that many other submissions will have covered the topics of increasing frequency of flooding, and the need for higher budgets to cope with this. We want to raise two issues which may have been given less airtime.

    1.  Cost benefit analysis in planning flood protection.

    The Defra methodology considers the immediate (though discounted) cost of building repairs and contents renewal, but makes no allowance for the consequential losses particularly:—

—  Increased insurance premiums or excesses.

—  Houses becoming unsellable.

    And, although it may be hard to quantify, the cost both financial and emotional of houses being uninhabitable for six months.

    It may be helpful on a day-to-day basis to have practical method for rationing funds, but to have a properly informed discussion about the real nature of the problem and long term solutions, surely we need to understand the full costs.

    2.  The priorities of the Environment Agency.

    Some organisations faced with a crisis in one of their areas of operation would just ask their benefactors for more money: others would look critically at every aspect of what they do and how they do it in order to focus resources where they are needed most. The second of these groups can act in a measured way, or they may simply rob Peter to pay Paul.

    Local observation and anecdote suggest that:

—  Time and money is wasted on trivia.

—  Flood defence budgets have been raided in the past to meet other needs.

  We would be grateful to the committee for examining these issues.

1.  INTRODUCTION

  The river Dene is a tributary of the Avon, joining it just East of Stratford-upon-Avon. Wellesbourne is a large village straddling the river and much of the centre including the affected part is a conservation area. Some buildings are listed.

  It has been flooded twice in the past nine years, affecting about 60 houses—over half of them to a depth of more than 60cms, and 85% to at least 30cms. One third of the homes are occupied by pensioners.

  After the 1998 event, a report by the Environment Agency concluded that it would not be "cost effective" to spend £100K improving the defences to give 1 in 100 year protection, opting instead for repairs to the existing defences coting £24K and providing (allegedly) 1 in 75 year assurance.

  Following the second flood in July 2007, a survey was carried out among the victims, and 46 of the 60 houses were represented (a couple of the houses were vacant and some people had decamped and could not be reached). This has been presented to the Environment Agency, and we understand a copy has been sent to your Committee by Professor Green of FHRC.

  The survey shows that the cost of building repairs is £2.5 million and of replacing contents £1.0 million.

  Six weeks after the flood, only 37% were living in their homes, and only half expected to be back by Christmas.

2.  COST BENEFIT ANALYSIS IN PLANNING LEVELS OF PROTECTION

  We don't presume to nitpick the detailed methodology of cost benefit analysis, but we do ask you to consider the variables which have simply been given no consideration in the models which are used.

  In particular:

2.1  Insurability

  Among our local victims are people who have been told that their insurance renewal will be subject to:

    —  20% excess;

    —  £10,000 excess; and

    —  a report from the Environment Agency on flood prevention.

  And of course many premiums are not yet due for renewal, so the full situation is probably not yet revealed.

2.2  Houses being unsellable

  Two floods in nine years has a devastating effect on the saleability of a house if there is no prospect of improved protection. If a house is hard to insure, it becomes extremely hard to sell.

  Apart from the obvious impact on the indebtedness or net worth of families, this has specific implications for:

    —  people changing jobs and having to move; and

    —  pensioners seeking to downsize or release equity.

  If we assumed a 20% reduction in house values, this would amount to £4.5 million compared to a buildings and contents cost of £3.5 million. In other words, the real cost to individuals is more than double the real cost of reinstating their homes.

2.3  Costs of homelessness

  Many people are still homeless and will not be back by Christmas. Some are in caravans, some with relatives, and some in hotels or rented accommodation. In all we estimate that 500 person months will be spent away from the 60 houses affected.

  The emotional and physical strain for the elderly living in caravans in the winter, or for young families crammed into holiday cottages, though harder to quantify, should also be feature prominently in considering the importance of improved protection.

2.4  Implications for cost benefit analysis

  The cost benefit calculations as they are currently done give only a partial picture of the costs. This may serve a short term purpose in allocating scarce funds between different possible projects, but it fails to provide a true picture of the financial and other pain that flooding brings.

  For better understanding of the longer term needs of the country as extreme weather events become more frequent, don't we need an appreciation of the real costs.

  It might even help deter building in flood plains.

3.  THE PRIORITIES OF THE ENVIRONMENT AGENCY

  We don't want to have a general rant about the EA. The people we have had dealings with since the flood have all been very professional and sympathetic, and we believe they will do their best to get us improved protection. However, a couple of local observations suggest that flood prevention may not always be given the priority it deserves.

3.1    Time and money wasted on trivia

  There is a weir downstream of the village in the middle of farmland close to the sewage works. A footbridge carries a path over it. For safety reasons there are galvanised steel railings around it and across the bridge.

  A few years ago a programme of mowing the surrounding grass was instituted. This serves no useful purpose at all, and could even be said to look ridiculous in an unkempt rural context.

  More recently, several workmen spent more than a week painting the galvanised railings black, and replacing a stile on the bridge with a kissing gate.

  Even more contentiously, they then covered the railings with stainless steel mesh so that when the floods came all the field debris washed up against the mesh forming a dam. The force of the water was such that the railings are now bent.

  If the resources used in this futile enterprise had been spent on maintaining the flood defences, we might not now be writing to you.

Is anyone asking tough questions about avoidable expenditure?

3.2  Raiding the flood defence budget.

  Perhaps it would be more diplomatic to call it re-deployment of resources to meet other more pressing needs, but there is a persistent rumour round here that the floods budget was raided to help sort out the recent farm payments fiasco. The sad thing is that no-one is surprised or shocked.

  Is it true that flood defence drops down the priority list when it is out of the headlines?

The River Dene Action Group—Wellesbourne