Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 120-139)

14 NOVEMBER 2007

DEPARTMENT FOR CULTURE, MEDIA AND SPORT AND OLYMPIC DELIVERY AUTHORITY

  Q120  Mr Curry: You think that is going to happen?

  Mr Higgins: So far we have had a good response. It is not always the tier one or the high level contractors because tier one contractors contract to tier two down to tier six and we have to make sure that the small businesses and their workforce get in. One thing we do have which benefits our site is that it is an incredibly connected site and, therefore, the workforce getting here by public transport and rail is good.

  Q121  Mr Curry: Can I just come back to this remarkable £18 million figure for the original cost for the urban development corporation. I was Minister for Regeneration for a while and, in fact, I suppose I was responsible for some of the development corporations. You have said that the Olympics is the biggest construction project in the Western World practically. I do find it inconceivable that anybody could then postulate a model based on an urban development corporation, it just beggars belief. Had you said you cannot postulate on this because there is no basis for comparison, but to move from that £18 million to where we are, I simply find it Harry Potter-ish really.

  Mr Stephens: It is very clear that was a very significant underestimate. That was the first attempt to put an estimate on these costs at a time when the decisions had not been taken on the delivery structure and it reflects the constant way in which these estimates are updated. That was the first attempt, obviously a very significant underestimate, and within a matter of months that was being revised by the time the bid was successfully won to £160 million.

  Q122  Mr Curry: I understand the explanation and I am sure when it was put forward there must have been some querulous comments in the Department and a few raised eyebrows, but we are clearly not going to get any further on that. The Stadium, you have not got a final end user lined up, have you?

  Mr Higgins: The end owner. It will be publicly owned. It is a publicly owned asset and the land is owned by the LDA.

  Q123  Mr Curry: But you want somebody to do something in it.

  Mr Higgins: We do need multiple use. The key thing with the Stadium going forward is effectively you have to have multiple use. You either have one single tenant privately owned football stadium or you have publicly owned multiple use stadiums and around the world we have seen many examples that these can be effectively established. There is not an international standard athletics track and field facility in London and a city this size needs it. It will have a standard track plus warm-up track, which will be a first. It will also be a facility that can be used for other sports. We have had a number of interests expressed from football through to rugby, and particularly community use. This area of East London is particularly short of community use venues.

  Q124  Mr Curry: For football and rugby the spectators are going to be a very long way away from what is happening, are they not?

  Mr Higgins: The same as they were in Wembley before Wembley was demolished.

  Q125  Mr Curry: So you are still looking for what I used to call some Third Division south team to come and—

  Mr Higgins: There are plenty of examples where this works but we all understand that premiership football sides are incompatible with athletics because they do not want the distance between the edge of the field of play and the seating, and that is understandable.

  Q126  Keith Hill: I would like to explore some of the components of the apparent more than doubling in the projected costs of the development. Let me turn first to this question of taxation. There is a new £836 million but I think you referred, Mr Stephens, to a possible total of £1.2 billion. Why does taxation appear as an additional cost in the budget?

  Mr Stephens: As the Report says, it is a cost to the Games but it is a receipt that returns to the Exchequer, so it is not an additional payment by the taxpayer, if you like. The ODA is actually paying tax, it is liable for VAT and, if it incurs it, it will be liable for corporation tax, but obviously its source of funds is entirely the public sector so it will pay that out of the funds it receives and those will return to the Exchequer.

  Q127  Keith Hill: So about 20% of the apparent increased cost which has so alarmed the newspapers, and possibly taxpayers, is actually an entirely paper transaction?

  Mr Stephens: Yes, that is correct. The increase net of tax is £4.1 billion.

  Q128  Keith Hill: There is evidence of good news, is there not, in these new figures in that I notice the ODA's infrastructure and regeneration budget is down by nothing less than £11 million. Why is that?

  Mr Stephens: That will reflect the latest estimates. Something that is important to understand is that all the time developments are happening, so since this budget has been composed, there have been significant developments with the first major project, the tunnels, completing on time and on budget. We have now got full access to the land on time. We are now able to undertake the full site investigations which are confirming that there are no serious unexpected problems with remediation. Planning applications, which were uncertain at this time, have now been completed. A number of tenders have been received against individual contracts. All the time there are these developments and at successive stages those need to be reflected in the new and revised estimates. On a project of this size and scale within the overall envelope, and we have set the overall envelope at 9.3, it is not a surprise to see individual projects going up or down and we should expect that going forward.

  Q129  Keith Hill: When we look at changes, for example in the infrastructure and regeneration budget, and in the core Olympic costs where there has been a very significant growth in anticipated costs, nevertheless you are saying that these estimates already include calculations about likely rates of inflation, construction cost inflation and you are seeking to take into account other variables which could affect the costs as well. In other words, these estimates that we have here represent your best calculation of the likely costs of the scheme.

  Mr Higgins: I can confirm that the Secretary of State's statement in March of this year, which is reflected in table one which sets out the base budget for the ODA of 5.25, and then with adding the VAT £6.1 billion, was as a result of work that was carried out by the ODA and CLM leading up to March 2007 and now as we report to the Funders Committee in two weeks' time I can confirm the work we have done since then, so nine months further on. We are further on site investigation, tendering for the site, planning is now approved, vacant possession has been achieved and we can confirm that base budget still stands and we are not asking the Funders Committee for any further base budget above that total figure of the 5.25 and the VAT that applies to that. The bottom line general programme contingency, the £2.2 billion, remains unallocated and that will remain unallocated after our Funders Committee at the end of this year.

  Q130  Keith Hill: I notice in that part of the budget we have just been talking about that there is, nevertheless, a £500 million contingency. Have you any idea whether that is going to be spent?

  Mr Higgins: That was announced by the Secretary of State in March and that identified known cost pressures at the time. The statement was in March 2007 and it reflected work that we had done leading up to that statement in partnership with CLM, so it did identify areas where we saw known cost pressures on individual projects, particularly projects which we were starting, so the enabling works, the utilities, the early works on the rail, works at Stratford regional station, so it provided prudent contingencies within those individual projects. Within that overall figure, that figure of £6.1 billion, including VAT, there is project level contingency, so that £500 million was recognising that.

  Q131  Keith Hill: Would I be right in thinking that actually the overall contingency in the programme, which amounts to £2.7 billion, is extremely prudent. It represents 42% of the new budget less contingency, does it not? The NAO itself observes that this is at the higher end of the range for non-standard civil engineering projects set out in Treasury guidance. Why has it been put at such a very high level?

  Mr Higgins: This is a project of a size and scale that has not been achieved before in this country and uniquely to a fixed deadline and, therefore, we think it is a prudent, realistic contingency. We expect part of that contingency to be spent, that is sensible practice. A contingency is not there to be locked in a box and never touched; a contingency is there to be utilised to reduce risk and our biggest risk on this project is time.

  Q132  Keith Hill: You expect some of it to be spent?

  Mr Higgins: Yes.

  Q133  Keith Hill: How much? What proportion?

  Mr Higgins: That is yet to be determined but certainly it is realistic to expect some of the contingency to be spent.

  Mr Stephens: If I may, the only safe assumption is to expect it all to be spent and that would be compatible with the £9.3 billion budget, and it has been set at a prudent but, I believe, realistic level. Obviously we are all working to ensure that, if possible, less is spent, but on a project of this size and complexity we must expect risks to materialise and as they materialise that will result in contingency being transferred from the programme to the ODA budget to ensure that those risks are managed.

  Q134  Keith Hill: I understand that, but we should also be aware, picking up Mr Higgins' point, that there is absolutely no guarantee that the entirety of that £2.7 billion in contingency will be spent.

  Mr Stephens: No.

  Q135  Keith Hill: In other words, if you include the taxation element and the contingency element in these new figures, there is really quite a lot which does not inevitably represent any real increase or any real extra burden on the taxpayer.

  Mr Stephens: You are absolutely right. None of that contingency has been spent as we speak. I think it is prudent and realistic to expect a significant amount of it to be spent on a complex and high risk project of this sort, particularly given the fixed deadline which, as the NAO Report brings out, produces particular risks. We are seeking to manage those, not least by advancing the timetable as much as possible so as to reduce the cost pressures. Whatever is not spent will be returned to the funders but it is realistic to expect a significant amount, if not all of the contingency, to be required.

  Q136  Keith Hill: One final question, and I come back to an issue that has been raised before. You had warnings perhaps about the figure that you put down for the private sector contribution, but why has the private sector contribution to this great national project proved so disappointing?

  Mr Stephens: I think as an overall picture it would be wrong to say that it is disappointing. As we have been explaining, that particular sum does not include a very significant private sector contribution to the Village which is being built and largely funded by the private sector. There is the wider Stratford regeneration multi-billion pound scheme which would not have proceeded at this scale and pace without the Olympics.

  Q137  Keith Hill: Well, I challenge you on that. As a Minister I had direct responsibility for the Thames Gateway and that development and I think that would have gone ahead in any circumstances. I do not think you can count the Stratford development as part of the private sector contribution to this development.

  Mr Stephens: I am not. I am illustrating that around the Park there is the wider public sector contribution. My point was at this scale and pace. There is a very significant wider private sector contribution and they are also making significant contributions to the separate LOCOG budget and this takes no account of true land sales and returns from the private sector in that sense. It is a rather narrow part, as it were, of the private sector contribution of what overall I think is a very significant private sector contribution.

  Chairman: Still, it is extraordinarily low. In a budget of £9 billion, the 100 and something from the private sector is unbelievably low when the buzzword in modern government is supposed to be about public-private partnership. I am staggered. I think that one of your problems is that loads of members of this Committee now are ex-ministers, so you had better be careful what you say, but Mr Mitchell has never been a minister and never wants to be a minister.

  Q138  Mr Mitchell: I do not know about "never wants to". The original low estimate of £4 billion, was that a deliberate attempt to deceive or was it just an accidental by-product of excessive optimism?

  Mr Stephens: Neither, I have to say.

  Q139  Mr Mitchell: Why was it so low then?

  Mr Stephens: This is the first Arup report and then the PwC risk assessment around that first estimate, the cost of the specimen Games, and then the more detailed PwC contribution to the bid document. I think that reflected the degree of expert input provided to it but it also reflected the state of knowledge and developments at the time, a time when it was not certain that the Games would be required in London, the land was not in public ownership and the delivery structures were not in place.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 22 April 2008